Port works restart
Kalundu moved from suspension into site remobilization
PFCIGL-RDC; official photograph accompanying the June 2026 site-remobilization report
PFCIGL's owner-side record changes the reading of Kalundu's schedule. After the USD 21.156 million GETRA-AXOR contract was suspended, the project unit and parties reviewed restart prerequisites on 4 June 2026. Contractors remobilized from 15 June, with Kalundu limited to site installation and ground preparation before effective rehabilitation works. The steering committee recorded progressive resumption on 24 June. The procurement plan's 2 July completion entry is therefore a stale baseline, not evidence that a completed package merely awaits closeout.
Owner evidence places the package at installation and preparation
Contract 1854104 documents the contractor names, signature date, USD 21.156 million committed amount and procurement method. PFCIGL's June publications establish the later delivery state: lifted suspension, unresolved launch prerequisites, remobilization from 15 June, site installation and progressive resumption. The procurement plan's 2 July date remains a published baseline, but the newer owner evidence shows that it no longer described the live programme. No cited record establishes effective rehabilitation start, measured progress, completion or acceptance as of 15 August 2026.
Restart control now defines Kalundu's programme
Kalundu combines an operating lake-port interface with dock raising, seasonal-flood resilience, storage and a logistics zone. After suspension, security clearance, contractor remobilization, supervision readiness, work-front release and a recovery programme become prerequisites to measurable construction. Treating an unrevised procurement-plan date as the live programme would obscure the actual controls on delivery and misstate what had occurred on site.
Evidence conclusion
A recovery programme and certified output now matter most
The contract award remains firm, but the public delivery sequence is now clearer. PFCIGL identifies GETRA-AXOR as works contractor and Prospectiva-ERCA as supervision mission; it reports remobilization from 15 June without publishing notice to proceed, supervision commencement, certified quantities or a revised contractual completion date. An approved recovery programme linked to released work fronts and engineer-certified production would establish how the dock and logistics scope advances beyond site installation.
Outstanding evidence
- Notice to proceed or effective post-suspension restart date
- Approved recovery programme and revised completion date
- Supervision commencement and engineer-certified production
- Dock elevation, flood-resilience and drainage work fronts
- Logistics-zone and storage-facility work fronts
- GETRA-AXOR legal structure and work allocation
- Marine access and barge-traffic continuity
- Suspension effects, amendments, claims and payment status
- Completion, acceptance and operational handover
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 7
- Uvira infrastructure sites remobilize after interruption PFCIGL-RDC, 18 June 2026; remobilization reported from 15 June 2026
- Kalundu parties align prerequisites for works launch PFCIGL-RDC, 4 June 2026
- Sixth PFCIGL interministerial steering committee session PFCIGL-RDC, 24 June 2026
- World Bank contract 1854104 for ZR-UGP-447404-CW-RFB World Bank Projects and Operations API, Contract signed 5 September 2025; record reviewed 5 August 2026
- P174814 DRC procurement plan including the Kalundu works contract World Bank, Current plan reviewed 5 August 2026
- Great Lakes Trade Facilitation and Integration Project appraisal document World Bank, 9 June 2022 approval baseline
- PFCIGL project description and Kalundu intervention scope PFCIGL-RDC, Current official page reviewed 15 August 2026