Great Ocean Road Coast and Parks Authority has a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for the Apollo Bay Harbour seawall under C26-0068. Buying for Victoria records a 20 July to 21 September 2026 contract period but no award or signing date. The owner says the existing wall protects the slipway, port depot and Fishermen's Co-op building and that its condition creates a material failure risk. The new gravity-block wall is planned on the seaward side of the existing structure around the slipway yard. No cited source yet proves site possession, first marine operation, installed quantities, completion or acceptance.
Project signal
Award in Australia
Current statusBuying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisationSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Harbour seawall renewal and coastal asset protection
Status
Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation / Confirmed
Last checked
8 August 2026
Coverage
Related sectors
Harbour seawall renewal and coastal asset protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Great Ocean Road Coast and Parks Authority
Delivery parties
Maintenance Concepts Pty Ltd - source-reported supplier under C26-0068, Demolition, temporary works, block supply, concrete, fill, geotextile, survey and environmental specialists - not named in the published record
Contract route
Buying for Victoria identifies C26-0068 as a current Construction Contracts record for Seawall, with Maintenance Concepts Pty Ltd, a fixed AUD 896,000 total and a 20 July to 21 September 2026 period. The portal record reviewed does not publish an award date, contract-signing date, tender identifier, bidder field or lower-tier schedule.
Execution window
The state portal records 20 July to 21 September 2026. Those are contract-period fields, not proof of site possession, mobilisation, first shoreline operation, practical completion or acceptance. The owner project page describes Stage 3 detailed design moving into Stage 4 construction, while the later state award establishes the delivery contract but not field progress.
Works package
The owner plans a new seawall on the seaward side of the existing wall around the harbour slipway yard. Its official design section shows a gravity-block wall with a concrete pad, geotextile and fill beside the retained existing structure. The protected assets include the slipway, port depot and Fishermen's Co-op building. The wider Apollo Bay Harbour Redevelopment also covers depot, Co-op, viewing-deck, parking and pedestrian works; those elements are not assigned to C26-0068 by the award record.
Marine interfaces
The package sits on an operating harbour edge between beach, slipway, yard and protected buildings. Critical interfaces include temporary shoreline stability, work beside the retained wall, tidal access, block and concrete placement, geotextile and fill control, slipway continuity, survey, public exclusion and protection of harbour operations. No source reviewed identifies the construction method, marine plant, block quantities, design levels or weather allowances.
Commercial evidence boundary
C26-0068 has a fixed AUD 896,000 total in the state award portal. The owner's AUD 12.61 million figure covers the broader Apollo Bay Harbour Redevelopment and is not the seawall contract value, final account or verified saving. No public record reviewed discloses variations, payment status, named subcontractors, suppliers or final value.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Construction contract
C26-0068 Apollo Bay Harbour Seawall Construction
Named party
Maintenance Concepts Pty Ltd
Status
Confirmed
Source position
Buying for Victoria records a current fixed AUD 896,000 construction contract running from 20 July to 21 September 2026. Source
Planned seawall arrangement
New gravity-block wall seaward of the existing wall
Named party
Great Ocean Road Coast and Parks Authority and Maintenance Concepts Pty Ltd
Status
Confirmed
Source position
The owner page and official design section place the new wall around the slipway yard and show the concrete-pad, geotextile and fill interface. Source
Existing asset condition
Harbour slipway-yard seawall
Named party
Great Ocean Road Coast and Parks Authority
Status
Confirmed
Source position
The owner says its 2025 assessment identified a risk of failure within the next decade and identifies the protected slipway, depot and Co-op building. Source
Wider harbour programme
Apollo Bay Harbour Redevelopment
Named party
Great Ocean Road Coast and Parks Authority
Status
Confirmed
Source position
The owner publishes a separate AUD 12.61 million programme that includes seawall strengthening and other harbour works; the figure is not assigned to C26-0068. Source
Subcontracts and supply chain
Blocks, concrete, geotextile, fill, survey and temporary works
Named party
Maintenance Concepts Pty Ltd and undisclosed specialists
Status
Undisclosed
Source position
The contract and owner pages reviewed identify no lower-tier organization, supplier or package value.
Mobilisation and close-out
Physical start, completion and acceptance
Named party
Great Ocean Road Coast and Parks Authority and Maintenance Concepts Pty Ltd
Status
Not evidenced
Source position
Contract-period dates are published, but no cited record proves site possession, first operation, installed quantities, practical completion or owner acceptance.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
C26-0068 exposes Maintenance Concepts, a fixed AUD 896,000 value and a current contract period; the date is not evidence of award, signing or field mobilisation.
The authority said early enabling works were complete and contractor appointment for the seawall was approaching, while keeping the AUD 12.61 million redevelopment programme broader than this contract.