Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate
Fisheries and Oceans Canada awarded Brian MacGillivary Construction contract 4500057429 for floating-dock works at Pugwash, Nova Scotia. CanadaBuys records a CAD 516,100 total and a four-month term ending 29 March 2024. The package reinstates armour and core stone, dredges the harbour bottom into an existing containment berm, installs floating docks, strongarms, gangways and a continuous concrete retaining wall, and modifies the berm approach. Measured quantities, subcontractors, commissioning and owner acceptance remain unpublished.
IMWO artist's impression of the published Pugwash small craft harbour floating-dock works scope
Canada / Americas
Fishing harbour wharf, dredging and shore protection
Delivery / Confirmed
6 August 2026
Coverage
Fishing harbour wharf, dredging and shore protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCanadaBuys carries 29 March 2024 as the last amendment and end of the four-month term, without a completion certificate, final quantity schedule or operating release.
SourceThe CAD 516,100 award placed dredging, containment, floating access, retaining-wall and berm works under Brian MacGillivary Construction as the integrated prime contractor.
SourceEvidence gap