Breakwaters

Great Lakes Dock holds Dunkirk's last 450-foot repair phase

Published 18 July 2026 Updated 10 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Long-reach material handler and work platform placing stone on the Dunkirk Harbor west breakwater on 7 August 2025

Kaylee Wendt / U.S. Army Corps of Engineers, Buffalo District; frame from 7 August 2025 video, not 2026 phase-two progress

Official federal award data identifies Great Lakes Dock & Materials for Dunkirk Harbor's remaining 450-foot breakwater phase at USD 1.936 million. The contract record resolves the contractor and supports USACE's USD 1.9 million narrative, while leaving the same release's USD 4.5 million bullet unsupported.

Published scope and current milestone

USAspending establishes Great Lakes Dock & Materials, USD 1,936,019.80, award date 5 March 2026, performance from 20 March to 14 October, firm-fixed-price delivery-order form, one recorded offer and the competitive small-business fair-opportunity route. The phase-one record now carries USD 9,155,616.59 of obligations. The 30 June USACE release controls field status, 1,850-foot and 450-foot phase lengths, November target, repair method and navigation note. Its USD 1.9 million narrative aligns with the award, while the USD 4.5 million bullet does not. Zero reported subawards, a contract end date and photographed activity are not lower-tier disclosure, owner acceptance or completed work. The image remains a 7 August 2025 field frame, not 2026 phase-two evidence.

Coastal delivery and performance implications

The remaining package is now commercially attributable: firm-fixed-price delivery order W912P426FA007 runs from 20 March to 14 October 2026 under USACE's marine-construction IDIQ. Phase-one obligations have also risen from the USD 7.56 million initial announcement to USD 9.156 million, but the reviewed award summary does not expose the modification scope.

Evidence conclusion

Geometry, acceptance and performance evidence

The delivery chain is clearer without overstating completion. Great Lakes Dock holds both phases, USACE reports 1,850 feet nearly repaired and the final 450 feet active, and the federal award establishes the phase-two contractor and amount. The contract date of 14 October and owner's November field target are separate clocks. Zero reported USAspending subawards does not prove there are no stone, transport, vessel or other lower-tier suppliers, and neither contract data nor the June field release proves accepted completion.

Outstanding evidence

  • First-phase inspection and accepted length
  • Owner correction or withdrawal of the unsupported USD 4.5 million bullet
  • Phase-one modification detail behind the current USD 9.156 million obligation
  • Stone placement and crest raising across the remaining 450 feet
  • Navigation separation around the work platform
  • Surveyed completion and owner acceptance against the 14 October contract date and November field target
  • Any reported stone, transport, marine-plant or other lower-tier award