Mumbai Marina Bids Need a Defined Marine-Asset Handover
Mumbai Port is procuring a 45-year marina concession while undertaking Phase I marine works. Bidders need to connect the revenue offer to the condition, capacity and release dates of the assets they will operate.
Port-built marine works feed a long operating concession
The Ministry of Ports, Shipping and Waterways describes a 45-year DBFOT concession at Victoria Dock with an estimated project cost of INR 922.67 crore. Mumbai Port has commenced marine works including a piled breakwater and approximately 150 m approach trestle, six service platforms, pontoons, gangways and capital dredging. Phase I provides for 424 berths within a planned full build-out of 604. The concessionaire develops landside facilities, additional berthing and long-term operations [1].
Delay relief follows the affected work, with limited port liability
RFP Clause 1.2.7 selects the highest gross-revenue share, subject to an 11.50% floor [5]. The draft concession agreement makes the marine release a pricing issue. Article 6.3(d) provides for extending completion and milestone dates to the extent the concessionaire's work is affected by delayed port works, as determined by the Independent Engineer. It also provides concession-period relief and approved operation of completed facilities; the clause limits the port's further liability on that account [4]. A delayed berth opening leaves the bidder carrying interest, staff and maintenance expenditure before the expected marina income. Those continuing costs need to enter the bid model alongside the specific time and concession remedies.
Evidence conclusion
Price the survey handover and the recurring dredging boundary
Appendix 4 Part B requires at least 30 days' written notice of each intended handover, as-built drawings and test certificates, plus certified survey data for dredging. It assigns initial Phase I basin dredging to -4.50 m Chart Datum to the port. Recurring maintenance then divides geographically: the port retains the P&V approach channel, while the concessionaire maintains the marina basin [4]. The operator's quantity and maintenance model should follow that surveyed boundary and starting bed condition. Concessionaire-requested changes that add cost to the port's works require prior approval, Independent Engineer certification and advance payment under Part B Section 2.1. Layout changes can therefore consume cash before the revised assets earn revenue. The official list retains a 15 December 2026,15:00 bid deadline; its sole listed corrigendum supplies the 30 October meeting link [2,3]. These are tender-stage draft terms to resolve before fixing the revenue-share offer.
Outstanding evidence
- Affected-work assessment and the draft delay remedies
- Certified as-dredged survey and basin/channel maintenance boundary
- Change-cost payments and phased revenue availability
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Mumbai Marina: DBFOT invitation and division of marine and concession works Press Information Bureau / Ministry of Ports, Shipping and Waterways, 21 October 2026
- Civil engineering tender list, CE.T.77/2026 Marina PPP Mumbai Port Authority, List read 1 November 2026
- Corrigendum I: video link for the 30 October pre-bid meeting Mumbai Port Authority, 29 October 2026
- Draft concession agreement: Article 6.3(d), Appendix 4 Part B and change costs Mumbai Port Authority, Tender document published 13 October 2026
- Request for proposal: Clause 1.2.7 revenue-share competition Mumbai Port Authority, 13 October 2026