West Bengal 45-jetty contract ledger

Khardah Ferry Ghat and passenger vessels on the Hooghly River, one named Phase I jetty location

Kha Subhendu, Khardah Ferry Ghat and Hooghly River, via Wikimedia Commons, CC BY-SA 4.0; named-location context, not evidence of contract completion or acceptance

West Bengal Transport Infrastructure Development Corporation's 45-location passenger-jetty programme can now be traced through 21 direct works awards in the World Bank supplier-contract dataset: 13 contracts for the 29 Phase I jetties and eight contracts for the 16 Phase II jetties. The reported supplier commitments total USD 24,836,527.26. That arithmetic closes the prime-contract map, not the delivery record: the latest implementation report contains incompatible statements on whether Metiabruze remains under implementation or all 45 jetties are complete.

Project signal

Construction in India

Current status World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete Source confidence Confirmed

Location

India / Asia Pacific

Segment

Inland-waterway floating jetties, gangways and passenger facilities

Status

World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete / Confirmed

Last checked

6 August 2026

Coverage

Related sectors

Inland-waterway floating jetties, gangways and passenger facilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
West Bengal Transport Infrastructure Development Corporation Limited under the World Bank-financed P166020 programme
Delivery parties
B N Bose & Company (Marine) Private Limited - Phase I Lot SL-1, Jana & Brothers - Phase I Lot SL-3 and Phase II 15-location Lot 5, A.C. Roy & Co / A C Roy Shipbuilders Private Limited - Phase I Lots SL-4 and SL-9 and Phase II 15-location Lot 1, Paritosh Ghosh Construction Private Limited - Phase I Lots SL-5 and SL-7 and Phase II 15-location Lot 2, Nalanda Engineering Enterprise - Phase I Lots SL-6 and SL-11 and Phase II 15-location Lot 3, Patra Shipping Private Limited - Phase I Lots SL-8 and SL-13, Phase II 15-location Lot 4 and four-location Lot 2, Milan Marine Service - Phase I Lot SL-10, Phase I second call and Kukrahati, P.G. Enterprise - Phase I Lot SL-12 and four-location Lot 1, Fabrication, piling, marine-plant, electrical, passenger-facility and other lower-tier parties - not identified in the reviewed public records
Contract route
The identified works were procured through World Bank-financed national Request for Bids packages under P166020. Phase I's main package, IN-WBTIDCL-145628-CW-RFB, produced 12 signed lot awards on 7 January 2021; its second call produced one award on 20 June 2022. Phase II's 15-location first call produced five lot awards on 4 April 2024, the four-location second call produced two awards on 16 August 2024, and Kukrahati was signed on 6 March 2024. July 2026 STEP data keep all five package rows at Signed rather than publishing actual contract-completion dates.
Execution window
The 13 Phase I contracts cover 29 jetties; their published planned completion dates have passed. The eight Phase II contracts cover 16 jetties, with the latest procurement plan showing planned completion in May, June and October 2025 depending on package. On 22 June 2026 the ISR narrative reported 44 of 45 locations complete and Metiabruze under implementation, while the same report's results table said all 45 were complete. The project currently closes on 30 September 2026; the June restructuring paper describes a possible second extension to September 2027 as contingent.
Works package
The award map covers design, fabrication, installation or reconstruction and commissioning of gangway-cum-pontoon and floating passenger jetties, plus passenger facilities and amenities, at 45 Hooghly River and connected inland-waterway locations. Phase I's main awards name 27 locations, and the second call adds Chandpal Ghat-2 and Noorpur. Phase II comprises the 15-location package plus Kukrahati; the separately published four-location second-call lots form part of that Phase II procurement chain rather than four additional programme locations.
Marine interfaces
The works combine floating pontoons, steel gangways, piles and moorings with tidal-river levels, vessel approaches, live ferry services, shore-side passenger access, utilities, accessibility and statutory vessel or structure requirements. The public contract descriptions do not establish pontoon dimensions, gangway spans, pile schedules, marine spreads, fabricators, electrical suppliers, tests, as-built quantities or acceptance at each location.
Commercial evidence boundary
The 21 supplier commitments sum to USD 24,836,527.26: USD 14,169,203.22 for the 13 Phase I contracts and USD 10,667,324.04 for the eight Phase II contracts. These are reproducible award-dataset amounts, not certified payments or final costs. They should not be compared with procurement estimates as savings without variation, quantity, retention, defects and final-account evidence.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Phase I main package

IN-WBTIDCL-145628-CW-RFB - 12 lot awards covering 27 named locations

Named party
B N Bose, Jana & Brothers, A.C. Roy, Paritosh Ghosh, Nalanda Engineering, Patra Shipping, Milan Marine Service and P.G. Enterprise
Status
Confirmed
Source position
Contracts 1641635, 1641655, 1641656, 1641658, 1641659, 1641662, 1641663, 1641664, 1641665, 1641667, 1641669 and 1641672 were signed on 7 January 2021 and total USD 13,118,322.44. That exact sum matches the latest procurement plan's actual amount. Source
Phase I second call

IN-WBTIDCL-145628-CW-RFB/ 2ND CALL - Chandpal Ghat-2 and Noorpur

Named party
Milan Marine Service
Status
Confirmed
Source position
Contract 1704371 was signed on 20 June 2022 with a reported supplier commitment of USD 1,050,880.78, bringing the 29-location Phase I award map to 13 contracts and USD 14,169,203.22. Source
Phase II 15-location first call

IN-WBTIDCL-379989-CW-RFB - five lot awards

Named party
A C Roy Shipbuilders, Paritosh Ghosh, Nalanda Engineering, Patra Shipping and Jana & Brothers
Status
Confirmed
Source position
Contracts 1810128 to 1810132 were signed on 4 April 2024 and total USD 6,974,437.91. The public award descriptions identify lots 1-5 but do not allocate exact locations within each lot. Source
Phase II four-location second call

IN-WBTIDCL-379989-CW-RFB 2ND CALL 2LOTS - Tamlipara, Chinsurah, Metiabruze and Pujali

Named party
P.G. Enterprise and Patra Shipping Private Limited
Status
Confirmed
Source position
Contracts 1801669 and 1801670 were signed on 16 August 2024 and total USD 2,723,396.21. IMWO also tracks this two-contract subset as the Hooghly four-location floating passenger-jetties child project. Source
Phase II Kukrahati

IN-WBTIDCL-399912-CW-RFB - Kukrahati New Ferry Ghat

Named party
Milan Marine Service
Status
Confirmed
Source position
Contract 1809510 was signed on 6 March 2024 with a reported supplier commitment of USD 969,489.92. Source
Programme closeout

Acceptance across 45 jetty locations

Named party
WBTIDCL and World Bank
Status
Reported
Source position
The 22 June 2026 ISR narrative says upgrades are complete at 44 of 45 locations and Metiabruze remains under implementation. Its results table says all 29 Phase I and all 16 Phase II jetties are complete. Neither statement supplies a location acceptance ledger. Source

Evidence gap

What remains unverified

Outstanding evidence

  • Corrected World Bank or WBTIDCL statement reconciling 44 and 45 completed locations
  • Metiabruze physical completion, commissioning and owner acceptance
  • Location-by-location acceptance dates for all 29 Phase I and 16 Phase II jetties
  • Pontoon, gangway, pile, mooring and passenger-facility as-built scope
  • Fabricators, piling contractors, marine plant, electrical and civil lower tiers
  • Final values, variations, certified payments, retention and defects obligations for all 21 contracts
  • Actual completion fields replacing Signed-only package states in STEP
  • Any September 2027 extension and its effect on unresolved package closeout

Reporting status

Construction, confirmed confidence

Last checked 6 August 2026 across 8 cited sources. The dated timeline above carries the project events.

Last checked 6 August 2026 Cited sources 8