Project record

Apollo Bay Harbour seawall construction

Participation
Not assessed
Project facts checked

Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

Project sources

Great Ocean Road Coast and Parks Authority has a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for the Apollo Bay Harbour seawall under C26-0068. Buying for Victoria records a 20 July to 21 September 2026 contract period but no award or signing date. The owner says the existing wall protects the slipway, port depot and Fishermen's Co-op building and that its condition creates a material failure risk. The new gravity-block wall is planned on the seaward side of the existing structure around the slipway yard. No cited source yet proves site possession, first marine operation, installed quantities, completion or acceptance.

Existing seawall at Apollo Bay Harbour beside the slipway yard, beach and working harbour edge

Great Ocean Road Coast and Parks Authority; exact existing-condition photograph, not current construction progress

Location

Australia / Asia Pacific

Segment

Harbour seawall renewal and coastal asset protection

Phase

Award / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Harbour seawall renewal and coastal asset protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Great Ocean Road Coast and Parks Authority
Delivery parties
Maintenance Concepts Pty Ltd - source-reported supplier under C26-0068, Demolition, temporary works, block supply, concrete, fill, geotextile, survey and environmental specialists - not named in the published record
Contract route
Buying for Victoria identifies C26-0068 as a current Construction Contracts record for Seawall, with Maintenance Concepts Pty Ltd, a fixed AUD 896,000 total and a 20 July to 21 September 2026 period. The portal record reviewed does not publish an award date, contract-signing date, tender identifier, bidder field or lower-tier schedule.
Execution window
The state portal records 20 July to 21 September 2026. Those are contract-period fields, not proof of site possession, mobilisation, first shoreline operation, practical completion or acceptance. The owner project page describes Stage 3 detailed design moving into Stage 4 construction, while the later state award establishes the delivery contract but not field progress.
Works package
The owner plans a new seawall on the seaward side of the existing wall around the harbour slipway yard. Its official design section shows a gravity-block wall with a concrete pad, geotextile and fill beside the retained existing structure. The protected assets include the slipway, port depot and Fishermen's Co-op building. The wider Apollo Bay Harbour Redevelopment also covers depot, Co-op, viewing-deck, parking and pedestrian works; those elements are not assigned to C26-0068 by the award record.
Marine interfaces
The package sits on an operating harbour edge between beach, slipway, yard and protected buildings. Critical interfaces include temporary shoreline stability, work beside the retained wall, tidal access, block and concrete placement, geotextile and fill control, slipway continuity, survey, public exclusion and protection of harbour operations. No source reviewed identifies the construction method, marine plant, block quantities, design levels or weather allowances.
Commercial evidence boundary
C26-0068 has a fixed AUD 896,000 total in the state award portal. The owner's AUD 12.61 million figure covers the broader Apollo Bay Harbour Redevelopment and is not the seawall contract value, final account or verified saving. No public record reviewed discloses variations, payment status, named subcontractors, suppliers or final value.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Construction contract

C26-0068 Apollo Bay Harbour Seawall Construction

Named party
Maintenance Concepts Pty Ltd
Evidence status
Confirmed
Source position
Buying for Victoria records a current fixed AUD 896,000 construction contract running from 20 July to 21 September 2026. Source
Planned seawall arrangement

New gravity-block wall seaward of the existing wall

Named party
Great Ocean Road Coast and Parks Authority and Maintenance Concepts Pty Ltd
Evidence status
Confirmed
Source position
The owner page and official design section place the new wall around the slipway yard and show the concrete-pad, geotextile and fill interface. Source
Existing asset condition

Harbour slipway-yard seawall

Named party
Great Ocean Road Coast and Parks Authority
Evidence status
Confirmed
Source position
The owner says its 2025 assessment identified a risk of failure within the next decade and identifies the protected slipway, depot and Co-op building. Source
Wider harbour programme

Apollo Bay Harbour Redevelopment

Named party
Great Ocean Road Coast and Parks Authority
Evidence status
Confirmed
Source position
The owner publishes a separate AUD 12.61 million programme that includes seawall strengthening and other harbour works; the figure is not assigned to C26-0068. Source
Subcontracts and supply chain

Blocks, concrete, geotextile, fill, survey and temporary works

Named party
Maintenance Concepts Pty Ltd and undisclosed specialists
Evidence status
Undisclosed
Source position
The contract and owner pages reviewed identify no lower-tier organization, supplier or package value.
Mobilisation and close-out

Physical start, completion and acceptance

Named party
Great Ocean Road Coast and Parks Authority and Maintenance Concepts Pty Ltd
Evidence status
Not evidenced
Source position
Contract-period dates are published, but no cited record proves site possession, first operation, installed quantities, practical completion or owner acceptance.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

State contract period begins in the award record

C26-0068 exposes Maintenance Concepts, a fixed AUD 896,000 value and a current contract period; the date is not evidence of award, signing or field mobilisation.

Source

Owner sets the broader harbour delivery context

The authority said early enabling works were complete and contractor appointment for the seawall was approaching, while keeping the AUD 12.61 million redevelopment programme broader than this contract.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Award or signing date and contract-effectiveness record
  • Site possession, mobilisation and first shoreline operation
  • Gravity-block wall geometry, quantities and design levels
  • Concrete pad, geotextile, fill and retained-wall interface
  • Temporary works, tidal access and slipway continuity
  • Maintenance Concepts delivery team and lower-tier packages
  • Survey, environmental controls and safe public exclusion
  • Variations, final value, practical completion and owner acceptance

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
8 August 2026
Cited sources
4

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 4