Patimban expansion remained in reclamation and dredging at mid-2025

Published 19 July 2026 Editorial responsibility IMWO Region Asia Pacific Confidence Confirmed
Official package drawing showing the Patimban Phase 1-2 Package 5 car-terminal expansion on the offshore port platform

TOA Corporation

JICA's April-June 2025 monitoring lists two different marine packages still in production at the end of the quarter. Package 5 was further ahead on sand fill, basin dredging and quay slabs; Package 6 had barely started its reported access-channel dredging measure and still had substantial reclamation and deck work open.

What changed

JICA's April-June 2025 report records Package 5 sand filling at 90.37%, seawall rock at 74.56%, basin dredging at 68.54% and quay deck-slab work at 92.98%. It records Package 6 sand filling at 54.81%, rock work on CDM at 71.74%, access-channel dredging at 77,471.08 m3 or 1.92%, and PC deck slabs at 87.59%. TOA and Penta-Ocean define the underlying Package 5 and 6 contract scopes. The Ministry's audited statement confirms completed Phase 1-1 handovers and keeps Packages 5 and 6 under construction. JICA's January 2025 loan agreement sets a 2028 programme target but does not establish current completion or Package 7 mobilisation.

Why it matters

Patimban is already a working car-export port, which makes the expansion easy to overstate. The operating first section does not mean the Phase 1-2 marine platform, new container berth or later terminal packages are finished. Residual-scope and capacity decisions depend on keeping the work-item percentages, package ownership and acceptance sequence separate.

Decision read

What remains open

The critical gap is no longer main-contract identification. It is evidence of accepted marine output. Package 5 still needed its basin, seawall, quay and terminal works brought through handover. Package 6 still faced a much larger dredging and reclamation path, followed by berth and terminal release. The next reliable change will be an owner or lender record tying final quantities and as-built depth to package acceptance. A later Package 7 award should be reported on its own line, not folded into Packages 5 or 6.

Next watchpoints

  • Package 5 final basin-dredging quantity and hydrographic acceptance
  • Package 5 seawall, quay, pavement, building and terminal handover
  • Package 6 access-channel dredging production and offshore-disposal close-out
  • Package 6 reclamation, ground improvement, berth and pavement acceptance
  • Package 7A and 7B award and mobilisation evidence
  • Container operator handover, equipment installation, trials and first repeat service
  • Water quality, fishing-ground and shoreline monitoring during marine production

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Sources used 7

Corrections and methodology

Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.