Award Boundary

Durban's ZAR 5.47m revetment award leaves delivery unverified

Published 11 August 2026 Updated 16 August 2026 Publisher IMWO Region Africa Confidence Confirmed
Official Port of Durban North Bank revetment cross-section showing armour, 50-100 kg rock and filter layers

Transnet National Ports Authority tender document; exact project engineering figure; public procurement record

National Treasury's active award record names KATLANTIC at ZAR 5,466,159, while TNPA's RFP fixes the workfront at a damaged entrance-channel section requiring approximately 1,000 m3 of 50-100 kg rock. Neither source confirms contract signature, notice to proceed, installed quantities or completion.

KATLANTIC and the award value are now confirmed

National Treasury lists the active award, KATLANTIC and ZAR 5,466,159. TNPA's RFP and rock specification define the technical and commercial tender boundary. The release has no award date or contract object, and National Treasury warns that the publication is not a complete record of all South African procurement.

The tender defines a traceable rock-placement package

The RFP turns a generic coastal-repair notice into a usable supply-chain boundary: landside survey, rock sourcing, sorting, transport, placement and out survey in a live port entrance. That makes quarry approval, grading, haulage and survey the relevant workstreams. It does not justify assigning unnamed subcontractors or floating-plant and diving roles from generic tender clauses.

Evidence conclusion

Contract and survey records determine delivery status

The ZAR 5.47 million award should be treated as prime-award evidence only. The 30 January 2024 release date is the tender publication date, not an award date, and the three-month period is a tender requirement rather than an actual programme. The approximately 500 metre revetment and its 0.7-1.4 tonne armour describe the existing asset; the awarded tender scope is a localised cavity repair using about 1,000 m3 of 50-100 kg rock. The next credible delivery signals are an executed NEC3 contract, notice to proceed, in-survey, approved rock source, placement records and out survey.

Outstanding evidence

  • Award date, executed NEC3 contract and notice to proceed
  • Approved quarry or rock source and compliance testing
  • In-survey and agreed damaged-section geometry
  • Landside haulage and no-stockpile sequencing
  • Entrance-channel vessel-traffic coordination
  • Placed quantity, interim surveys and out survey
  • Completion certificate, owner acceptance and final account
  • Named survey, testing, haulage or other lower-tier contractors