USACE Buffalo District is repairing Dunkirk Harbor's west breakwater with stone reinforcement and a higher crest. Its June 2026 release says about 1,850 feet were repaired in the first phase and the remaining 450 feet are now under way through November. The same release gives two different values for that second phase, leaving its price unresolved and no programme total stated.
United States / Americas
Port infrastructure
USACE reports the first phase nearing completion and a 450-foot second phase continuing through November 2026 / Confirmed
18 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The district says approximately 1,850 feet are nearing completion and the last 450 feet will run through November 2026. The same release gives two different phase-two cost figures, USD 4.5 million and USD 1.9 million, which remain unresolved.
Read controlling sourceBuffalo District video shows marine plant and a long-reach material handler working on the Dunkirk breakwater. It confirms construction activity in August 2025 but does not establish production quantities, accepted length or the later second-phase start.
Read controlling sourceThe USD 7.56 million Great Lakes Dock & Materials award covered approximately 1,450 feet of lake-side stone overlay and an east-head wrap over two construction seasons. Its limits and value are not directly reconciled to the 2026 phase figures.
Read controlling sourceDelivery watch
USACE clarification of the phase-two contract and cost, followed by accepted first-phase limits and measured completion of the remaining 450 feet
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe 30 June 2026 USACE release controls current construction status, the reported 1,850-foot first phase, remaining 450-foot second phase, stone and crest work, November target and no expected navigation impact. That release contains an internal cost conflict: USD 4.5 million in a project bullet and USD 1.9 million in the narrative for phase two. It also describes phase one as USD 9.1 million. The 22 July 2024 award release instead records USD 7.56 million, Great Lakes Dock & Materials and approximately 1,450 feet plus an east-head wrap. The records do not explain whether later figures include added reaches, modifications or different package boundaries, so no reconciliation is assumed. The official phase map labels the full outer breakwater at 2,812 linear feet and shows a reach outside the current repair scope. The August 2025 video confirms field operations but not 2026 second-phase mobilisation, quantity or acceptance.
Phase: construction. Evidence reviewed: 18 July 2026.