Coastal Delivery
Ebeye reached 1,421 m before an unexpected rock shortfall emerged
By 28 November 2025, 1,421 metres of Ebeye's 1,800 metres of new seawall had been built, nearly 80% of the scope. The same implementation report says Hall identified an unexpected rock shortfall and the project team was still developing solutions. The risk sits inside a USD 52,635,577.03 construction contract and a supply chain that moves armourstone from Ras Al Khaimah through deep-water transfer and barge delivery to a constrained atoll work front.
Published scope and current milestone
The January 2026 World Bank implementation report controls the 1,421 metres built by 28 November 2025, 6,500 people reported with enhanced resilience, unexpected rock shortfall and unresolved southern-end asset-protection indicator. The World Bank contract API separately records Hall Civil Contracting Pty Ltd, contract 1786103 and the exact USD 52,635,577.03 value. Hall and Haskoning describe 1,800 metres of new seawall and about 65,000 tonnes of intended armour use. Bontrup reports approximately 80,000 tonnes supplied. The 2,100-metre results target includes 300 metres of existing seawall, so all value, tonnage and length figures remain in their own source boundaries.
Coastal delivery and performance implications
The progress number materially changes the picture: this is no longer only a mobilisation and logistics story. It also reveals why delivered tonnage cannot stand in for completion. The remaining 379 metres, the southern-end interface protecting the power station and solar array, and final acceptance all depend on closing the rock gap without losing grading, profile or schedule control.
Evidence conclusion
Geometry, acceptance and performance evidence
Ebeye now presents a late-stage supply-chain test. The reported 1,421 metres proves substantial construction progress but not accepted protection, and the rock shortfall reopens quarry availability, grading, shipping, transfer, barge and work-front productivity questions for the remaining 379 metres. Commercially, the executed works contract is USD 52.64 million, while the USD 63.44 million figure is the wider Component 2 cost. A rock solution, southern-end construction, surveyed geometry, completion certification and maintenance handover remain separate gates.
Outstanding evidence
- Approved source, quantity, grading and schedule for the rock-shortfall remedy
- Owner-certified progress and acceptance of the remaining 379 metres
- Quarry source, 3/6-tonne grading and quality-release documentation
- Ocean-voyage, deep-water transfer, barge and unloading productivity records
- Temporary jetty, access-road, stockpile and reef-flat close-out
- Surveyed toe, filter, armour profile, chainage, tie-ins and drainage
- Southern-end construction protecting the power station and solar array
- Post-storm overtopping, erosion and adjacent-asset performance
- Completion certificate, defects, final account and maintenance handover
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 8
- Pacific Resilience Project II implementation status and results report World Bank, 15 January 2026
- Contract award 1786103 - Ebeye Coastal Protection Works World Bank, Contract signed 9 May 2024; API reviewed 6 August 2026
- Pacific Resilience Project II current project record World Bank, API reviewed 6 August 2026
- Coastal protection Marshall Islands Bontrup, Current logistics record reviewed 14 July 2026
- Ebeye coastal protection works Hall Contracting, Current project page reviewed 14 July 2026
- Major milestone in Marshall Islands with two Australian companies commencing works Haskoning, 16 February 2025
- Pacific Resilience Project II implementation status and results report World Bank, 15 April 2025
- Ebeye coastal protection environmental and social impact assessment and management plan Republic of the Marshall Islands Ministry of Finance, June 2024