Project record

Apia Port climate-resilient breakwater and terminal upgrade

Aerial view of the Apia International Port container terminal showing the yard, wharf, coastal revetment and X-bloc breakwater

Samoa Ports Authority; exact Apia International Port image, not represented as current construction-progress evidence

Samoa's main international gateway is being upgraded under ADB project 47358-002. China Harbour Engineering Company holds the main landside civil works and breakwater-repair package, Beca supervises construction, and the delivery chain also includes Royal HaskoningDHV, Think Environment Consult, INSPIRE Consult and Cheoy Lee Shipyards. The latest implementation position separates near-close-out terminal sections from the unresolved marine critical path: Section 1 quality-assurance records and Section 2 handover were expected in June 2026, but the 100-metre breakwater reconstruction moved from a December 2026 contractor estimate in the 2024 monitoring report to mid-July 2027, followed by a one-year defects period.

Project signal

Construction in Samoa

Current status Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate Source confidence Confirmed

Location

Samoa / Global islands

Segment

Port infrastructure

Status

Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate / Confirmed

Last checked

11 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Government of Samoa, Ministry of Finance and Samoa Ports Authority
Delivery parties
China Harbour Engineering Company Limited - main landside civil works and breakwater-repair contractor, Beca International Consultants Limited - construction supervision consultant, USD 3,881,125.46 contract, Royal HaskoningDHV Nederland B.V. - green-port initiative consultant, USD 900,226.60 contract, Think Environment Consult - CHEC environmental consultant for EIA and construction environmental management planning, INSPIRE Consult - CHEC consultant for quarry consultations, Cheoy Lee Shipyards Ltd. - tugboat supplier; USD 5,150,000 first-tug contract and USD 7,365,000 second-tug contract
Contract route
ADB records one internationally competed civil-works contract awarded in March 2021. Its operational procurement database names China Harbour Engineering Company Limited for the 'Landside Civil Works and Breakwater Repair' award and reports an ADB-financed amount of 35,415,550.78, while the discovery workbook does not expose the currency or full contract value. The project page separately describes the civil package as a USD 43.1 million awarded procurement line. Beca's supervision, Royal HaskoningDHV's green-port work and the Cheoy Lee tugboat contracts are separate awards and must not be summed as CHEC lower tiers.
Execution window
CHEC mobilised on 16 August 2021. The July-December 2024 monitoring report showed contractor estimates of April 2025 for Section 1, June 2025 for Section 2 and December 2026 for Section 3 and overall completion. ADB's later project record moves Section 1 quality-assurance documentation and Section 2 handover to June 2026 and the 100-metre breakwater to mid-July 2027, after which a one-year defects period is expected. The main ADB grant closing date has been extended from 31 March 2024 to 31 March 2029.
Works package
The civil programme covers reconstruction of the existing breakwater; aids to navigation; new and repaired pavements and stormwater drainage; buildings and portwide services; container-yard lighting; partial wharf-deck replacement; conversion of Shed 2 for devanning; an equipment-maintenance workshop; Shed 1 modifications; an X-ray scanner building; and a customs inspection shelter. The wider project also includes two tugboats, a wave-monitoring system and green-port initiatives.
Marine interfaces
The project joins a 100-metre breakwater reconstruction to an operating container and general-cargo gateway that handles almost all of Samoa's international trade. Breakwater redesign, X-bloc production and storage, quarry supply, navigation access, tug operations, wharf-deck work, terminal circulation and ongoing vessel calls must therefore be sequenced as one live-port system. Completion of landside buildings does not resolve the wave-exposure and harbour-protection risk carried by Section 3.
Commercial evidence boundary
ADB lists total project cost at USD 75.03 million, comprising USD 62.26 million of ADB financing and USD 12.77 million of counterpart funding. At 30 April 2026, the main grant showed USD 60.57 million of cumulative awards, or 97%, and USD 35.51 million of disbursements, or 57%. These project and grant figures are not the CHEC contract value. CHEC's full contract amount, current variation account, breakwater redesign price, lower-tier construction subcontract values and final forecast cost remain unpublished.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Main civil award

Landside Civil Works and Breakwater Repair

Named party
China Harbour Engineering Company Limited
Status
Confirmed
Source position
ADB's operational procurement database names CHEC on the March 2021 works award; SPA's monitoring report records the civil contract signed on 29 March 2021 and mobilisation on 16 August 2021. Source
Section 1

X-ray building, shelters and pavements

Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB reports the X-ray building and scanner operational but says quality-assurance documentation was expected in June 2026 because records were limited; no later acceptance record was recovered. Source
Section 2

Remaining terminal works

Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB's current record expected electrical commissioning in May 2026 and handover in June 2026; no later signed handover was recovered. Source
Section 3

Reconstruction of 100 metres of existing breakwater

Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB reports the output as not achieved and expects CHEC's civil works at the breakwater site to finish in mid-July 2027, followed by a one-year defects period. Source
Construction supervision

Construction supervision services

Named party
Beca International Consultants Limited
Status
Confirmed
Source position
ADB records a USD 3,881,125.46 contract dated 8 February 2021; current monitoring remains ongoing. Source
Environmental and quarry consultation support

EIA, CEMP and quarry consultations

Named party
Think Environment Consult and INSPIRE Consult
Status
Confirmed
Source position
SPA's monitoring report identifies both firms as CHEC-appointed specialist consultants; no public package values or current execution status are disclosed. Source
Tugboat supply

Two replacement tugboats

Named party
Cheoy Lee Shipyards Ltd.
Status
Confirmed
Source position
ADB records the first USD 5.15 million tugboat contract and a separate USD 7.365 million second-tugboat award dated 8 May 2026; these are project packages, not CHEC subcontracts. Source

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Breakwater becomes the July 2027 critical path

ADB's current record moves the 100-metre breakwater from the contractor's earlier December 2026 estimate to mid-July 2027 and places a one-year defects period after completion.

Source

Second tugboat contract awarded

Cheoy Lee received a separate USD 7.365 million award, advancing fleet renewal without closing the CHEC civil and breakwater package.

Source

SPA monitoring report records a December 2026 contractor estimate

The report establishes the prior schedule baseline and provides the package-level comparison needed to quantify the later seven-month breakwater delay.

Source

CHEC civil contract signed

CHEC became the prime civil contractor, with mobilisation following on 16 August 2021 and specialist construction subcontract values still undisclosed.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Signed Section 1 quality-assurance close-out and acceptance
  • Section 2 electrical commissioning, handover and defects list
  • Approved breakwater redesign, price and programme
  • Section 3 field start and movement from mid-July 2027
  • X-bloc production, storage, placement and acceptance quantities
  • Quarry supply, haulage, marine plant and lower-tier assignments
  • Aids to navigation, wave monitoring and live-port operating controls
  • CHEC variations, Beca supervision extension and forecast final cost
  • One-year defects period and formal whole-project handover

Reporting status

Construction, confirmed confidence

Last checked 11 August 2026 across 8 cited sources. The dated timeline above carries the project events.

Last checked 11 August 2026 Cited sources 8

Sources and related records

Read featured analysis Methodology Submit a correction Project tracker

Project sources 8