Coastal Delivery
Avalon stages beachfill equipment ahead of hydraulic placement
Avalon's 28 August update reports equipment staging and completed pre-project surveys under review ahead of hydraulic beachfill. Sand pumping remains anticipated around 5 September. The transition matters because a prepared workfront, the dredging start and the completed coastal-protection profile are separate milestones.
Survey review precedes the pumping front
USACE's 5 June award names Norfolk Dredging Company for a shared USD 15.8 million Avalon and Stone Harbor contract. It specifies 941,032 cubic yards for Avalon. The borough's late-August account describes access through 20th Street and staging at 9th Street. Its 9th-25th Street placement description differs from the district's original 9th-28th Street extent; a final surveyed workfront is still needed to reconcile them.
Beach width is an engineered protection asset
The district's April programme factsheet describes a 150-foot berm backed by a dune crest at +14.75 feet NAVD, within a recurring nourishment programme. Restoring that cross-section is different from making a beach look wider. Borrow-area dredging, hydraulic transport, shore grading and beach access must operate as one delivery chain. A headline sand quantity alone says little about where the protection profile has actually been restored.
Evidence conclusion
Placement forecasts and contract closeout diverge
The June NJDEP and USACE council presentation gives a 9 June notice to proceed and a 9 November contract completion date including cleanup. By late August the borough anticipates pumping around 5 September. These describe contractual and operational clocks, rather than interchangeable finish dates. The next delivery measure is a dated pumping start tied to the receiving reach, followed by quantities and accepted profiles. Equipment on the beach is a physical preparation milestone, but no placed volume or accepted section accompanies this update.
Outstanding evidence
- Dated pumping start and the first receiving reach
- Surveyed placement limits reconciled with the original award extent
- Berm and dune profiles accepted against the design template
- Stone Harbor sequencing, cleanup and contractual closeout
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- Equipment staging and pre-project survey update Borough of Avalon, 18, 27 and 28 August 2026 sections
- Avalon and Stone Harbor nourishment contract award USACE Philadelphia District, 5 June 2026
- Council presentation: engineered profile, notice to proceed and contract schedule NJDEP / USACE Philadelphia District, hosted by Stone Harbor, 16 June 2026
- Seven Mile Island coastal storm risk management programme USACE Philadelphia District, 15 April 2026