Project record

Kalundu Port rehabilitation and modernization works

PFCIGL, local-authority and contractor representatives inspect the Kalundu Port waterfront beside Lake Tanganyika vessels in March 2026

PFCIGL-RDC; official photograph from the Kalundu Port security and restart inspection

Contract 1854104 records GETRA and AXOR Construction under ZR-UGP-447404-CW-RFB for rehabilitation and modernization of Kalundu Port in South Kivu, signed on 5 September 2025 for USD 21,156,296.88. Delivery was subsequently suspended. On 4 June 2026 the PFCIGL project unit, GETRA-AXOR and newly recruited supervision consortium Prospectiva-ERCA reviewed the prerequisites for an effective restart. PFCIGL says contractors began remobilizing on 15 June and described Kalundu activity as site installation and ground preparation; the interministerial steering committee recorded progressive resumption on 24 June. No cited owner or engineer record supplies measured physical progress, an effective rehabilitation-works start, completion or acceptance.

Project signal

Construction in Democratic Republic of the Congo

Current status PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works Source confidence Confirmed

Location

Democratic Republic of the Congo / Africa

Segment

Port infrastructure

Status

PFCIGL reported that GETRA-AXOR remobilized from 15 June 2026 and that Kalundu works were progressively resuming; activity then remained at site installation and ground preparation before effective rehabilitation works / Confirmed

Last checked

15 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
PFCIGL-RDC Project Management Unit (UGP), under the Democratic Republic of the Congo Ministry of External Trade
Delivery parties
GETRA-AXOR contractor group - works contractor under ZR-UGP-447404-CW-RFB, Prospectiva-ERCA consortium - control and supervision mission; not a works subcontractor, Marine, piling, concrete, logistics-zone, survey and building-services subcontractors - not identified in the cited records
Contract route
A prior-review, open-international Request for Bids used a single-stage two-envelope process. The plan records a 5 September 2025 signature and 2 July 2026 planned completion. Contract 1854104 reports a USD 21.156 million committed amount split equally between the two named suppliers for reporting purposes.
Execution window
The procurement plan's 2 July 2026 completion date is no longer a reliable live baseline: PFCIGL's owner-side updates show that a suspension had first to be lifted, start prerequisites were still under review on 4 June and site installation resumed from 15 June. The wider P174814 programme closes on 30 June 2028, but no cited revision supplies a replacement package programme, effective works-start date or contractual completion date.
Works package
The appraisal baseline calls for renovation of existing Kalundu port facilities, raising the dock area to reduce seasonal flooding, developing a logistics zone and providing storage for business associations using charter boats. The signed-contract title confirms rehabilitation and modernization, but the cited award data do not disclose final dimensions, quantities, design changes or as-built scope.
Marine interfaces
The package sits on an operating Lake Tanganyika waterfront exposed to seasonal water-level changes. Key interfaces include dock elevation, vessel access, barge berthing, cargo apron continuity, drainage, shore structures, logistics-zone access and uninterrupted regional lake traffic. Public records do not identify dredging, piling, temporary berths or marine-plant assignments.
Commercial evidence boundary
The supplier API's equal USD 10.578 million allocations are reporting entries and disclose neither a work split nor a legal joint-venture share. The USD 21.156 million award also differs from the procurement plan's USD 12 million estimate and the appraisal's USD 23 million intervention envelope; those are separate dated baselines, not proof of variation or overrun.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Published completion baseline became stale

The procurement plan's 2 July date cannot be treated as evidence of late closeout because owner-side records show that the suspended package was only remobilizing in June; no revised package programme is public.

Source

Steering committee recorded progressive resumption

The PFCIGL interministerial steering committee acknowledged progressive resumption at Kalundu while noting continuing security constraints and calling for stronger contract follow-up.

Source

GETRA-AXOR began site remobilization

PFCIGL says contractors remobilized from 15 June and identifies Kalundu activity as site installation and ground preparation before effective rehabilitation works.

Source

Post-suspension restart prerequisites reviewed

The project unit, GETRA-AXOR and supervision consortium Prospectiva-ERCA met after the suspension was lifted to resolve technical, administrative and organizational prerequisites for launch.

Source

GETRA and AXOR signed the Kalundu works contract

Contract 1854104 reports USD 21,156,296.88 for rehabilitation and modernization under ZR-UGP-447404-CW-RFB, naming GETRA and AXOR Construction as suppliers.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Effective restart date, notice to proceed and approved recovery programme
  • Engineer-certified physical progress after remobilization
  • Dock-raising, flood-level and drainage design outcomes
  • Logistics-zone and storage-facility completion
  • GETRA-AXOR contractual structure and package allocation
  • Marine access, temporary berthing and barge-traffic sequencing
  • Survey, concrete, piling, electrical and local subcontractors
  • Final contract value, suspension effects, amendments, payments and claims
  • Completion, acceptance and operational handover

Reporting status

Construction, confirmed confidence

Last checked 15 August 2026 across 9 cited sources. The dated timeline above carries the project events.

Last checked 15 August 2026 Cited sources 9