Project record
Marsa Maroc is extending the 310-metre multipurpose-terminal frontage at Jorf Lasfar so two larger vessels can berth more effectively. The owner earmarked MAD 240 million in 2024 and reported the project launched in 2025 with an expected capacity increase of about 50%. Tanger Med Engineering developed the earlier feasibility and preliminary design. Tectone's execution-design record names its client as 'SOAMEGC SUD' and defines block-quay extensions of 30.20 metres at -12 m and 50.40 metres at -14 m plus a mooring dolphin and 34.70-metre boatmen's bridge, creating a strong but spelling-qualified link to marine contractor SOMAGEC SUD.
Morocco / Africa
Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation
Marsa Maroc says the berth-front extension was launched and remained part of its active 2025 investment programme. Execution-design evidence identifies two quay extensions and a mooring dolphin; no owner acceptance or completed operating release has been published / Confirmed
2 August 2026
Coverage
Multipurpose berth extension, block quay, mooring dolphin, access bridge and terminal equipment modernisation is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogTectone published a project-specific execution-design record naming 'SOAMEGC SUD' as client and defining the two block-quay extensions, dolphin and bridge. This materially narrows the delivery chain without replacing the missing owner award notice.
SourceMarsa Maroc's annual report states the berth-front extension was launched and should increase terminal capacity by about 50%, but it does not claim physical completion or operating acceptance.
SourceThe owner established a project-specific budget for the multipurpose-terminal mooring-front extension. The amount is retained as a budget rather than recast as a contract value.
SourceEvidence gap