Location
São Tomé and Príncipe / Africa
Project record
São Tomé and Príncipe's USD 21.9 million BEFIRM programme has signed AfDB financing and defined marine scope at Neves, Porto Alegre, and Chimalô. Official safeguards describe a replacement Porto Alegre quay with about 1,940 m³ of foundation dredging, a 4.0-metre operating-depth and 3,200 m² logistics interface at Neves, and cold-chain and logistics works at Chimalô. The works contractor, notice to proceed and construction start are not disclosed.
São Tomé and Príncipe / Africa
Marine infrastructure
AfDB financing signed and three site-level safeguard packages disclosed; design-supervision and works awards remain unverified / Confirmed
1 August 2026
Coverage
Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogMapAfrica records UA 15 million from the Transition Support Facility and UA 1.5 million from the African Development Fund. Signature moves the programme beyond board approval but does not establish effectiveness, disbursement, procurement, or works execution.
SourceThe announcement identifies Neves, Porto Alegre, and Chimalô for rehabilitation, disaster-management support at Port Santo António Praia, 400 fiberglass boats, six cold stores, four refrigerated trucks, and implementation across 2026-2030. These are programme outputs, not awarded quantities or accepted assets.
SourceBoard approval established the financing baseline and planned 31 December 2030 completion. Design, supervision, floating-quay, dredging and civil-works packages remained unawarded at this stage.
SourceAfDB disclosures cover Chimalô, Neves, and Porto Alegre. They establish concept-level quay, dredging, operating-depth, logistics, cold-chain, utility, resettlement, and environmental controls while remaining pre-contract design and safeguard records.
SourceThe appraisal report records an identification mission from 24 November to 11 December 2023 that confirmed the need for separate environmental and social studies at Chimalô, Neves-Rosema, and Porto Alegre. This is the earliest reviewed site-definition gate, not a construction start.
SourceEvidence gap