Coastal Delivery
Ebeye reached 1,421 m before an unexpected rock shortfall emerged
By 28 November 2025, 1,421 metres of Ebeye's 1,800 metres of new seawall had been built, nearly 80% of the scope. The January 2026 World Bank report recorded an unexpected rock shortfall and a remedy under development. That account describes the material constraint within a USD 52,635,577.03 construction contract and a quarry-to-shore supply chain from Ras Al Khaimah. The President's Office subsequently confirmed handover of the completed seawall and footpath on 17 September 2026.
Published scope and current milestone
The January 2026 World Bank report recorded the historical November 2025 progress, 6,500 people reported with enhanced resilience, rock shortfall and then-unresolved southern-end indicator. The President's Office article of 21 September 2026 confirms the completed seawall and footpath handover on 17 September. Hall's undated completion account, reviewed on 21 October, reports 1.81 kilometres and 84,000 tonnes of armour rock and fill. The original contract API, Haskoning and Bontrup evidence retains its signature date, contract value, intended armour, supply quantity and programme-indicator definitions. Completion announcements leave the final certified quantities and account unverified.
Coastal delivery and performance implications
The November 2025 shortfall affected the final 379 metres of planned new work and the delivery sequence linking quarry supply, ocean transport, barge transfer and armour placement. The September 2026 handover closes the earlier incomplete-work position. The agreed material remedy and its cost and schedule effects remain relevant to the final account.
Evidence conclusion
Geometry, acceptance and performance evidence
Ebeye's current milestone is the September 2026 physical handover. The November 2025 World Bank report remains evidence of the earlier rock constraint. Commercial close-out requires reconciliation of the signed USD 52.64 million works contract, the wider USD 63.44 million component cost and the government's approximately USD 47 million completion announcement. Hall's 84,000 tonnes covers armour rock and fill, while earlier design and supplier statements use different material scopes. The final account, as-built acceptance records and post-storm observations determine financial close-out and the asset's documented protection performance.
Outstanding evidence
- Documented source, quantity, grading, cost and schedule for the rock-shortfall remedy
- Completion certificate and final chainage following the September handover
- Quarry source, 3/6-tonne grading and quality-release documentation
- Ocean-voyage, deep-water transfer, barge and unloading productivity records
- Temporary jetty, access-road, stockpile and reef-flat close-out
- Surveyed toe, filter, armour profile, chainage, tie-ins and drainage
- Southern-end as-built and acceptance records for the power station and solar array interface
- Post-storm overtopping, erosion and adjacent-asset performance
- Completion certificate, defects, final account and maintenance handover
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 10
- President Heine attends Ebeye seawall and footpath handover ceremony Office of the President and Cabinet, Republic of the Marshall Islands, 21 September 2026; handover dated 17 September 2026
- Multi-million-dollar coastal protection project completed Hall Contracting, Undated completion account reviewed 21 October 2026
- Pacific Resilience Project II implementation status and results report World Bank, 15 January 2026
- Contract award 1786103 - Ebeye Coastal Protection Works World Bank, Contract signed 9 May 2024; API reviewed 6 August 2026
- Pacific Resilience Project II current project record World Bank, API reviewed 6 August 2026
- Coastal protection Marshall Islands Bontrup, Current logistics record reviewed 14 July 2026
- Ebeye coastal protection works Hall Contracting, Current project page reviewed 14 July 2026
- Major milestone in Marshall Islands with two Australian companies commencing works Haskoning, 16 February 2025
- Pacific Resilience Project II implementation status and results report World Bank, 15 April 2025
- Ebeye coastal protection environmental and social impact assessment and management plan Republic of the Marshall Islands Ministry of Finance, June 2024