Project record

Plymouth Mount Batten pontoon replacement

Official LHC Design visualization of Plymouth's Mount Batten replacement pontoon and accessible ferry landing, with bridge and berthing infrastructure

LHC Design via Mount Batten Centre; future-state design visualization, not construction-progress or completion evidence

Plymouth City Council signed Teignmouth Maritime Services Limited for design and construction of the Mount Batten replacement pontoon and bridgehead repairs. Find a Tender records GBP 3,201,127 excluding VAT, signature on 3 November 2025 and a 4 November 2025 to 31 August 2026 contract period. King's Harbour Master Plymouth opened a February-to-June marine works window for temporary-pontoon installation, permanent-pontoon installation, piling and diving. Weather delayed the barge, but the Mount Batten Centre records the temporary pontoon and bridge commissioned on 17 March. The permanent asset remains in delivery: no cited owner document establishes final installation, commissioning, handover or completion.

Project signal

Construction in United Kingdom

Current status Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed Source confidence Confirmed

Location

United Kingdom / Europe

Segment

Marinas, pontoons and berthing infrastructure

Status

Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed / Confirmed

Last checked

9 August 2026

Coverage

Related sectors

Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Plymouth City Council
Delivery parties
Teignmouth Maritime Services Limited - confirmed NEC4 ECC Option A design-and-build contractor, Pontoon fabricator, permanent piling supplier, linkspan supplier, diving subcontractor, environmental-tile supplier and marine-plant providers - no contract-specific organization disclosed
Contract route
Plymouth used a below-threshold open competition under Find a Tender OCID ocds-h6vhtk-05044f and local reference DN774869. Three tenders were received by 11 July 2025. The council approved the TMS award on 3 October, signed the contract on 3 November, and published contract-details notice 000756-2026 on 6 January 2026. The contract uses NEC4 Engineering and Construction Contract Option A with a priced activity schedule.
Execution window
Find a Tender records 4 November 2025 to 31 August 2026. King's Harbour Master notice 024/26 scheduled temporary-pontoon installation from 16 to 20 February and marine construction, including new pontoon installation and piling, from 23 February to 19 June, with diving throughout. Weather delayed the barge and temporary works into March. Plymouth later targeted permanent completion by late summer 2026. These dates do not establish accepted completion.
Works package
The core design-and-build scope includes removal and disposal of the existing pontoon, supply and installation of a replacement pontoon system, bridgehead and seawall repairs, piling as required, linkspan installation, accessibility facilities, environmental enhancements such as artificial reef or settlement tiles, and potential reuse of existing piles or linkspan elements where feasible. The awarded option configuration and final commercial-berth count are not fully resolved in the public notice chain.
Marine interfaces
The works sit beside an operating watersports centre and ferry route in the Dockyard Port of Plymouth. Delivery interfaces include temporary ferry continuity, slipway closures, barge access, piling, diving, navigation shapes, wash controls, bridgehead and seawall stability, tidal access, public safety, accessible water transfer and environmental features. The harbour notice proves a controlled marine work window but does not name vessels, plant owners or lower tiers.
Commercial evidence boundary
The signed main works contract is GBP 3,201,127 excluding VAT and GBP 3,841,352.40 including VAT. Plymouth's public release describes a GBP 4.2 million investment across the broader scheme. The values have different boundaries and must not be added or treated as a price increase. The council authorized limited modifications within an undisclosed contingency, while variations, certified payments, final account and exercised options remain unpublished.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Legal award

Mount Batten pontoon and bridgehead design-and-build works

Named party
Teignmouth Maritime Services Limited
Status
Confirmed
Source position
Find a Tender records a 3 November 2025 signature and GBP 3,201,127 excluding VAT under NEC4 ECC Option A. Source
Marine construction controls

Temporary pontoon, permanent pontoon, piling and diving

Named party
Teignmouth Maritime Services Limited under Plymouth and harbour controls
Status
Confirmed
Source position
King's Harbour Master notice 024/26 records the February-to-June 2026 work sequence and navigation precautions. Source
Temporary access facility

Temporary pontoon and bridge commissioning

Named party
Mount Batten Centre and project team
Status
Confirmed
Source position
The centre records successful installation and health-and-safety commissioning on 17 March 2026 after a weather-delayed barge arrival. Source
Ferry continuity

Temporary service interruption and resumption

Named party
Mount Batten Ferry
Status
Confirmed
Source position
The operator records weather-related extension of the interruption and service resumption on 14 March 2026. Source
Permanent asset completion

Replacement pontoon, bridgehead and seawall handover

Named party
Plymouth City Council and Teignmouth Maritime Services Limited
Status
Not evidenced
Source position
No cited source confirms permanent installation, commissioning, owner handover, accepted completion or final account.
Lower-tier delivery chain

Pontoon fabrication, piles, linkspan, diving, environmental features and marine plant

Named party
No contract-specific lower-tier organization named
Status
Undisclosed
Source position
The reviewed procurement, owner, harbour, operator and contractor sources identify no Mount Batten subcontractor or supplier.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Temporary pontoon and bridge commissioned

Ferry continuity resumed after enabling works, but this commissioning milestone neither installs nor accepts the permanent pontoon and bridgehead assets.

Source

Weather delays barge arrival

Marine plant could not depart Southampton as planned, shifting ferry suspension, temporary-berth installation and slipway-access dates into March.

Source

Controlled marine work window opens

The harbour notice exposes a sequenced temporary installation, permanent-pontoon, piling and diving campaign with live navigation and wash controls.

Source

Contract details notice fixes the signed award

The notice fixes TMS's signed responsibility, legal contract value, contract period and NEC4 Option A payment and delivery structure.

Source

Plymouth approves the TMS award

The officer decision names TMS at GBP 3,201,125.90 after three tenders, before the later rounded contract notice value.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Permanent pontoon installation, commissioning and owner handover
  • As-built pontoon dimensions, pile schedule and linkspan reuse
  • Final commercial-berth and accessibility configuration
  • Bridgehead, seawall and environmental-tile completion
  • Ferry transfer from the temporary to permanent facility
  • Named pontoon, piling, linkspan, diving and marine-plant lower tiers
  • Contract modifications, exercised options and final account
  • Navigation notice cancellation and operating acceptance

Reporting status

Construction, confirmed confidence

Last checked 9 August 2026 across 9 cited sources. The dated timeline above carries the project events.