Location
Burundi / Africa
Project record
Bujumbura Port now has three distinct delivery tracks. The active AfDB/EU Phase I package covers a 545-metre protective dike, basin and harbour dredging, repaired and new quays, passenger and Ro-Ro facilities, a marine dock, equipment, and 11.7 kilometres of access roads. A separate JICA package was handed over in October 2024. A UNDP/EU engineering study presented in March 2026 defines a further climate-resilience planning track rather than completed construction.
Burundi / Africa
Marine infrastructure
Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline / Confirmed
21 July 2026
Coverage
Marine infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe study followed the 2024 Lake Tanganyika flooding and proposes phased reinforcement, drainage, and resilient expansion measures. It creates a planning and investment track; it does not establish completion or new physical progress of the active Phase I marine works.
SourceThe notice confirms continued activity within the wider corridor programme. Its scope is not a progress certificate for the protective dike, dredging, quays, marine dock, roads, or port equipment.
SourceAfDB, the EU, and Burundi set the latest reviewed quantitative baseline and an end-2026 target for the infrastructure works. The release also identified follow-on quay and marine-dock works and 11.7 kilometres of access roads.
SourceThe completed package covered container-terminal, ship-repair, drainage-diversion, and basin improvements. Its handover must remain separate from the active AfDB/EU Phase I dike, dredging, quay, dock, road, and equipment scope.
SourceLe Renouveau identified Khoury Contracting Company and reported delay associated with plan validation and imported equipment. The record established delivery risk rather than an accepted completion percentage.
SourceThe contract start defines the original execution baseline for the active AfDB/EU package. Subsequent inspection evidence displaced that original window and moved the working infrastructure target to end-2026.
SourceThe statutory change removes rail regulation from the authority and corrects the current owner-side name. Historical project documents still name AMPF; the change does not alter the KCC works contract, scope, progress baseline, schedule, or acceptance status.
SourceThe lender baseline combines port and access-road rehabilitation, port facilities, institutional support, trade facilitation, and project management. MapAfrica currently lists the programme as ongoing with planned completion on 31 December 2027.
SourceEvidence gap