Mermaid Beach repair scope centres on six displaced walkway units
IMWO original source-based engineering and procurement chart
Folkestone and Hythe's Mermaid Beach tender covers recovery, repair and reinstatement of six 32-tonne precast walkway units. The council reports the rock structure intact. Submissions closed on 25 September 2026 at 13:00 UTC+01:00, with an award and actual repair progress still unconfirmed.
Walkway units define the advertised repair
Tender history 083907-2026 states the six-unit scope, estimates, submission time and safety criteria. The council's 6 August release describes the displaced concrete sections, intact rock structure and up-to-GBP 200,000 repair allocation. The 22 July agenda lists the repair item. Complete bidding and technical attachments have not been obtained; the published schedule provides planned dates rather than evidence of mobilisation or completion.
Heavy units share a public-access beach
Recovering 32-tonne units introduces lifting and temporary-work requirements on a beach used by the public. The notice asks bidders to address site security and protection of operatives and beach users, alongside three marine-civil examples from the preceding five years. A workable repair method also needs verified access, ground support, handling sequence and tide and weather limits. These are project-specific preparation questions; the published notice and council account do not supply a complete lifting or temporary-works design.
Evidence conclusion
Award and site arrangements remain outstanding
This procurement's submission window has closed. The next records needed are the selected contractor, issued repair method, public-access controls and actual reinstatement. The GBP 175,000 excluding-VAT tender estimate and separate council allocation of up to GBP 200,000 have different purposes. Neither establishes the eventual contract price or payment. Keeping the intact rock structure visible also preserves the limited walkway-repair scope when comparing this case with whole-breakwater reconstruction.
Outstanding evidence
- Contract award and selected repair contractor
- Issued lifting, access and temporary-work arrangements
- Public-beach access and operative protection
- Dated unit recovery, repair and reinstatement
- Contract price, acceptance and payment record
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
-
Mermaid Beach repairs: official procurement history
UK Find a Tender, 4 September 2026; checked 14 October 2026
Bounded six-unit scope, expired deadline, evaluation, planned period and portal route; no award object in this history.
-
Reconstruction of Breakwater at Mermaid Beach: tender notice
Folkestone and Hythe District Council / Find a Tender, 4 September 2026
Original notice locator; the structured history provides the notice facts. The title is broader than the advertised six-unit scope.
-
Breakwater repair work agreed by council
Folkestone and Hythe District Council, 6 August 2026
Owner account of displaced walkway sections, an intact rock structure and repair funding; no completion claim.
-
Council agenda: Mermaid Beach repairs and the capital programme
Folkestone and Hythe District Council, 22 July 2026
Item 16 lists the capital-programme proposal and report. Agenda entry is separate from the August account of approval.