Luleå's 14 million m³ award follows a failed tender and redesign
Malmporten's current SEK 5.7 billion contract is the result of a procurement reset, not a straight-line award. A 2024 preparatory dredging package reached the water, the first main tender exceeded budget, the fairway design was optimized, and Boskalis-Van Oord now holds the roughly 14-million-m³ remaining-works package.
What changed
The Swedish Maritime Administration's March 2022 market dialogue published an early whole-program baseline of about 22 million m³ and an April 2024-December 2026 implementation concept. A June 2024 authority release then defined a separate roughly 1.5-million-m³ preparatory package; the July field update named Optimus, Kahamari 2 and Magnor, and the March 2026 status page says those works finished in October 2024. The same status page says the common main-works tender and deepwater-quay tender were stopped in February 2025 after bids exceeded budget, followed by fairway-design optimization and a two-stage retender from September. Port of Luleå's June 2026 award release uses September 2025 as the previous-procurement cancellation date, so the public record is not fully aligned. The owners signed the remaining-works contract on 2 July 2026. Port, authority, Boskalis and Van Oord sources define about 40 kilometres of fairway, roughly 14 million m³ of mixed soil and rock, a SEK 5.7 billion / approximately EUR 500 million value, ice-free-season execution from 2027 and completion by 15 August 2030. The published figures refer to different baselines: 22 million m³ for the old programme, 1.5 million m³ for the preparatory package and 14 million m³ for the current remaining-works contract.
Why it matters
The sequence changes the risk reading. The old 21-22-million-m³ whole-program baseline, the completed 1.5-million-m³ preparatory package and the current 14-million-m³ contract are different scope states. Suppliers and analysts need to track what was removed, completed, retendered or left in the separate deepwater-port and quay programme before comparing quantities, prices or progress.
Decision read
What remains open
Malmporten is now a production-intensive capital works contract with a documented procurement-reset history. Attention shifts from award value to whether the 2027 mobilisation converts the optimized scope into seasonal production, hard-material excavation, compliant material routing, accepted hydrography and usable reclaimed land while the separate port-side works keep pace.
Next watchpoints
- Spring 2027 mobilization
- Ice-free-season production plan
- Rock excavation and drill-and-blast sequencing
- Reclamation and deepwater-port interface dates
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 9
- Sweden’s largest dredging project to start in 2027 Swedish Maritime Administration, 2 July 2026
- Malmporten remaining dredging contract signed Port of Luleå, 2 July 2026
- Boskalis and Van Oord awarded large dredging contract for Port of Luleå Boskalis, 2 July 2026
- Van Oord and Boskalis awarded Malmporten dredging contract Van Oord, 2 July 2026
- Sweden's largest dredging project takes the next step Port of Luleå, 12 June 2026
- Malmporten project status and procurement background Swedish Maritime Administration, 31 March 2026
- Malmporten preparatory dredging begins Swedish Maritime Administration, 23 July 2024
- First Malmporten dredging contractor appointed Swedish Maritime Administration, 13 June 2024
- Malmporten market-dialogue scope baseline Swedish Maritime Administration, 24 March 2022
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.