Project record
Malmporten has moved through a completed 2024 preparatory dredging package, an over-budget main tender, a redesigned procurement and a signed SEK 5.7 billion Boskalis-Van Oord contract for roughly 14 million cubic metres of remaining fairway and harbour works.
Sweden / Europe
Port infrastructure
Dredging contract signed for 2027 start / Confirmed
15 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe owners moved the main dredging package from conditional award to a signed approximately SEK 5.7 billion contract for about 40 kilometres of fairway, with execution from 2027 and completion by 15 August 2030. Signing does not prove fleet mobilisation, accepted depth, reclaimed land or deepwater-port readiness.
SourceThe owner announced a roughly 14-million-m³ optimized scope and planned contract signing after the review period. The record at that gate established an award decision; the signed contract followed on 2 July.
SourceA redesigned fairway scope returned to market through prequalification and invited bids. The later owner release describes the previous procurement as cancelled in September 2025, while the authority's detailed status record says the common tender had been stopped in February; The two descriptions remain separate rather than being collapsed into one event.
SourceThe Swedish Maritime Administration says the submitted bids exceeded budget and that the deepwater-quay procurement was also stopped. The subsequent design optimization was intended to reduce cost without changing capacity, safety or function.
SourceThe authority records completion of the 2024 preparatory works in October. That package was physical progress, but it did not complete the remaining fairway, harbour-basin, quay or deepwater-port works.
SourceOptimus and Kahamari 2 started in the harbour area, followed by Magnor in the Sandgrönn fairway and planned support from Simson. The fleet disclosure is evidence of active preparatory production, not completion of the later main contract.
SourceThe approximately SEK 655 million base package, with a further option, covered roughly 1.5 million m³ in the harbour and part of Sandgrönnleden before winter. Its quantity and value must remain separate from the later remaining-works contract.
SourceThe early owner brief described about 22 million m³, around 1 million m³ of rock, parallel port construction and normal operations, and an April 2024-December 2026 concept. These were procurement-planning assumptions and are not the current 14-million-m³ remaining-works contract.
SourceEvidence gap