Project record
Madagascar's signed US$305 million transport programme allocates US$102.24 million to ports and waterways: US$30 million for Majunga, US$32 million for Tulear and US$29.94 million for 200 kilometres of the Pangalanes Canal. The May procurement plan records a US$28 million Majunga works package pending implementation and a US$6.36 million canal maintenance and dredging-fleet package under review, while Tulear's main works and the canal's main dredging works were not listed as active works packages in that revision.
Madagascar / Africa
Marine infrastructure
IDA financing signed; marine packages are planned, under review, pending, cancelled, or absent from the reviewed plan / Confirmed
15 July 2026
Coverage
Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogAIIB's project page confirms direct co-financing intent, Category A treatment and the same no-port-dredging versus canal-dredging boundary. Proposed status is not financing approval or effectiveness, and the IDA agreement sets 31 March 2027 as the co-financing deadline.
SourceCredits 8004-MG and 8005-MG moved the World Bank financing from approval into a signed legal framework for a US$305 million project. Signature did not activate unissued marine packages, satisfy co-financing conditions or evidence physical works.
SourceThe plan recorded the US$28 million Majunga works package as pending implementation, the US$6.36 million canal maintenance and dredging-fleet package under review, and a US$1.2 million landing-stage package cancelled. It listed no active main Tulear or canal-dredging works package, and planned dates do not confirm later notices or awards.
SourceThe approval record dates the IDA financing decision before the 28 April public announcement. It confirms the programme, while component safeguards, tenders, contractors, mobilisation and accepted navigation outcomes remain later steps.
SourceThe PAD allocated US$30 million to Majunga, US$32 million to Tulear and US$29.94 million to the Pangalanes Canal within an eight-subcomponent port and waterway programme. These are programme allocations, not contract values or awarded amounts.
SourceThe appraisal PID and ESRS defined existing-quay work at Majunga and Tulear without port dredging and assigned spot dredging, turbidity, freshwater habitat and dredged-material management to Pangalanes. Site-specific instruments remained required before related bidding and works.
SourceThe concept ESRS defined the three transport corridors and early high-risk environmental and social framework. It remained a preparation-stage baseline, with final budgets, package design and procurement status unset.
SourceEvidence gap