Can Gio International Transshipment Port

Project rendering of the planned Can Gio container berths at Go Con Cho beside the Cai Mep estuary

Saigon Port; project rendering, not construction evidence

Ho Chi Minh City has selected Vietnam Maritime Corporation, Saigon Port and Terminal Investment Limited Holding as the investor consortium for Can Gio. The approved concept covers about 571 hectares at Go Con Cho, a 7.5-kilometre main berth line and capacity for vessels up to 250,000 DWT. No marine works contract or construction mobilisation has been announced.

Project signal

Approval in Vietnam

Current status Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced Source confidence Confirmed

Location

Vietnam / Asia Pacific

Segment

Deep-water ports and container terminals

Status

Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced / Confirmed

Last checked

20 July 2026

Coverage

Related sectors

Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Ho Chi Minh City People's Committee; investor consortium led by Vietnam Maritime Corporation
Delivery parties
Developer consortium: Vietnam Maritime Corporation, Saigon Port and Terminal Investment Limited Holding S.A., Marine works contractors not identified
Contract route
Ho Chi Minh City approved the investor consortium under Decision 2155/QD-UBND after the Prime Minister approved the investment policy under Decision 148/QD-TTg. The later marine design, enabling works, dredging, reclamation, quay and terminal construction procurement packages remain undisclosed.
Execution window
The approved programme targets about 4.8 million TEU of capacity by 2030 and 16.9 million TEU by 2047. Public reporting also describes a 20-year implementation period from physical handover of land and water. These are programme targets, not evidence of a current construction start or a fixed package completion date.
Works package
A planned international container transshipment port on about 571 hectares of land and water at Go Con Cho, with roughly 7.5 kilometres of main berths. The initial plan provides two to four berths for vessels up to 250,000 DWT, expanding over time to about 13 berths. Dredging, reclamation, ground-improvement, quay-foundation, material-route and individual construction-lot quantities remain unpublished.
Marine interfaces
The site lies at the Cai Mep estuary on the left side of the Vung Tau-Thi Vai navigation channel, opposite the established Cai Mep terminal cluster. Delivery must resolve berth geometry beside a live deep-water route, land and water boundaries, vessel manoeuvring, construction access and the interface with Can Gio's mangrove and forest estate. Nearly 83 hectares of forest land are identified for repurposing in the investment-policy record.
Commercial evidence boundary
The scale is material, but the opportunity remains upstream of works procurement. The investor consortium and capital envelope are public; marine quantities, package splits, qualification route, contract values, risk allocation, accepted design levels and construction schedule are not. A credible supply or contracting position depends on the feasibility design, environmental conditions and tender documents rather than the headline 571-hectare footprint.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Ho Chi Minh City selected the investor consortium

Decision 2155/QD-UBND approved Vietnam Maritime Corporation, Saigon Port and Terminal Investment Limited Holding as the project investor. The decision establishes the developer group, not a marine construction award.

Source

Saigon Port approved its consortium and capital position

Shareholders authorised Saigon Port to join VIMC and MSC/TiL in the investor application and to take 15% of the project company's charter capital after approval.

Source

The Prime Minister approved the investment policy

Decision 148/QD-TTg moved Can Gio into the formal investment process and set the basis for investor selection. It did not award the later design or construction packages.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Project enterprise formation and final consortium capital commitments
  • Environmental impact assessment approval and disclosed marine conditions
  • Forest conversion, land allocation and water-surface handover
  • Approved feasibility design and berth, basin and navigation geometry
  • Dredging, reclamation, ground-improvement and material-management quantities
  • Quay, bridge, utility and terminal package boundaries
  • Works tender, named contractor, contract value and notice to proceed
  • Baseline hydrography, mobilisation and first verified marine production
  • Accepted berth depth, terminal handover, trials and first repeat services

Reporting status

Approval, confirmed confidence

Last checked 20 July 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 20 July 2026 Cited sources 6