Project record

Bristol Pero's Bridge removal and repair

Participation
Requires review
Participation checked

Span removal scheduled for 2 November week

Participation source

Three bridge spans are scheduled for barge removal to Albion Dry Dock in November. Temporary mooring relocation and daylight-only movements define the marine access needed for the repair operation.

Bristol Pero's Bridge removal and repair project diagram: Three spans / heavy-lift barge; Daylight movement / cleared moorings; Albion Dry Dock / receiving workfront.

IMWO original project diagram; source: Bristol Harbour Authority

Location

United Kingdom / Europe

Segment

Moveable bridge marine access

Phase

Construction / Confirmed

Last checked

1 November 2026

Coverage

Related sectors

Moveable bridge marine access is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Bristol City Council / Bristol Harbour Authority
Delivery parties
Marine lifting and towage arranged for the November removal; current contractor appointment and full repair programme require the council contract records.
Contract route
Council repair-contract decisions recorded by the 15 September Harbour Committee. Harbour notice 48/26 governs the planned span removal and towage operation.
Execution window
Daylight lifting and vessel movements during the week of 2 November 2026. The harbour notice specifies removal to Albion Dry Dock rather than a bridge reopening date.
Works package
Lifting and removal of three bridge spans, barge transport to Albion Dry Dock and the associated clearance of affected moorings and transit workfront.
Marine interfaces
The floating lift position, tow route and receiving dock each require reserved space. Navigation restrictions can follow the barge manoeuvre beyond the immediate bridge opening.
Commercial evidence boundary
Mooring relocation and transit clearance determine when the lifting spread can work. A daylight-only movement programme needs a receiving slot as well as a crane booking.

Evidence gap

What remains unverified

Outstanding evidence

  • Daily lifting and towage instructions
  • Mooring clearance and Albion Dry Dock receiving arrangements
  • Survey movements and the specific locks needed for plant transit

Reporting status

Project phase
Construction
Evidence confidence
Confirmed
Last checked
1 November 2026
Cited sources
4