USACE has issued the FY26 Richmond Inner Harbor maintenance dredging RFP. The firm-fixed-price package covers Reaches 1 through 14 to -37 feet MLLW with one foot of paid overdepth, and directs suitable dredged material to Montezuma Wetlands. Proposals are due 14 August 2026.
Project signal
Tender in United States
Current statusUpdated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recordedSource confidenceConfirmed
Location
United States / Americas
Segment
Port infrastructure
Status
Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded / Confirmed
Last checked
19 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, San Francisco District
Delivery parties
No contractor selected in the reviewed solicitation
Contract route
Full and open request for proposals using lowest-price technically acceptable evaluation for one firm-fixed-price contract
Execution window
Proposals due 14 August 2026 at 11:30 PDT; award, notice to proceed and field window remain unconfirmed
Works package
Maintenance dredging of Reaches 1 through 14 to -37 feet MLLW with one foot of paid overdepth, with suitable material transported to Montezuma Wetlands
Marine interfaces
Mechanical channel dredging across an operating commercial harbor, reach-by-reach hydrographic control, barge transport, DMMO suitability and wetland-placement acceptance
Commercial evidence boundary
The updated solicitation estimates USD 10 million to USD 25 million and packages all 14 reaches into one firm-fixed-price contract. The earlier USACE planning deck carried a lower cost band and 350,000-cubic-yard planning estimate; those figures should not be presented as the current contract value or final quantity.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The current notice set the 14 August proposal deadline, USD 10 million to USD 25 million estimate, LPTA evaluation, 14-reach scope, -37-foot requirement and Montezuma route without identifying an award or contractor.
The FY2026 planning schedule set an initial baseline
The district planning deck carried a 350,000-cubic-yard estimate, lower cost band and July award target. Those planning figures are retained for change tracking, not treated as current contract terms.