Pontoon evidence
Mount Batten temporary access precedes permanent handover
Mount Batten's temporary pontoon restored ferry access in March 2026. TMS's GBP3.201 million contract, Plymouth's GBP4.2 million investment and permanent handover remain separate delivery records with distinct evidence.
A weather-delayed enabling package restored the ferry connection
Find a Tender and Plymouth's contract register identify TMS as contractor and give the contract value; the council award record gives the wider GBP 4.2 million investment. King's Harbour Master published the work window, while the centre and ferry operator document the delay and temporary commissioning. The images depict the proposed finished scheme and provide no evidence of construction progress.
One waterfront project carries three different evidence boundaries
Passengers returned through a temporary system while permanent pontoon, piling, linkspan, bridgehead, seawall, accessibility and environmental works remained in delivery. Treating service continuity as permanent acceptance would hide the remaining installation and commercial interfaces.
Evidence conclusion
Contract value, programme investment and acceptance must remain separate
TMS is the confirmed NEC4 Option A design-and-build contractor at GBP 3,201,127 excluding VAT. Plymouth's GBP 4.2 million statement covers the wider investment, not a revised main-contract value. The harbour work window covers new-pontoon installation, piling and diving, while the centre confirms only the temporary facility commissioned on 17 March. Permanent completion remains unverified pending dated commissioning or owner handover.
Outstanding evidence
- Permanent pontoon and linkspan installation evidence
- As-built pile, berth and accessibility configuration
- Bridgehead, seawall and environmental enhancement completion
- Ferry transfer from temporary to permanent facilities
- Named fabrication, piling, diving and marine-plant lower tiers
- Permanent commissioning, owner acceptance and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 7
- Mount Batten pontoon contract details notice 000756-2026 Find a Tender, Published 6 January 2026; contract signed 3 November 2025
- Mount Batten pontoon contract register entry Plymouth City Council contract register, Contract signed 3 November 2025; reviewed 9 August 2026
- Work begins to transform the Mount Batten Pontoon Plymouth City Council, 12 February 2026
- Mount Batten engineering works information PLNTM 024/26 King's Harbour Master Plymouth, 13 February 2026
- Mount Batten Centre redevelopment works updates Mount Batten Watersports and Activities Centre, Updates through 17 March 2026; reviewed 9 August 2026
- Mount Batten Ferry service interruption and resumption Mount Batten Ferry, 25 February to 14 March 2026
- Mount Batten pontoon contract award officer decision Plymouth City Council, 3 October 2025