Floating Jetties

West Bengal's 21 jetty contracts leave Metiabruze acceptance unresolved

Published 6 August 2026 Publisher IMWO Region Asia Pacific Confidence Confirmed
Sovabazar Ferry Ghat on the Hooghly River, one named Phase I passenger-jetty location

Biswarup Ganguly, Sovabazar Ferry Ghat, via Wikimedia Commons, CC BY 3.0; named-location context, not evidence of 2026 programme completion or acceptance

World Bank supplier data now identify every direct works award used to map West Bengal's 29 Phase I and 16 Phase II floating passenger jetties. The 21 contracts carry USD 24,836,527.26 in reported supplier commitments across eight contractor groups. Prime-contract identification is complete, while the latest implementation report still says both 44 and 45 locations are complete.

All 21 direct works awards are now attributable

The World Bank supplier-contract dataset confirms all 21 contract numbers, prime suppliers, signature dates and reported commitments. The July 2026 procurement plan confirms the five package rows and planned completion boundaries. The June 2026 ISR contains the 44-of-45 narrative and 45-of-45 results-table conflict. No cited source proves location-level acceptance, final cost or lower-tier appointments.

Metiabruze keeps programme acceptance unresolved

The award map changes procurement analysis from a programme-level estimate into a contract-level evidence chain. It identifies which firms hold each phase and call, but the same precision exposes what remains absent: exact Phase II first-call site allocation, lower-tier fabricators and installers, final values, location acceptance and a reconciled Metiabruze status.

Evidence conclusion

Programme status remains construction pending owner acceptance

Outstanding evidence

  • A corrected World Bank ISR or WBTIDCL completion statement
  • Metiabruze commissioning and owner acceptance
  • Location-specific acceptance records for all 45 programme sites
  • Exact site allocation across Phase II 15-location Lots 1-5
  • Pontoon, gangway, piling, mooring and passenger-facility as-builts
  • Named fabrication, marine-plant, electrical and civil lower tiers
  • Final values, variations, payment and defects closeout across 21 contracts
  • Actual completion dates replacing Signed-only procurement-plan states