Location
Saudi Arabia / Middle East
Project record
Air Products; exact NEOM Green Hydrogen Project and marine export jetty
NEOM Green Hydrogen Company is completing a purpose-built liquid-ammonia export jetty at Oxagon for up to 1.2 million tonnes per year of green ammonia. NGHC reported the integrated project above 90% complete in March 2026, and Air Products now describes construction in final completion with commissioning started through energization. The marine chain is unusually visible: Air Products is primary EPC and system integrator, Jacobs is the named jetty consultant, Saudi Archirodon is the marine contractor, Longitude supported the tanker-interface design and EPC process, and disclosed downstream roles include Velosi, EMJ Permadec, ICS Technologies and MarinTel. VTS radar commissioning is a component milestone, not proof of an accepted berth or first export cargo.
Saudi Arabia / Middle East
Deep-water ports and energy terminals
Overall complex above 90% complete; energization and commissioning started, with jetty VTS radar commissioned but first ammonia transfer not confirmed / Confirmed
1 August 2026
Coverage
Deep-water ports and energy terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe EPC contractor's current investor record moves the integrated complex into commissioning, while leaving marine handover, loading-system acceptance and first cargo unconfirmed.
SourceThe owner retained first green-ammonia product availability in 2027 and placed the project in late execution rather than commercial operation.
SourceICS Technologies reported installation and commissioning of its STRAITMASTER radar with MarinTel, closing a VTS component gate but not the full berth-acceptance chain.
SourceThe supplier delivered more than 550 m2 across eight permanent-formwork panel types to Saudi Archirodon's jetty package, confirming the Jacobs and Saudi Archirodon marine chain.
SourceThe USD 8.4 billion financing and USD 6.7 billion EPC agreements moved the integrated plant and export infrastructure into full execution.
SourceEvidence gap