WACA ResIP 1 is in its final delivery phase across six countries, but its civil works do not form one regional construction contract. Côte d'Ivoire's Grand-Lahou works, Senegal's Gorée protection, and country packages in Benin, Mauritania, São Tomé and Príncipe, and Togo carry different scope, schedule, environmental, social, and acceptance conditions. ResIP 2 and the 2026 WACA+ programme are follow-on frameworks and are not evidence that ResIP 1 packages are complete or re-awarded.
Project signal
Construction in West Africa
Use the regional record to locate country work fronts, then move to country-level owner, lender, procurement, contractor, survey, and acceptance evidence before assigning award, construction, or completion status. Do not aggregate finance, progress, quantities, contractors, or closing dates across the six countries.
Current statusResIP 1 in finalisation; country work fronts and closing dates remain separateSource confidenceConfirmed
Location
West Africa / Africa
Segment
Coastal infrastructure
Status
ResIP 1 in finalisation; country work fronts and closing dates remain separate / Confirmed
Evidence reviewed
17 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Participating governments and implementing agencies in Benin, Côte d'Ivoire, Mauritania, São Tomé and Príncipe, Senegal, and Togo
Delivery parties
Country and package contractors are not consolidated in the reviewed regional restructuring records
Contract route
World Bank regional investment financing implemented through country project units and separate country-level civil-works, consulting, environmental, and community packages
Execution window
ResIP 1 is in finalisation, but there is no single valid regional completion date for every work front. The May 2025 restructuring paper extended Côte d'Ivoire and Senegal to June 2026. A June 2026 Senegal additional-financing paper then proposed a further 12-month extension to 30 June 2027 without changing Senegal's scope. Country dates must therefore be controlled against the relevant restructuring or financing record.
Works package
Multi-country erosion and flood-risk reduction through coastal protection, lagoon and waterway works, quays, dikes, rockfill, drainage, landscape management, ecosystem restoration, monitoring systems, and institutional measures. The record is a programme map, not a substitute for country package definitions.
Marine interfaces
Lagoon dredging, inlet and barrier management, rock and dike protection, quays at Braffédon, Singapour, and Lahou Kpanda, Gorée Island coastal structures, coastal drainage, live-community access, sediment behaviour, sea-state work windows, and heritage and environmental controls vary by country and site.
Commercial read
ResIP 1 comprises multiple country packages and financing decisions, not a single cross-border tender or one contractor award. Senegal's additional-financing request reflects cost and schedule pressure on existing scope; it is not evidence of a new regional marine contract. ResIP 2 and WACA+ create separate future opportunity lanes whose finance and scope must not be attributed to ResIP 1.
Next milestone
Track country-level financing effectiveness, revised closing dates, outstanding contract scope, sea-state work windows, physical completion, environmental and social close-out, as-built and acceptance records, and the handover boundary between ResIP 1, ResIP 2, and WACA+.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Senegal sought more time for the Gorée works
The additional-financing paper linked the delay to sea conditions, supply constraints, inflation, and heritage-site design changes, then proposed a 30 June 2027 closing date. That date remains a financing proposal, not a completion record for Gorée or the wider programme.
The World Bank launched WACA+ as a separate programme
The first WACA+ financing covers new work in Benin and Mauritania. It opens a follow-on pipeline but does not extend every ResIP 1 contract or change the status of the six-country work fronts already under delivery.
The regional steering committee put ResIP 1 in its final phase
The update separated ResIP 1 close-out from ResIP 2 expansion into The Gambia, Ghana, and Guinea-Bissau. Each country still needs its own civil-works, safeguards, and acceptance record.
The World Bank revised the Côte d'Ivoire and Senegal timelines
The restructuring paper recorded delays and moved both country programmes to June 2026. It did not create one regional construction schedule: Grand-Lahou, Gorée, and the other work fronts remain separate packages.
Track country-level financing effectiveness, revised closing dates, outstanding contract scope, sea-state work windows, physical completion, environmental and social close-out, as-built and acceptance records, and the handover boundary between ResIP 1, ResIP 2, and WACA+.
Decision watchpoints
Country-specific closing dates and financing effectiveness
Grand-Lahou and Gorée contractor programmes and sea-state work windows
Lagoon, inlet, barrier, quay, dike, rockfill, drainage, and promenade acceptance by site
Sediment, erosion, flood, heritage, environmental, and community-access controls
Environmental and social action close-out rather than civil completion alone
As-built surveys, owner acceptance, and maintenance responsibility
Clear handover boundaries between ResIP 1, ResIP 2, and WACA+
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed17 July 2026Sources in this record5
Source record
World Bank restructuring records define ResIP 1 as a six-country programme and identify country-specific work fronts, including lagoon dredging, barrier protection, quays, dikes, rockfill, drainage, and landscape management. The May 2025 paper recorded delays and revised completion paths in Côte d'Ivoire and Senegal. The June 2026 Senegal additional-financing paper is later evidence for Gorée: it attributes cost overruns and delays to sea conditions, supply constraints, inflation, and heritage-site design adjustments and proposes a 30 June 2027 closing date. WACA's December 2025 regional update says ResIP 1 is in its final phase while ResIP 2 extends to The Gambia, Ghana, and Guinea-Bissau. The March 2026 World Bank WACA+ release defines a separate Benin-Mauritania programme. These layers are kept separate rather than merged into one construction narrative.
Phase: construction. Evidence reviewed: 17 July 2026.