Mount Batten temporary access precedes permanent handover

Published 9 August 2026 Updated 16 August 2026 Publisher IMWO Region Europe Confidence Confirmed
Plymouth Mount Batten accessible pontoon hoist and ferry berth, official LHC Design visualization

LHC Design via Mount Batten Centre; future-state design visualization, not construction-progress or completion evidence

Mount Batten's temporary pontoon restored ferry access in March 2026. TMS's GBP3.201 million contract, Plymouth's GBP4.2 million investment and permanent handover remain separate delivery records with distinct evidence.

A weather-delayed enabling package restored the ferry connection

Find a Tender and Plymouth's contract register identify TMS as contractor and give the contract value; the council award record gives the wider GBP 4.2 million investment. King's Harbour Master published the work window, while the centre and ferry operator document the delay and temporary commissioning. The images depict the proposed finished scheme and provide no evidence of construction progress.

One waterfront project carries three different evidence boundaries

Passengers returned through a temporary system while permanent pontoon, piling, linkspan, bridgehead, seawall, accessibility and environmental works remained in delivery. Treating service continuity as permanent acceptance would hide the remaining installation and commercial interfaces.

Evidence conclusion

Contract value, programme investment and acceptance must remain separate

TMS is the confirmed NEC4 Option A design-and-build contractor at GBP 3,201,127 excluding VAT. Plymouth's GBP 4.2 million statement covers the wider investment, not a revised main-contract value. The harbour work window covers new-pontoon installation, piling and diving, while the centre confirms only the temporary facility commissioned on 17 March. Permanent completion remains unverified pending dated commissioning or owner handover.

Outstanding evidence

  • Permanent pontoon and linkspan installation evidence
  • As-built pile, berth and accessibility configuration
  • Bridgehead, seawall and environmental enhancement completion
  • Ferry transfer from temporary to permanent facilities
  • Named fabrication, piling, diving and marine-plant lower tiers
  • Permanent commissioning, owner acceptance and final account