Plymouth City Council signed Teignmouth Maritime Services Limited for design and construction of the Mount Batten replacement pontoon and bridgehead repairs. Find a Tender records GBP 3,201,127 excluding VAT, signature on 3 November 2025 and a 4 November 2025 to 31 August 2026 contract period. King's Harbour Master Plymouth opened a February-to-June marine works window for temporary-pontoon installation, permanent-pontoon installation, piling and diving. Weather delayed the barge, but the Mount Batten Centre records the temporary pontoon and bridge commissioned on 17 March. The permanent asset remains in delivery: no cited owner document establishes final installation, commissioning, handover or completion.
Project signal
Construction in United Kingdom
Current statusTeignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmedSource confidenceConfirmed
Location
United Kingdom / Europe
Segment
Marinas, pontoons and berthing infrastructure
Status
Teignmouth Maritime Services holds the GBP 3.201 million excluding-VAT design-and-build contract; a weather-delayed temporary pontoon and bridge were commissioned on 17 March 2026, while permanent pontoon completion and owner handover remain unconfirmed / Confirmed
Last checked
9 August 2026
Coverage
Related sectors
Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Plymouth used a below-threshold open competition under Find a Tender OCID ocds-h6vhtk-05044f and local reference DN774869. Three tenders were received by 11 July 2025. The council approved the TMS award on 3 October, signed the contract on 3 November, and published contract-details notice 000756-2026 on 6 January 2026. The contract uses NEC4 Engineering and Construction Contract Option A with a priced activity schedule.
Execution window
Find a Tender records 4 November 2025 to 31 August 2026. King's Harbour Master notice 024/26 scheduled temporary-pontoon installation from 16 to 20 February and marine construction, including new pontoon installation and piling, from 23 February to 19 June, with diving throughout. Weather delayed the barge and temporary works into March. Plymouth later targeted permanent completion by late summer 2026. These dates do not establish accepted completion.
Works package
The core design-and-build scope includes removal and disposal of the existing pontoon, supply and installation of a replacement pontoon system, bridgehead and seawall repairs, piling as required, linkspan installation, accessibility facilities, environmental enhancements such as artificial reef or settlement tiles, and potential reuse of existing piles or linkspan elements where feasible. The awarded option configuration and final commercial-berth count are not fully resolved in the public notice chain.
Marine interfaces
The works sit beside an operating watersports centre and ferry route in the Dockyard Port of Plymouth. Delivery interfaces include temporary ferry continuity, slipway closures, barge access, piling, diving, navigation shapes, wash controls, bridgehead and seawall stability, tidal access, public safety, accessible water transfer and environmental features. The harbour notice proves a controlled marine work window but does not name vessels, plant owners or lower tiers.
Commercial evidence boundary
The signed main works contract is GBP 3,201,127 excluding VAT and GBP 3,841,352.40 including VAT. Plymouth's public release describes a GBP 4.2 million investment across the broader scheme. The values have different boundaries and must not be added or treated as a price increase. The council authorized limited modifications within an undisclosed contingency, while variations, certified payments, final account and exercised options remain unpublished.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Legal award
Mount Batten pontoon and bridgehead design-and-build works
Named party
Teignmouth Maritime Services Limited
Status
Confirmed
Source position
Find a Tender records a 3 November 2025 signature and GBP 3,201,127 excluding VAT under NEC4 ECC Option A. Source
Marine construction controls
Temporary pontoon, permanent pontoon, piling and diving
Named party
Teignmouth Maritime Services Limited under Plymouth and harbour controls
Status
Confirmed
Source position
King's Harbour Master notice 024/26 records the February-to-June 2026 work sequence and navigation precautions. Source
Temporary access facility
Temporary pontoon and bridge commissioning
Named party
Mount Batten Centre and project team
Status
Confirmed
Source position
The centre records successful installation and health-and-safety commissioning on 17 March 2026 after a weather-delayed barge arrival. Source
Ferry continuity
Temporary service interruption and resumption
Named party
Mount Batten Ferry
Status
Confirmed
Source position
The operator records weather-related extension of the interruption and service resumption on 14 March 2026. Source
Permanent asset completion
Replacement pontoon, bridgehead and seawall handover
Named party
Plymouth City Council and Teignmouth Maritime Services Limited
Status
Not evidenced
Source position
No cited source confirms permanent installation, commissioning, owner handover, accepted completion or final account.
Lower-tier delivery chain
Pontoon fabrication, piles, linkspan, diving, environmental features and marine plant
Named party
No contract-specific lower-tier organization named
Status
Undisclosed
Source position
The reviewed procurement, owner, harbour, operator and contractor sources identify no Mount Batten subcontractor or supplier.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Ferry continuity resumed after enabling works, but this commissioning milestone neither installs nor accepts the permanent pontoon and bridgehead assets.