Andaman Lakshadweep Harbour Works closed its two-cover EPC recall for 450 metres of seawall and shore protection at Mus on 6 May 2026. The procurement portal still shows evaluation without an award. The ministry's 2026-27 works statement retains the INR 471.3 million sanctioned scheme and a separate INR 421.3 million budget provision, while IIT Madras is listed for PMC services.
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Andaman Lakshadweep Harbour Works (ALHW)
Delivery parties
Indian Institute of Technology Madras - PMC services consultant listed for the 450 m Mus seawall scheme, EPC contractor - no award of contract published by 16 August 2026
Contract route
ALHW published recall tender 2026_ALHW_903743_1 on India's Central Public Procurement Portal as an open, two-cover EPC procurement. The tender required a technical package and separate price bid, carried an INR 6.32 million EMD and 75-day bid validity, and closed on 6 May 2026 after a date extension.
Execution window
The official tender page sets a 457-day works period. With no public AOC, contract date or notice to proceed, there is no evidence-based calendar start or completion date.
Works package
The tender synopsis names 450 metres of seawall and shore protection. The ministry's 2024-25 annual report describes a sanctioned 450-metre shore-protection line with a 150-metre approach and says the intended outcome is to limit land erosion and harbour-basin accumulation. It also records proposed NTCPWC design revalidation after changes in the shore profile. The published synopsis does not show whether the 150-metre approach or the revalidated geometry was carried unchanged into the recalled EPC package.
Marine interfaces
Mus lies on Car Nicobar's exposed coast beside a harbour formed by a 490-metre breakwater and a lee-side jetty. CWPRS recorded shoreline change within the harbour and used numerical modelling to examine the proposed seawall. Wave loading, toe support, graded filters, armour grading, quarry-to-island logistics and temporary access therefore sit on the same delivery path as adjacent-shore erosion or accretion monitoring. The reported change in shore profile makes the final design basis and survey date commercially significant.
Commercial evidence boundary
The INR 431.74 million tender estimate is not an accepted contract price. Separately, the ministry's 2026-27 works statement lists an INR 471.3 million scheme estimate, INR 11.8 million actual expenditure to the end of 2024-25, no probable expenditure during 2025-26 and an INR 421.3 million provision for 2026-27. Those are programme-budget entries rather than evidence of EPC award, physical progress or payment under the recalled tender.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.