NSW Public Works awarded Civil Constructions contract CAN-RFT-2012462 for AUD 3,814,475 to replace the failed timber seawall at Kully Bay on the Lake Illawarra edge of Warrawong Parklands. The open tender covers demolition of the existing timber structure, new shoreline rip-rap protection and associated landscaping. Buy NSW records a 4 May to 30 November 2026 contract period, while NSW Planning reported construction underway on 15 May and expects the new seawall by the end of 2026. The NSW Government's separate AUD 5 million investment is a programme funding figure, not the contract value or final expenditure.
Project signal
Construction in Australia
Current statusCivil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidenceSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Foreshore seawall and rip-rap protection
Status
Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence / Confirmed
Last checked
5 August 2026
Coverage
Related sectors
Foreshore seawall and rip-rap protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
NSW Department of Planning, Housing and Infrastructure, with procurement managed by NSW Public Works
Delivery parties
Civil Constructions - source-reported contractor under CAN-RFT-2012462 at AUD 3,814,475, Demolition, rock supply, landscaping, ecological, survey and other specialist subcontractors - not named in the published contract record
Contract route
NSW Public Works published open RFT-2012462 on 16 February 2026 under a two-envelope process with a mandatory site meeting. Tenders closed on 17 March. The contract-award notice records Civil Constructions, AUD 3,814,475, a 4 May 2026 start and 30 November 2026 end, and was published on 12 May 2026.
Execution window
The tender estimated 32 weeks. The award record runs from 4 May to 30 November 2026, and NSW Planning says the seawall is expected by the end of 2026. Construction was officially reported underway on 15 May. These schedule dates do not establish practical completion, environmental close-out, public reopening or owner acceptance.
Works package
The awarded physical scope is bounded to demolition of the existing timber seawall, construction of new shoreline rip-rap protection and associated landscaping. NSW Planning describes an environmentally sensitive seawall intended to restore northern-foreshore access, support marine habitat and improve resilience to erosion and storm impacts. The master plan records the existing timber structure, walkway and adjacent slab as partially collapsed and structurally unsafe, but its wider park amenities remain outside the contract boundary unless separately evidenced.
Marine interfaces
The work sits on the northern Lake Illawarra foreshore at Kully Bay and joins shoreline demolition, rip-rap placement, erosion and storm resilience, tidal or lake-edge access, public exclusion, habitat-sensitive design and landscape reinstatement. The award notice does not disclose rock source and grading, temporary water controls, marine plant, survey baseline, contamination handling, ecological hold points, detailed quantities or public-reopening criteria.
Commercial evidence boundary
The public award exposes AUD 3,814,475 of contracted seawall work to Civil Constructions. The AUD 5 million NSW Government investment is a separate funding envelope and cannot be used as the contract price, final account or saving. No public schedule identifies subcontractors, rock suppliers, landscape trades, variations, certified expenditure or final value.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Owner and funding
Warrawong Parklands Kully Bay seawall
Named party
NSW Department of Planning, Housing and Infrastructure and NSW Public Works
Status
Confirmed
Source position
NSW Planning records a separate AUD 5 million government investment for the seawall and safe northern-foreshore access. Source
Construction award
CAN-RFT-2012462 seawall reconstruction
Named party
Civil Constructions
Status
Confirmed
Source position
Buy NSW records the source-reported contractor, AUD 3,814,475 value and 4 May to 30 November 2026 contract period. Source
Physical scope
Timber seawall demolition, rip-rap protection and landscaping
Named party
NSW Public Works and Civil Constructions
Status
Confirmed
Source position
The open RFT defines replacement of the failed structure through demolition, shoreline rip-rap protection and associated landscaping. Source
Construction progress
Kully Bay seawall field works
Named party
NSW Planning and Civil Constructions
Status
Confirmed
Source position
NSW Planning reported construction underway on 15 May 2026 and described the seawall as the first major Warrawong Parklands delivery milestone. Source
Existing condition
Failed timber seawall, walkway and adjacent slab
Named party
NSW Department of Planning, Housing and Infrastructure
Status
Confirmed
Source position
The official master plan says wave action and borer infestation caused structural failure, partial collapse, adjacent slab damage and closure of the unsafe area. Source
Subcontracts and supply chain
Rock, demolition, landscaping, ecology, survey and temporary works
Named party
Civil Constructions and undisclosed specialists
Status
Undisclosed
Source position
The owner, tender and award sources name the contractor but no lower-tier delivery parties or suppliers.
Completion and reopening
Practical completion, acceptance and safe public access
Named party
NSW Planning, NSW Public Works and Civil Constructions
Status
Not evidenced
Source position
The contract and owner publish November and year-end targets, but no completion certificate, acceptance record, final account or reopening notice has been located.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The project moved beyond award into physical shoreline delivery, while installed quantities, completion, owner acceptance and public reopening remain open.
The two-envelope procurement closed after four addenda covering contract conditions, RFIs, landscape drawings, survey files, and geotechnical and environmental material.
The tender established the timber-demolition, shoreline rip-rap and associated landscaping baseline, together with a 32-week estimated delivery period.