WACA ResIP 1 is in its final delivery phase across six countries, but its civil works do not form one regional construction contract. Côte d'Ivoire's Grand-Lahou works, Senegal's Gorée protection, and country packages in Benin, Mauritania, São Tomé and Príncipe, and Togo carry different scope, schedule, environmental, social, and acceptance conditions. ResIP 2 and the 2026 WACA+ programme are follow-on frameworks and are not evidence that ResIP 1 packages are complete or re-awarded.
Benin / Côte d'Ivoire / Mauritania / São Tomé and Príncipe / Senegal / Togo / Africa
Segment
Coastal infrastructure
Phase
Construction / Confirmed
Last checked
17 July 2026
Coverage
Related sectors
Coastal infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Participating governments and implementing agencies in Benin, Côte d'Ivoire, Mauritania, São Tomé and Príncipe, Senegal, and Togo
Delivery parties
Country and package contractors are not consolidated in the reviewed regional restructuring records
Contract route
World Bank regional investment financing implemented through country project units and separate country-level civil-works, consulting, environmental, and community packages
Execution window
ResIP 1 is in finalisation, but there is no single valid regional completion date for every work front. The May 2025 restructuring paper extended Côte d'Ivoire and Senegal to June 2026. A June 2026 Senegal additional-financing paper then proposed a further 12-month extension to 30 June 2027 without changing Senegal's scope. Country dates must therefore be controlled against the relevant restructuring or financing record.
Works package
Multi-country erosion and flood-risk reduction through coastal protection, lagoon and waterway works, quays, dikes, rockfill, drainage, landscape management, ecosystem restoration, monitoring systems, and institutional measures. The record is a programme map, not a substitute for country package definitions.
Marine interfaces
Lagoon dredging, inlet and barrier management, rock and dike protection, quays at Braffédon, Singapour, and Lahou Kpanda, Gorée Island coastal structures, coastal drainage, live-community access, sediment behaviour, sea-state work windows, and heritage and environmental controls vary by country and site.
Commercial evidence boundary
ResIP 1 comprises multiple country packages and financing decisions, not a single cross-border tender or one contractor award. Senegal's additional-financing request reflects cost and schedule pressure on existing scope; it is not evidence of a new regional marine contract. ResIP 2 and WACA+ create separate future opportunity lanes whose finance and scope must not be attributed to ResIP 1.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The additional-financing paper linked the delay to sea conditions, supply constraints, inflation, and heritage-site design changes, then proposed a 30 June 2027 closing date. That date remains a financing proposal, not a completion record for Gorée or the wider programme.
The World Bank launched WACA+ as a separate programme
The first WACA+ financing covers new work in Benin and Mauritania. It opens a follow-on pipeline but does not extend every ResIP 1 contract or change the status of the six-country work fronts already under delivery.
The regional steering committee put ResIP 1 in its final phase
The update separated ResIP 1 close-out from ResIP 2 expansion into The Gambia, Ghana, and Guinea-Bissau. Each country still needs its own civil-works, safeguards, and acceptance record.
The World Bank revised the Côte d'Ivoire and Senegal timelines
The restructuring paper recorded delays and moved both country programmes to June 2026. It did not create one regional construction schedule: Grand-Lahou, Gorée, and the other work fronts remain separate packages.