Location
Burundi / Africa
Project record
Bujumbura Port now has three distinct delivery tracks. The active AfDB/EU Phase I package covers a 545-metre protective dike, basin and harbour dredging, repaired and new quays, passenger and Ro-Ro facilities, a marine dock, equipment, and 11.7 kilometres of access roads. A separate JICA package was handed over in October 2024. A UNDP/EU engineering study presented in March 2026 defines a further climate-resilience planning track rather than completed construction.
Burundi / Africa
Marine infrastructure
Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline / Confirmed
21 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The study followed the 2024 Lake Tanganyika flooding and proposes phased reinforcement, drainage, and resilient expansion measures. It creates a planning and investment track; it does not establish completion or new physical progress of the active Phase I marine works.
Read controlling sourceThe notice confirms continued activity within the wider corridor programme. Its scope is not a progress certificate for the protective dike, dredging, quays, marine dock, roads, or port equipment.
Read controlling sourceAfDB, the EU, and Burundi set the latest reviewed quantitative baseline and an end-2026 target for the infrastructure works. The release also identified follow-on quay and marine-dock works and 11.7 kilometres of access roads.
Read controlling sourceThe completed package covered container-terminal, ship-repair, drainage-diversion, and basin improvements. Its handover must remain separate from the active AfDB/EU Phase I dike, dredging, quay, dock, road, and equipment scope.
Read controlling sourceLe Renouveau identified Khoury Contracting Company and reported delay associated with plan validation and imported equipment. The record established delivery risk rather than an accepted completion percentage.
Read controlling sourceThe contract start defines the original execution baseline for the active AfDB/EU package. Subsequent inspection evidence displaced that original window and moved the working infrastructure target to end-2026.
Read controlling sourceThe statutory change removes rail regulation from the authority and corrects the current owner-side name. Historical project documents still name AMPF; the change does not alter the KCC works contract, scope, progress baseline, schedule, or acceptance status.
Read controlling sourceThe lender baseline combines port and access-road rehabilitation, port facilities, institutional support, trade facilitation, and project management. MapAfrica currently lists the programme as ongoing with planned completion on 31 December 2027.
Read controlling sourceDelivery watch
Obtain a dated post-March-2025 physical-progress record for the Phase I marine works; then confirm protective-dike completion, passenger/Ro-Ro quay and marine-dock start and acceptance, basin and outer-harbour dredging quantities and disposal route, road completion, equipment delivery, resilience-study investment decisions, and any reconciliation of the end-2026 infrastructure target with the 31 December 2027 programme date.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerBurundi's Decree No 100/118 created the current Autorité Maritime et Portuaire du Burundi (AMPB) on 27 March 2023 after the Council of Ministers decided to replace AMPF and separate rail regulation. Older ESIA, procurement, and contract records therefore retain AMPF as the historical client name; the correction does not change KCC's contract or any works milestone. AfDB's 17 March 2025 release records the 7 March field inspection and remains the latest reviewed official quantitative physical-progress source: a 545-metre protective dike at 45%, follow-on quay and marine-dock works, 11.7 kilometres of roads, an end-2026 infrastructure target, a EUR45.25 million package, and the 52/43/5 funding split. Burundi's responsible ministry independently recorded active port and RN9 works, progress below contractual expectations, and the need to accelerate delivery. Le Renouveau identifies KCC, the 24-month execution period from 1 July 2023, and earlier delay causes. The ESIA defines the marine and road scope. JICA's October 2024 record concerns a separate completed grant package. AfDB's current MapAfrica record lists the wider programme as ongoing through 31 December 2027. The February 2026 AfDB notice concerns adjacent fisher and enterprise-support works. UNDP's 26 March 2026 record concerns an engineering and resilience planning study after the 2024 flood damage. Neither 2026 item establishes new physical progress of the Phase I marine package.
Phase: construction. Evidence reviewed: 21 July 2026.