USACE Buffalo District awarded Dean Marine and Excavating USD 14.9 million to repair 425 feet of the East Arrowhead breakwater and 307 feet of the Outer West breakwater at Oswego Harbor. It is the second of three funded phases covering more than 1,330 feet; a separate 600-foot Outer West package is already under way.
Project signal
Award in United States
Current statusUSD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028Source confidenceConfirmed
Location
United States / Americas
Segment
Port infrastructure
Status
USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028 / Confirmed
Last checked
14 August 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Buffalo District
Delivery parties
Dean Marine and Excavating, Great Lakes Dock and Materials
Contract route
Three-phase, federally funded breakwater repair programme; phase two awarded to Dean Marine and Excavating on 30 April 2026
Execution window
Phase one began in August 2025 and was scheduled through winter 2026; phase two is planned from summer 2026 through 2028; phase three construction is targeted for 2027
Works package
Phase one repairs 600 feet of Outer West under a USD 9.1 million contract. Phase two repairs 425 feet of East Arrowhead and 307 feet of Outer West under the USD 14.9 million Dean Marine award. A funded third phase is planned to continue work on both breakwaters.
Marine interfaces
Armourstone breakwater reconstruction from marine plant beside an open federal navigation channel, with separate work limits on the East Arrowhead and Outer West structures. The channel and breakwaters support vessel access for aluminum, grain, corn, soybeans, wind components, rock salt and other cargo, but no cited source quantifies restriction hours or phase-specific operating effects.
Commercial evidence boundary
The new award commits a defined 732-foot package, but it is not a notice that work has started. The first package also remains open until its 600-foot reach is inspected and accepted. Contractor, length and close-out therefore remain separate phase-level fields.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Dean Marine and Excavating received a USD 14.9 million contract covering 425 feet of East Arrowhead and 307 feet of Outer West. USACE planned a summer 2026 start, but the award does not establish mobilisation or production.
The 600-foot Outer West phase moved into construction
USACE recorded the start of the USD 9.1 million Great Lakes Dock and Materials package after completing the separate 2,700-foot West Arrowhead repair. The current programme should not merge those two work limits.
The USD 9.1 million contract set a 600-foot rubble-mound overlay scope with completion scheduled for winter 2026. That package has a different contractor and acceptance path from the 2026 award.