Urban outfall dredging
Libertad dredging is reported complete without published package closeout
Rayman Builders signed the USD 1.071 million Libertad Outfall dredging contract on 6 October 2023. The Philippines Commission on Audit identifies the same package as DPWH contract 22Z00033, records a PHP 60.833 million contract cost and lists PHP 60.665 million in construction in progress at 31 December 2024. A November-December 2025 World Bank mission reports that all eight DPWH dredging contracts were completed. That supports completed contract status for the group that includes Libertad, but it does not publish this package's measured volume, sediment destination, as-built geometry, hydraulic clearance or DPWH acceptance.
Programme reporting now places the contract in the completed group
World Bank contract 1747629 identifies Rayman Builders, the signature and the USD amount. The Commission on Audit independently identifies contract 22Z00033, its PHP contract cost and the construction-in-progress balance at 31 December 2024. The procurement plan gives the package title, estimate, Signed state and planned date. The November-December 2025 aide-memoire reports all eight DPWH dredging contracts completed, which supports completion at the contract-group level. Libertad's package-specific quantity, survey, hydraulic result, acceptance and final account remain unpublished.
An urban outfall must be closed out as a hydraulic asset
Removing sediment is only one part of flood-readiness. The package must prove where material went, what cross-section remained, whether utilities and structures were protected, whether the outfall flows as designed and whether the owner accepted the result before the next flood season.
Evidence conclusion
Contract completion and hydraulic acceptance remain different questions
Contract 1747629 and the procurement plan establish a narrow Pasay dredging package. The Commission on Audit adds an independent financial identity: contract 22Z00033, PHP 60.833 million contract cost and PHP 60.665 million in construction in progress at 31 December 2024. Those audited figures do not establish final payment or technical acceptance. The later aide-memoire closes the earlier uncertainty over whether the eight DPWH dredging contracts reached completion, but its aggregate 10-kilometre waterway result cannot be assigned to Libertad. A defensible package closeout still needs actual dates, plant and method, sediment testing and destination, measured volume, as-built survey, hydraulic clearance, pumping-station interface, environmental records and DPWH acceptance.
Outstanding evidence
- Actual mobilisation and finish dates
- Plant, method and measured volume
- Sediment classification and destination
- As-built outfall section or survey
- Hydraulic and flood-season readiness
- DPWH acceptance, variations and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- World Bank contract 1747629 for PH-DPWH-335435-CW-RFB World Bank Projects and Operations API, Contract signed 6 October 2023
- Metro Manila Flood Management Project Phase I audited financial statements for 2024 Philippines Commission on Audit, Financial position at 31 December 2024; audit report signed 30 June 2025
- P153814 procurement plan including Libertad Outfall dredging World Bank, Published June 2025
- P153814 implementation status and results report World Bank, 5 November 2025
- P153814 November-December 2025 implementation support mission aide-memoire World Bank, Mission 3 November-1 December 2025; reviewed 13 August 2026