Patimban expansion remained in reclamation and dredging at mid-2025
JICA's April-June 2025 monitoring lists two different marine packages still in production at the end of the quarter. Package 5 was further ahead on sand fill, basin dredging and quay slabs; Package 6 had barely started its reported access-channel dredging measure and still had substantial reclamation and deck work open.
What changed
JICA's April-June 2025 report records Package 5 sand filling at 90.37%, seawall rock at 74.56%, basin dredging at 68.54% and quay deck-slab work at 92.98%. It records Package 6 sand filling at 54.81%, rock work on CDM at 71.74%, access-channel dredging at 77,471.08 m3 or 1.92%, and PC deck slabs at 87.59%. TOA and Penta-Ocean define the underlying Package 5 and 6 contract scopes. The Ministry's audited statement confirms completed Phase 1-1 handovers and keeps Packages 5 and 6 under construction. JICA's January 2025 loan agreement sets a 2028 programme target but does not establish current completion or Package 7 mobilisation.
Why it matters
Patimban is already a working car-export port, which makes the expansion easy to overstate. The operating first section does not mean the Phase 1-2 marine platform, new container berth or later terminal packages are finished. Residual-scope and capacity decisions depend on keeping the work-item percentages, package ownership and acceptance sequence separate.
Decision read
What remains open
The critical gap is no longer main-contract identification. It is evidence of accepted marine output. Package 5 still needed its basin, seawall, quay and terminal works brought through handover. Package 6 still faced a much larger dredging and reclamation path, followed by berth and terminal release. The next reliable change will be an owner or lender record tying final quantities and as-built depth to package acceptance. A later Package 7 award should be reported on its own line, not folded into Packages 5 or 6.
Next watchpoints
- Package 5 final basin-dredging quantity and hydrographic acceptance
- Package 5 seawall, quay, pavement, building and terminal handover
- Package 6 access-channel dredging production and offshore-disposal close-out
- Package 6 reclamation, ground improvement, berth and pavement acceptance
- Package 7A and 7B award and mobilisation evidence
- Container operator handover, equipment installation, trials and first repeat service
- Water quality, fishing-ground and shoreline monitoring during marine production
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 7
- Patimban Port environmental and social monitoring, April-June 2025 Japan International Cooperation Agency, 2025 Q2; posted 29 January 2026
- Patimban Port Development Project monitoring register Japan International Cooperation Agency, Publication date not stated; evidence reviewed 19 July 2026
- Patimban Port Development Project III Japan International Cooperation Agency, Current project page reviewed 19 July 2026
- Directorate General of Sea Transportation audited 2024 financial report Ministry of Transportation, Indonesia, 2025
- Award of Patimban Package 5 car-terminal construction TOA Corporation, 23 December 2022
- Award of Patimban Package 6 Container Terminal No. 2 construction Penta-Ocean Construction, 27 October 2022
- JICA signs the third Patimban Port Development loan Japan International Cooperation Agency, 13 January 2025
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.
Review methodology Open intelligence archive Submit a correction