Dredged Material

Buffalo Harbor splits its 2026 dredging between disposal and a future wetland

Published 17 July 2026 Updated 16 August 2026 Publisher IMWO Region Americas Confidence Confirmed
Ryba Marine's clamshell dredge loading Buffalo Harbor sediment into a material scow in September 2020

Jess Levenson, U.S. Army Corps of Engineers; historical Buffalo Harbor operations, not 2026 mobilisation

Buffalo Harbor's 2026 maintenance package will mechanically remove approximately 190,000 cubic yards from deep-draft federal channels. The planned routing sends about 110,000 cubic yards to CDF #4 and about 80,000 cubic yards to Shipping Slip 3, whose containment breakwater was completed in 2024. Slip 3 placement is the second phase of a 285,000-cubic-yard programme expected to continue through 2028; habitat formation follows after the required fill level is reached.

Published scope and current milestone

The 17 July USACE release identifies the 2026 award, contractor, quantities, material routes and planned dates, but does not report field production. The October 2025 harbor fact sheet gives channel lengths, depths and maintenance history. The 2023 wetland release defines the three-phase works, 6.7-acre target and approximately 285,000-cubic-yard fill requirement. ECHDC's current page confirms the 2024 breakwater completion and placement programme through 2028. The photograph shows Buffalo Harbor dredging by Ryba in September 2020 and is historical operational context, not evidence of 2026 mobilisation.

Dredging quantity and delivery implications

This is both navigation maintenance and beneficial use, but the two outputs are not interchangeable. The harbor serves channels authorized from 22 to 30 feet and closes on excavation quantities and hydrographic condition. Slip 3 closes first on accepted material and fill elevation, then on native vegetation, habitat structures and ecological performance. The 2026 campaign can advance both programmes without completing the wetland.

Evidence conclusion

Survey, placement and acceptance evidence

The USD 2.3 million award fixes contractor, planned quantity and destinations, while the 17 July notice remains prospective. The announced 1-25 August Slip 3 window should yield destination receipts and a revised fill elevation; the wider wetland page still shows placement continuing through 2028. Confirmation of the route split matters because CDF #4 and Slip 3 have different acceptance purposes, and only post-dredge surveys can establish whether the navigation reaches were restored to their maintained depths.

Outstanding evidence

  • Confirmed mobilisation from the planned 18 July start
  • Daily and final measured dredging quantities by reach
  • Actual receipt totals at CDF #4 and Slip 3
  • Sediment testing and placement approvals
  • Post-dredge survey against authorized depths of 22 to 30 feet
  • Slip 3 fill elevation and cumulative progress toward 285,000 cubic yards
  • Native planting, habitat-feature installation and later ecological monitoring