Project record

Oswego Harbor 2026 breakwater repair phases

Large armourstone along the Oswego Harbor breakwater with the port and Lake Ontario beyond in May 2022

Avery Schneider, U.S. Army; Oswego Harbor context from May 2022, not 2026 construction progress

USACE Buffalo District awarded Dean Marine and Excavating USD 14.9 million to repair 425 feet of the East Arrowhead breakwater and 307 feet of the Outer West breakwater at Oswego Harbor. It is the second of three funded phases covering more than 1,330 feet; a separate 600-foot Outer West package is already under way.

Project signal

Award in United States

Current status USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028 Source confidence Confirmed

Location

United States / Americas

Segment

Port infrastructure

Status

USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028 / Confirmed

Last checked

14 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
U.S. Army Corps of Engineers, Buffalo District
Delivery parties
Dean Marine and Excavating, Great Lakes Dock and Materials
Contract route
Three-phase, federally funded breakwater repair programme; phase two awarded to Dean Marine and Excavating on 30 April 2026
Execution window
Phase one began in August 2025 and was scheduled through winter 2026; phase two is planned from summer 2026 through 2028; phase three construction is targeted for 2027
Works package
Phase one repairs 600 feet of Outer West under a USD 9.1 million contract. Phase two repairs 425 feet of East Arrowhead and 307 feet of Outer West under the USD 14.9 million Dean Marine award. A funded third phase is planned to continue work on both breakwaters.
Marine interfaces
Armourstone breakwater reconstruction from marine plant beside an open federal navigation channel, with separate work limits on the East Arrowhead and Outer West structures. The channel and breakwaters support vessel access for aluminum, grain, corn, soybeans, wind components, rock salt and other cargo, but no cited source quantifies restriction hours or phase-specific operating effects.
Commercial evidence boundary
The new award commits a defined 732-foot package, but it is not a notice that work has started. The first package also remains open until its 600-foot reach is inspected and accepted. Contractor, length and close-out therefore remain separate phase-level fields.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

USACE awarded the 732-foot second repair phase

Dean Marine and Excavating received a USD 14.9 million contract covering 425 feet of East Arrowhead and 307 feet of Outer West. USACE planned a summer 2026 start, but the award does not establish mobilisation or production.

Source

The 600-foot Outer West phase moved into construction

USACE recorded the start of the USD 9.1 million Great Lakes Dock and Materials package after completing the separate 2,700-foot West Arrowhead repair. The current programme should not merge those two work limits.

Source

USACE awarded the first Outer West package

The USD 9.1 million contract set a 600-foot rubble-mound overlay scope with completion scheduled for winter 2026. That package has a different contractor and acceptance path from the 2026 award.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dean Marine mobilisation on the phase-two work limits
  • Stone delivery and placement by East Arrowhead and Outer West section
  • Marine traffic controls while the federal navigation channel remains open
  • Surveyed or inspected length completed under the 600-foot phase-one package
  • Phase-two completion and acceptance against the 425-foot and 307-foot limits
  • Phase-three contract details and the planned 2027 construction start

Reporting status

Award, confirmed confidence

Last checked 14 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 14 August 2026 Cited sources 5