Contract 1854104 records GETRA and AXOR Construction under ZR-UGP-447404-CW-RFB for rehabilitation and modernization of Kalundu Port in South Kivu, signed on 5 September 2025 for USD 21,156,296.88. Delivery was subsequently suspended. On 4 June 2026 the PFCIGL project unit, GETRA-AXOR and newly recruited supervision consortium Prospectiva-ERCA reviewed the prerequisites for an effective restart. PFCIGL says contractors began remobilizing on 15 June and described Kalundu activity as site installation and ground preparation; the interministerial steering committee recorded progressive resumption on 24 June. No cited owner or engineer record supplies measured physical progress, an effective rehabilitation-works start, completion or acceptance.
Project signal
Construction in Democratic Republic of the Congo
Current statusPFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation worksSource confidenceConfirmed
Location
Democratic Republic of the Congo / Africa
Segment
Port infrastructure
Status
PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works / Confirmed
Last checked
15 August 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
PFCIGL-RDC Project Management Unit (UGP), under the Democratic Republic of the Congo Ministry of External Trade
Delivery parties
GETRA-AXOR contractor group - works contractor under ZR-UGP-447404-CW-RFB, Prospectiva-ERCA consortium - control and supervision mission; not a works subcontractor, Marine, piling, concrete, logistics-zone, survey and building-services subcontractors - not identified in the cited records
Contract route
A prior-review, open-international Request for Bids used a single-stage two-envelope process. The plan records a 5 September 2025 signature and 2 July 2026 planned completion. Contract 1854104 reports a USD 21.156 million committed amount split equally between the two named suppliers for reporting purposes.
Execution window
The procurement plan's 2 July 2026 completion date is no longer a reliable live baseline: PFCIGL's owner-side updates show that a suspension had first to be lifted, start prerequisites were still under review on 4 June and site installation resumed from 15 June. The wider P174814 programme closes on 30 June 2028, but no cited revision supplies a replacement package programme, effective works-start date or contractual completion date.
Works package
The appraisal baseline calls for renovation of existing Kalundu port facilities, raising the dock area to reduce seasonal flooding, developing a logistics zone and providing storage for business associations using charter boats. The signed-contract title confirms rehabilitation and modernization, but the cited award data do not disclose final dimensions, quantities, design changes or as-built scope.
Marine interfaces
The package sits on an operating Lake Tanganyika waterfront exposed to seasonal water-level changes. Key interfaces include dock elevation, vessel access, barge berthing, cargo apron continuity, drainage, shore structures, logistics-zone access and uninterrupted regional lake traffic. Public records do not identify dredging, piling, temporary berths or marine-plant assignments.
Commercial evidence boundary
The supplier API's equal USD 10.578 million allocations are reporting entries and disclose neither a work split nor a legal joint-venture share. The USD 21.156 million award also differs from the procurement plan's USD 12 million estimate and the appraisal's USD 23 million intervention envelope; those are separate dated baselines, not proof of variation or overrun.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The procurement plan's 2 July date cannot be treated as evidence of late closeout because owner-side records show that the suspended package was only remobilizing in June; no revised package programme is public.
Steering committee recorded progressive resumption
The PFCIGL interministerial steering committee acknowledged progressive resumption at Kalundu while noting continuing security constraints and calling for stronger contract follow-up.
PFCIGL says contractors remobilized from 15 June and identifies Kalundu activity as site installation and ground preparation before effective rehabilitation works.
The project unit, GETRA-AXOR and supervision consortium Prospectiva-ERCA met after the suspension was lifted to resolve technical, administrative and organizational prerequisites for launch.
Contract 1854104 reports USD 21,156,296.88 for rehabilitation and modernization under ZR-UGP-447404-CW-RFB, naming GETRA and AXOR Construction as suppliers.