Project record

Mus seawall at Car Nicobar

NASA astronaut photograph showing Car Nicobar's complete low-lying coastline and surrounding reef waters

NASA astronaut photograph via Wikimedia Commons; island context only, not construction-progress evidence

Andaman Lakshadweep Harbour Works closed its two-cover EPC recall for 450 metres of seawall and shore protection at Mus on 6 May 2026. The procurement portal still shows evaluation without an award. The ministry's 2026-27 works statement retains the INR 471.3 million sanctioned scheme and a separate INR 421.3 million budget provision, while IIT Madras is listed for PMC services.

Project signal

Tender in India

Current status Recall tender is in post-bid evaluation; no public AOC or named EPC contractor Source confidence Confirmed

Location

India / Asia Pacific

Segment

Coastal infrastructure

Status

Recall tender is in post-bid evaluation; no public AOC or named EPC contractor / Confirmed

Last checked

16 August 2026

Coverage

Related sectors

Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Andaman Lakshadweep Harbour Works (ALHW)
Delivery parties
Indian Institute of Technology Madras - PMC services consultant listed for the 450 m Mus seawall scheme, EPC contractor - no award of contract published by 16 August 2026
Contract route
ALHW published recall tender 2026_ALHW_903743_1 on India's Central Public Procurement Portal as an open, two-cover EPC procurement. The tender required a technical package and separate price bid, carried an INR 6.32 million EMD and 75-day bid validity, and closed on 6 May 2026 after a date extension.
Execution window
The official tender page sets a 457-day works period. With no public AOC, contract date or notice to proceed, there is no evidence-based calendar start or completion date.
Works package
The tender synopsis names 450 metres of seawall and shore protection. The ministry's 2024-25 annual report describes a sanctioned 450-metre shore-protection line with a 150-metre approach and says the intended outcome is to limit land erosion and harbour-basin accumulation. It also records proposed NTCPWC design revalidation after changes in the shore profile. The published synopsis does not show whether the 150-metre approach or the revalidated geometry was carried unchanged into the recalled EPC package.
Marine interfaces
Mus lies on Car Nicobar's exposed coast beside a harbour formed by a 490-metre breakwater and a lee-side jetty. CWPRS recorded shoreline change within the harbour and used numerical modelling to examine the proposed seawall. Wave loading, toe support, graded filters, armour grading, quarry-to-island logistics and temporary access therefore sit on the same delivery path as adjacent-shore erosion or accretion monitoring. The reported change in shore profile makes the final design basis and survey date commercially significant.
Commercial evidence boundary
The INR 431.74 million tender estimate is not an accepted contract price. Separately, the ministry's 2026-27 works statement lists an INR 471.3 million scheme estimate, INR 11.8 million actual expenditure to the end of 2024-25, no probable expenditure during 2025-26 and an INR 421.3 million provision for 2026-27. Those are programme-budget entries rather than evidence of EPC award, physical progress or payment under the recalled tender.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The extended technical-bid opening date passed

ALHW's corrigendum moved technical opening to 12 May. The current portal shows a post-bid workflow but no AOC, so the record remains at tender stage.

Source

The recalled EPC tender closed

The extension moved the bid deadline from 28 April to 6 May. The close does not identify a qualified bidder, accepted price or contractor.

Source

ALHW published the current recall

Tender 2026_ALHW_903743_1 put the 450-metre seawall into a two-cover EPC procurement with an INR 431.74 million estimate and a 457-day works period.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Technical and financial evaluation outcome
  • Award of contract, accepted price and named EPC contractor
  • Formal works commencement and the start date for the 457-day programme
  • Final seawall alignment, cross-section, toe and filter details
  • Treatment of the 150-metre approach road described in the sanctioned scheme
  • Rock source, island logistics, temporary access and marine plant
  • Neighbouring shoreline response, surveys and environmental controls
  • As-built length, owner acceptance and post-monsoon performance

Reporting status

Tender, confirmed confidence

Last checked 16 August 2026 across 9 cited sources. The dated timeline above carries the project events.

Last checked 16 August 2026 Cited sources 9