Breakwaters
Great Lakes Dock holds Dunkirk's last 450-foot repair phase
Official federal award data identifies Great Lakes Dock & Materials for Dunkirk Harbor's remaining 450-foot breakwater phase at USD 1.936 million. The contract record resolves the contractor and supports USACE's USD 1.9 million narrative, while leaving the same release's USD 4.5 million bullet unsupported.
Published scope and current milestone
USAspending establishes Great Lakes Dock & Materials, USD 1,936,019.80, award date 5 March 2026, performance from 20 March to 14 October, firm-fixed-price delivery-order form, one recorded offer and the competitive small-business fair-opportunity route. The phase-one record now carries USD 9,155,616.59 of obligations. The 30 June USACE release controls field status, 1,850-foot and 450-foot phase lengths, November target, repair method and navigation note. Its USD 1.9 million narrative aligns with the award, while the USD 4.5 million bullet does not. Zero reported subawards, a contract end date and photographed activity are not lower-tier disclosure, owner acceptance or completed work. The image remains a 7 August 2025 field frame, not 2026 phase-two evidence.
Coastal delivery and performance implications
The remaining package is now commercially attributable: firm-fixed-price delivery order W912P426FA007 runs from 20 March to 14 October 2026 under USACE's marine-construction IDIQ. Phase-one obligations have also risen from the USD 7.56 million initial announcement to USD 9.156 million, but the reviewed award summary does not expose the modification scope.
Evidence conclusion
Geometry, acceptance and performance evidence
The delivery chain is clearer without overstating completion. Great Lakes Dock holds both phases, USACE reports 1,850 feet nearly repaired and the final 450 feet active, and the federal award establishes the phase-two contractor and amount. The contract date of 14 October and owner's November field target are separate clocks. Zero reported USAspending subawards does not prove there are no stone, transport, vessel or other lower-tier suppliers, and neither contract data nor the June field release proves accepted completion.
Outstanding evidence
- First-phase inspection and accepted length
- Owner correction or withdrawal of the unsupported USD 4.5 million bullet
- Phase-one modification detail behind the current USD 9.156 million obligation
- Stone placement and crest raising across the remaining 450 feet
- Navigation separation around the work platform
- Surveyed completion and owner acceptance against the 14 October contract date and November field target
- Any reported stone, transport, marine-plant or other lower-tier award
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- Repair work continues on Dunkirk breakwater U.S. Army Corps of Engineers, Buffalo District, 30 June 2026
- Dunkirk west breakwater repair phase map U.S. Army Corps of Engineers, Buffalo District via DVIDS, 29 June 2026
- Dunkirk Breakwater Repair Phase 2 award W912P426FA007 USAspending.gov, U.S. Department of the Treasury, Award signed 5 March 2026; record reviewed 3 August 2026
- Dunkirk Breakwater Repair phase-one award W912P424F0022 USAspending.gov, U.S. Department of the Treasury, Award signed 25 June 2024; record reviewed 3 August 2026
- Dunkirk Harbor Breakwater Repair U.S. Army Corps of Engineers, Buffalo District, 7 August 2025
- Critical repairs on the way for Dunkirk breakwater U.S. Army Corps of Engineers, Buffalo District, 22 July 2024