Project record
Aiwo's wharf, fuel pipeline and reverse-osmosis plant are operating. A monitoring report released in July 2026 says dredging was 78% complete by June 2025, the northern-yard interim apron was at 97% and all buildings had been handed over, but ADB's current project page still carries a broader unfinished-work list.
Nauru / Global islands
Port infrastructure
ADB still lists the project as active. Its July 2026 monitoring report records 78% dredging, 97% of the northern-yard interim apron complete and all buildings handed over at the end of June 2025, while the current project page still lists full dredging and buildings among awaited items / Confirmed
19 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe main grants now close on 31 December 2026. ADB reports the wharf, pipelines, southern yard and reverse-osmosis plant complete, while the northern yard, roads, sheds, buildings and full berth-pocket dredging remain outstanding.
SourceThe call demonstrates that the new wharf is handling a Nauru-owned container vessel. It does not close the remaining dredging, yard, road or building scope.
SourceThe report released in July 2026 records dredging at 78%, the northern-yard interim apron at 97%, all buildings handed over and only the fire-pump system outstanding in the southern yard at the reporting cutoff.
SourceThe water-system component entered service after the fuel pipeline, creating an operating marine-utility interface while other port works continued.
SourceEvidence gap