A USD 1.1 million Geo Gradel contract covers approximately 59,000 cubic yards from Rocky River Harbor. Work began in late May, with about 50,000 cubic yards assigned to a nearshore area east of the harbor and 9,000 cubic yards to a designated open-lake area.
Project signal
Construction in United States
Current statusMechanical dredging began in late May 2026 and is scheduled to continue through AugustSource confidenceConfirmed
Location
United States / Americas
Segment
Port infrastructure
Status
Mechanical dredging began in late May 2026 and is scheduled to continue through August / Confirmed
Last checked
18 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Buffalo District
Delivery parties
Geo Gradel
Contract route
USD 1.1 million federal maintenance-dredging contract awarded in April 2026 to Toledo-based Geo Gradel
Execution window
Operations began in late May 2026 and are scheduled to continue through August 2026.
Works package
Mechanical dredging of approximately 59,000 cubic yards from the federal navigation channel, with about 50,000 cubic yards assigned to nearshore placement east of the harbor and 9,000 cubic yards to a designated open-lake placement area
Marine interfaces
Mechanical excavation from a narrow recreational navigation channel, loading into scows, two separate Lake Erie material routes, and navigation separation around active plant and public boating access
Commercial evidence boundary
The award, contractor, total planned quantity and two placement routes are public. The remaining delivery evidence is operational: measured excavation, route-by-route quantities, environmental compliance, post-dredge survey and accepted channel condition. The planned split should not be reported as completed beneficial use or disposal.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Buffalo District video shows an excavator working from a spudded platform and loading dredged sediment into a scow. It confirms field operations but not measured production, final material routing or completion.
The district reported a USD 1.1 million Geo Gradel contract, approximately 59,000 cubic yards and a planned split of about 50,000 cubic yards nearshore and 9,000 cubic yards to an open-lake area, with work continuing through August.
The federal work plan funded sediment and environmental preparation
USACE listed Rocky River for environmental coordination and sediment sampling and analysis. That preparation supports later dredging decisions but did not itself establish the 2026 contract, selected routes or completed field work.