Project record
USACE Buffalo District awarded Ryba Marine Construction a USD 2.3 million contract for approximately 190,000 cubic yards of mechanical dredging from Buffalo Harbor's outer-harbor and river federal channels. The published plan sends about 110,000 cubic yards to confined disposal facility #4 and about 80,000 cubic yards to Shipping Slip 3 for a future 6.7-acre wetland.
United States / Americas
Port infrastructure
USD 2.3 million Ryba award confirmed; field start scheduled from 18 July 2026 / Confirmed
17 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The release identifies Ryba, a USD 2.3 million award, approximately 190,000 cubic yards, a start as early as 18 July, and separate CDF #4 and Slip 3 quantities. These are contracted and planned values, not measured field results.
Read controlling sourceUSACE and Erie Canal Harbor Development Corporation described a 6.7-acre Slip 3 wetland requiring approximately 285,000 cubic yards over an estimated three dredging cycles, followed by planting and habitat features. That programme baseline does not establish current fill or ecological performance.
Read controlling sourceUSACE awarded Ryba a separate USD 991,500 contract for approximately 80,000 cubic yards routed to the harbor CDF. That earlier contract shows recurring two-year maintenance but is not evidence of 2026 production.
Read controlling sourceDelivery watch
Accountable evidence of mobilisation from 18 July, followed by route-specific measured placement and post-dredge channel surveys
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerUSACE's 17 July 2026 release controls the current award, contractor, 190,000-cubic-yard scope, planned start and 110,000/80,000-cubic-yard routing split. That release stops before mobilisation, production or completion. The December 2023 wetland release defines Slip 3's 6.7-acre target and approximately 285,000 cubic yards over several dredging cycles; the current 80,000 cubic yards is one planned contribution, not wetland completion. The Buffalo Harbor and CDF #4 fact sheets provide channel and facility baselines. The 2022 Ryba award is historical campaign context only.
Phase: award. Evidence reviewed: 17 July 2026.