Samoa's main international gateway is being upgraded under ADB project 47358-002. China Harbour Engineering Company holds the main landside civil works and breakwater-repair package, Beca supervises construction, and the delivery chain also includes Royal HaskoningDHV, Think Environment Consult, INSPIRE Consult and Cheoy Lee Shipyards. The latest implementation position separates near-close-out terminal sections from the unresolved marine critical path: Section 1 quality-assurance records and Section 2 handover were expected in June 2026, but the 100-metre breakwater reconstruction moved from a December 2026 contractor estimate in the 2024 monitoring report to mid-July 2027, followed by a one-year defects period.
Project signal
Construction in Samoa
Current statusSection 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificateSource confidenceConfirmed
Location
Samoa / Global islands
Segment
Port infrastructure
Status
Section 1 quality-assurance close-out and Section 2 handover were expected in June 2026, while CHEC's 100-metre breakwater reconstruction is now expected in mid-July 2027; neither the June milestones nor breakwater completion has a later published acceptance certificate / Confirmed
Last checked
11 August 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Government of Samoa, Ministry of Finance and Samoa Ports Authority
Delivery parties
China Harbour Engineering Company Limited - main landside civil works and breakwater-repair contractor, Beca International Consultants Limited - construction supervision consultant, USD 3,881,125.46 contract, Royal HaskoningDHV Nederland B.V. - green-port initiative consultant, USD 900,226.60 contract, Think Environment Consult - CHEC environmental consultant for EIA and construction environmental management planning, INSPIRE Consult - CHEC consultant for quarry consultations, Cheoy Lee Shipyards Ltd. - tugboat supplier; USD 5,150,000 first-tug contract and USD 7,365,000 second-tug contract
Contract route
ADB records one internationally competed civil-works contract awarded in March 2021. Its operational procurement database names China Harbour Engineering Company Limited for the 'Landside Civil Works and Breakwater Repair' award and reports an ADB-financed amount of 35,415,550.78, while the discovery workbook does not expose the currency or full contract value. The project page separately describes the civil package as a USD 43.1 million awarded procurement line. Beca's supervision, Royal HaskoningDHV's green-port work and the Cheoy Lee tugboat contracts are separate awards and must not be summed as CHEC lower tiers.
Execution window
CHEC mobilised on 16 August 2021. The July-December 2024 monitoring report showed contractor estimates of April 2025 for Section 1, June 2025 for Section 2 and December 2026 for Section 3 and overall completion. ADB's later project record moves Section 1 quality-assurance documentation and Section 2 handover to June 2026 and the 100-metre breakwater to mid-July 2027, after which a one-year defects period is expected. The main ADB grant closing date has been extended from 31 March 2024 to 31 March 2029.
Works package
The civil programme covers reconstruction of the existing breakwater; aids to navigation; new and repaired pavements and stormwater drainage; buildings and portwide services; container-yard lighting; partial wharf-deck replacement; conversion of Shed 2 for devanning; an equipment-maintenance workshop; Shed 1 modifications; an X-ray scanner building; and a customs inspection shelter. The wider project also includes two tugboats, a wave-monitoring system and green-port initiatives.
Marine interfaces
The project joins a 100-metre breakwater reconstruction to an operating container and general-cargo gateway that handles almost all of Samoa's international trade. Breakwater redesign, X-bloc production and storage, quarry supply, navigation access, tug operations, wharf-deck work, terminal circulation and ongoing vessel calls must therefore be sequenced as one live-port system. Completion of landside buildings does not resolve the wave-exposure and harbour-protection risk carried by Section 3.
Commercial evidence boundary
ADB lists total project cost at USD 75.03 million, comprising USD 62.26 million of ADB financing and USD 12.77 million of counterpart funding. At 30 April 2026, the main grant showed USD 60.57 million of cumulative awards, or 97%, and USD 35.51 million of disbursements, or 57%. These project and grant figures are not the CHEC contract value. CHEC's full contract amount, current variation account, breakwater redesign price, lower-tier construction subcontract values and final forecast cost remain unpublished.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Main civil award
Landside Civil Works and Breakwater Repair
Named party
China Harbour Engineering Company Limited
Status
Confirmed
Source position
ADB's operational procurement database names CHEC on the March 2021 works award; SPA's monitoring report records the civil contract signed on 29 March 2021 and mobilisation on 16 August 2021. Source
Section 1
X-ray building, shelters and pavements
Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB reports the X-ray building and scanner operational but says quality-assurance documentation was expected in June 2026 because records were limited; no later acceptance record was recovered. Source
Section 2
Remaining terminal works
Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB's current record expected electrical commissioning in May 2026 and handover in June 2026; no later signed handover was recovered. Source
Section 3
Reconstruction of 100 metres of existing breakwater
Named party
CHEC under Beca supervision
Status
Reported
Source position
ADB reports the output as not achieved and expects CHEC's civil works at the breakwater site to finish in mid-July 2027, followed by a one-year defects period. Source
Construction supervision
Construction supervision services
Named party
Beca International Consultants Limited
Status
Confirmed
Source position
ADB records a USD 3,881,125.46 contract dated 8 February 2021; current monitoring remains ongoing. Source
Environmental and quarry consultation support
EIA, CEMP and quarry consultations
Named party
Think Environment Consult and INSPIRE Consult
Status
Confirmed
Source position
SPA's monitoring report identifies both firms as CHEC-appointed specialist consultants; no public package values or current execution status are disclosed. Source
Tugboat supply
Two replacement tugboats
Named party
Cheoy Lee Shipyards Ltd.
Status
Confirmed
Source position
ADB records the first USD 5.15 million tugboat contract and a separate USD 7.365 million second-tugboat award dated 8 May 2026; these are project packages, not CHEC subcontracts. Source
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
ADB's current record moves the 100-metre breakwater from the contractor's earlier December 2026 estimate to mid-July 2027 and places a one-year defects period after completion.
SPA monitoring report records a December 2026 contractor estimate
The report establishes the prior schedule baseline and provides the package-level comparison needed to quantify the later seven-month breakwater delay.
CHEC became the prime civil contractor, with mobilisation following on 16 August 2021 and specialist construction subcontract values still undisclosed.