Project record
Patimban's operating first section sits beside an unfinished expansion. JICA's April-June 2025 monitoring records active reclamation, basin and access-channel dredging, quay-wall construction and pavement foundations across Package 5 and Package 6. Package 5 sand filling had reached 90.37% and basin dredging 68.54%; Package 6 sand filling was 54.81% and its reported access-channel dredging 1.92%. Those are work-item measures, not whole-port completion percentages.
Indonesia / Asia Pacific
Port infrastructure
Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date / Confirmed
19 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe April-June quarter records ongoing reclamation, dredging, quay and pavement work in Packages 5 and 6. It supplies measured work-item progress but no final marine acceptance or full terminal handover.
SourceThe monitoring report records 1,482 Package 5 PC deck slabs, or 100% of the bill-of-quantities item. Quay assembly, rubble, reclamation, dredging, pavement and terminal handover remained separate work fronts.
SourceThe investment in Patimban Global Gateway Terminal established another operating counterparty while the container terminal itself remained under construction. Operator formation is not civil completion or service release.
SourceThe JPY 83.408 billion agreement finances remaining Phase 1-2 terminal and dredging scope and sets 2028 as the planned point when facilities enter operation. The loan did not certify current construction or award later packages.
SourceThe start opened the separate car-terminal expansion work front under the TOA-led joint operation. It did not change the completed Phase 1-1 boundary or prove the Package 5 marine platform complete.
SourceThe Penta-Ocean-led consortium moved into execution on the 419 m berth, deepening, reclamation and ground-improvement package. Completion and terminal operation remained later gates.
SourceThe contractor fixed the five-company joint operation, a roughly USD 209 million value and the berth, quay, reclamation, dredging and terminal scope. Contract award did not establish physical progress or acceptance.
SourceThe contractor identified a six-company consortium and a roughly JPY 48.4 billion package covering the berth, dredging, reclamation, ground improvement and terminal civil works.
SourceEvidence gap