Tonga's Ministry of Infrastructure has combined the next Nafanua Port works into package MOI-WK2-13: repair and extension of the entrance breakwater, a new berth for small boats and a new passenger terminal. The World Bank's revised procurement plan dated 2 October 2025 marks the package under implementation. No named contractor or contract value appears in the plan, and neither the tender nor supervision notice records a notice to proceed or site mobilisation.
Project signal
Award in Tonga
Treat Nafanua as a post-tender package awaiting public delivery evidence. The procurement status is stronger than an open opportunity but weaker than a notice to proceed or physical mobilisation. Keep the sheet-pile protection, bollards and concrete slab completed under the earlier transport project in 2020 and early 2021 separate from the current package.
Current statusWorld Bank's revised procurement plan marks MOI-WK2-13 under implementation; contractor, contract value, notice to proceed and site mobilisation remain publicly unconfirmedSource confidenceConfirmed
Location
Tonga / Global islands
Segment
Port infrastructure
Status
World Bank's revised procurement plan marks MOI-WK2-13 under implementation; contractor, contract value, notice to proceed and site mobilisation remain publicly unconfirmed / Confirmed
Evidence reviewed
20 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Government of Tonga, Ministry of Infrastructure
Delivery parties
Works contractor not publicly named by 20 July 2026
Contract route
The Ministry issued an open international, single-stage two-envelope request for bids using the World Bank Small Works SPD on 11 August 2025. The revised procurement plan records MOI-WK2-13 as under implementation and shows an actual amount of 0.00, so no contract value can be reported from that plan. Earlier separate packages for the passenger terminal and two-lot breakwater repair are marked cancelled; the current record follows the integrated package instead.
Execution window
No package-specific completion date appears in the procurement plan, tender notice or supervision notice. The Ministry's 31 March 2026 request for a resident engineer, site inspector and environmental and social specialist confirms that construction supervision was being assembled, but it does not establish a notice to proceed or site mobilisation.
Works package
Repair the existing entrance breakwater and construct an extension, build a new small-boat berth after Tropical Cyclone Harold damaged the existing slipway, and construct a new passenger terminal. Earlier sheet-pile wall protection, bollards and a concrete slab delivered in 2020 and early 2021 are prior works. The appraisal's detailed Nafanua section refers to a 50-year return-period storm and a 20-year design life, while its results framework describes 50-year storm resilience as equivalent to a 25-year design life; both statements are retained rather than normalised.
Marine interfaces
The package has to improve the exposed harbour entrance while Nafanua continues to serve 'Eua's ferry, cargo and small-boat traffic. The central marine interfaces are breakwater geometry and armour logistics, safe access to the new small-boat berth, construction sequencing around vessel calls, and the link between the protected water area and passenger-terminal operation. Dredging is absent from the published package definition.
Commercial read
The revised plan moves the owner-level works procurement beyond open bidding, while the contractor, contract value, notice to proceed and subcontract map remain undisclosed. Any remaining opportunity should be tied to a disclosed delivery party or package need rather than inferred from the procurement plan.
Next milestone
Publication of the works contractor, contract value and notice to proceed, followed by plant and armour mobilisation and visible start of breakwater, small-boat berth or passenger-terminal works.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The Ministry sought a dedicated construction-supervision team
The request covered a resident engineer, site inspector and environmental and social specialist for the Nafanua works. It supports delivery preparation but does not prove that the works contractor mobilised.
The revised procurement plan marked the integrated package under implementation
MOI-WK2-13 replaced the earlier split approach in the public plan. The separate passenger-terminal and two-lot breakwater packages are marked cancelled, while the integrated package carries no published contractor or actual contract amount.
The Ministry issued the integrated works request for bids
The notice put the breakwater, small-boat berth and passenger-terminal work into one open international, two-envelope Small Works package, replacing the previous split procurement path.
Publication of the works contractor, contract value and notice to proceed, followed by plant and armour mobilisation and visible start of breakwater, small-boat berth or passenger-terminal works.
Decision watchpoints
Named works contractor and contract value
Notice to proceed and baseline condition survey
Breakwater armour source, transport and placement plan
Plant and materials mobilisation to 'Eua
Small-boat berth setting-out and marine access controls
Passenger-terminal construction and utility interfaces
As-built surveys and works acceptance
Breakwater and harbour performance after a significant storm
Tonga Ministry of InfrastructureOrganization profile / Government transport-infrastructure ministry and maritime-works implementing agency
Project availability status
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed20 July 2026Sources in this record6
Source record
The 2 October 2025 World Bank procurement plan controls the current package status and cancellation of the earlier separate packages. The project appraisal defines the integrated marine scope and separates earlier 2020-21 repairs. The August 2025 bid notice records the procurement method, while the March 2026 supervision notice supports delivery preparation but not physical mobilisation. The ESMP supplies exact-site photographs and environmental context, not proof that the current package has started.