Project record

Warrawong Parklands Kully Bay seawall reconstruction

Temporary props supporting the failed underside of the existing timber structure at the Kully Bay seawall beside Lake Illawarra

NSW Department of Planning, Housing and Infrastructure, Warrawong Parklands Master Plan page 56; existing-condition evidence, not current construction progress

NSW Public Works awarded Civil Constructions contract CAN-RFT-2012462 for AUD 3,814,475 to replace the failed timber seawall at Kully Bay on the Lake Illawarra edge of Warrawong Parklands. The open tender covers demolition of the existing timber structure, new shoreline rip-rap protection and associated landscaping. Buy NSW records a 4 May to 30 November 2026 contract period, while NSW Planning reported construction underway on 15 May and expects the new seawall by the end of 2026. The NSW Government's separate AUD 5 million investment is a programme funding figure, not the contract value or final expenditure.

Project signal

Construction in Australia

Current status Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence Source confidence Confirmed

Location

Australia / Asia Pacific

Segment

Foreshore seawall and rip-rap protection

Status

Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence / Confirmed

Last checked

5 August 2026

Coverage

Related sectors

Foreshore seawall and rip-rap protection is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
NSW Department of Planning, Housing and Infrastructure, with procurement managed by NSW Public Works
Delivery parties
Civil Constructions - source-reported contractor under CAN-RFT-2012462 at AUD 3,814,475, Demolition, rock supply, landscaping, ecological, survey and other specialist subcontractors - not named in the published contract record
Contract route
NSW Public Works published open RFT-2012462 on 16 February 2026 under a two-envelope process with a mandatory site meeting. Tenders closed on 17 March. The contract-award notice records Civil Constructions, AUD 3,814,475, a 4 May 2026 start and 30 November 2026 end, and was published on 12 May 2026.
Execution window
The tender estimated 32 weeks. The award record runs from 4 May to 30 November 2026, and NSW Planning says the seawall is expected by the end of 2026. Construction was officially reported underway on 15 May. These schedule dates do not establish practical completion, environmental close-out, public reopening or owner acceptance.
Works package
The awarded physical scope is bounded to demolition of the existing timber seawall, construction of new shoreline rip-rap protection and associated landscaping. NSW Planning describes an environmentally sensitive seawall intended to restore northern-foreshore access, support marine habitat and improve resilience to erosion and storm impacts. The master plan records the existing timber structure, walkway and adjacent slab as partially collapsed and structurally unsafe, but its wider park amenities remain outside the contract boundary unless separately evidenced.
Marine interfaces
The work sits on the northern Lake Illawarra foreshore at Kully Bay and joins shoreline demolition, rip-rap placement, erosion and storm resilience, tidal or lake-edge access, public exclusion, habitat-sensitive design and landscape reinstatement. The award notice does not disclose rock source and grading, temporary water controls, marine plant, survey baseline, contamination handling, ecological hold points, detailed quantities or public-reopening criteria.
Commercial evidence boundary
The public award exposes AUD 3,814,475 of contracted seawall work to Civil Constructions. The AUD 5 million NSW Government investment is a separate funding envelope and cannot be used as the contract price, final account or saving. No public schedule identifies subcontractors, rock suppliers, landscape trades, variations, certified expenditure or final value.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Owner and funding

Warrawong Parklands Kully Bay seawall

Named party
NSW Department of Planning, Housing and Infrastructure and NSW Public Works
Status
Confirmed
Source position
NSW Planning records a separate AUD 5 million government investment for the seawall and safe northern-foreshore access. Source
Construction award

CAN-RFT-2012462 seawall reconstruction

Named party
Civil Constructions
Status
Confirmed
Source position
Buy NSW records the source-reported contractor, AUD 3,814,475 value and 4 May to 30 November 2026 contract period. Source
Physical scope

Timber seawall demolition, rip-rap protection and landscaping

Named party
NSW Public Works and Civil Constructions
Status
Confirmed
Source position
The open RFT defines replacement of the failed structure through demolition, shoreline rip-rap protection and associated landscaping. Source
Construction progress

Kully Bay seawall field works

Named party
NSW Planning and Civil Constructions
Status
Confirmed
Source position
NSW Planning reported construction underway on 15 May 2026 and described the seawall as the first major Warrawong Parklands delivery milestone. Source
Existing condition

Failed timber seawall, walkway and adjacent slab

Named party
NSW Department of Planning, Housing and Infrastructure
Status
Confirmed
Source position
The official master plan says wave action and borer infestation caused structural failure, partial collapse, adjacent slab damage and closure of the unsafe area. Source
Subcontracts and supply chain

Rock, demolition, landscaping, ecology, survey and temporary works

Named party
Civil Constructions and undisclosed specialists
Status
Undisclosed
Source position
The owner, tender and award sources name the contractor but no lower-tier delivery parties or suppliers.
Completion and reopening

Practical completion, acceptance and safe public access

Named party
NSW Planning, NSW Public Works and Civil Constructions
Status
Not evidenced
Source position
The contract and owner publish November and year-end targets, but no completion certificate, acceptance record, final account or reopening notice has been located.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

NSW Planning confirmed construction underway

The project moved beyond award into physical shoreline delivery, while installed quantities, completion, owner acceptance and public reopening remain open.

Source

Contract award notice published

Buy NSW identified Civil Constructions, the AUD 3,814,475 value and the 4 May to 30 November contract period.

Source

Open seawall tender closed

The two-envelope procurement closed after four addenda covering contract conditions, RFIs, landscape drawings, survey files, and geotechnical and environmental material.

Source

NSW Public Works opened the seawall RFT

The tender established the timber-demolition, shoreline rip-rap and associated landscaping baseline, together with a 32-week estimated delivery period.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Civil Constructions legal entity identity and project-specific delivery team
  • Demolition sequence and temporary lake-edge protection
  • Rip-rap source, grading, placed quantity and as-built profile
  • Habitat-sensitive features and ecological inspection hold points
  • Landscape reinstatement and public-access interface
  • Survey, environmental close-out and defects status
  • Contract variations, certified final value and payment close-out
  • Practical completion, owner acceptance and promenade reopening

Reporting status

Construction, confirmed confidence

Last checked 5 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 5 August 2026 Cited sources 5

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 5