Richmond puts 14 channel reaches into one dredging RFP
USACE's updated Richmond Inner Harbor RFP covers Reaches 1 through 14 at -37 feet MLLW plus one foot of paid overdepth. Suitable material is to move to Montezuma Wetlands, and proposals are due 14 August 2026.
Published scope and current milestone
The 15 July SAM.gov solicitation controls the current deadline, depth, evaluation route, cost range and Montezuma destination. The 9 June presolicitation and March USACE schedule are retained as procurement history. The schedule's 350,000-cubic-yard planning estimate and lower cost band are not presented as current contract terms. The hydrographic index and EA/EIR provide survey and programme context, not evidence of 2026 mobilisation or acceptance.
Dredging quantity and delivery implications
This is one contract with a defined depth and placement route, but the public solicitation leaves the final quantity by reach, contractor, plant and accepted output open. The USD 10 million to USD 25 million current estimate also replaces the lower planning range in the district's March schedule.
Evidence conclusion
Survey, placement and acceptance evidence
Richmond remains at tender until an amendment or award fixes the deadline, contractor and value. Baseline surveys, plant mobilisation, DMMO suitability, Montezuma receipts and post-dredge acceptance then determine execution status. The earlier 350,000-cubic-yard planning estimate stays in the change log until the current specifications or measured quantities are public.
Outstanding evidence
- Amendments and final proposal close
- Award, contractor and firm-fixed-price value
- Baseline quantity and survey limits by reach
- Clamshell plant, barges and mobilisation date
- DMMO suitability and Montezuma receipt records
- Measured production and paid overdepth
- Post-dredge survey and USACE acceptance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Richmond Inner Harbor FY26 maintenance dredging solicitation W912P726RA020 SAM.gov / U.S. Army Corps of Engineers, Updated 15 July 2026
- Richmond Inner Harbor FY26 maintenance dredging presolicitation SAM.gov / U.S. Army Corps of Engineers, 9 June 2026
- FY2026 San Francisco District navigation acquisition schedule U.S. Army Corps of Engineers, San Francisco District, March 2026
- Richmond Harbor hydrographic survey index U.S. Army Corps of Engineers, San Francisco District, Current page reviewed 19 July 2026
- Federal Navigation Channels final EA/EIR covering Richmond Harbor U.S. Army Corps of Engineers, San Francisco District, April 2015; reviewed 3 August 2026