Location
The Gambia / Africa
Project record
The Banjul Port Fourth Expansion is a USD 129.02 million programme combining public grants, government funding and approximately USD 98.64 million of planned private financing. Albayrak Group signed the port concession in July 2024 and Alport Banjul took over operations on 14 February 2025. A Damen-built hybrid ferry named Barra was commissioned on 23 March 2026. Those are real delivery milestones, but they do not prove completion of the programme's 345 m jetty extension, 22,000 m2 container-yard expansion, ferry-terminal relocation, widened access road or integrated port and customs systems.
The Gambia / Africa
Port infrastructure
Port concession operating and green ferry commissioned; core jetty and container-terminal expansion completion remains unverified / Confirmed
16 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogCommissioning closed one AfDB-financed vessel package and added a low-emission Banjul-Barra asset. It did not complete the port jetty, container terminal, ferry-terminal relocation or road packages.
SourceThe EOI opened an independent implementation-assessment workstream. It did not name the selected auditor or certify any completed civil package.
SourceThe concession moved from agreement into operating control. Alport reports faster vessel handling after the transfer, but operating performance does not establish the civil expansion's as-built dimensions.
SourceThe QCBS consultancy route defined surveys, detailed design, tender support and supervision for approximately 3.5 km of Bund Road and Cotton Street. It did not establish a consultant award or works mobilisation.
SourceThe July 2024 agreement activated the private-finance route identified in the appraisal plan. Public summaries name Albayrak Group, while the exact civil-package and Negmar boundaries remain incomplete.
SourceGPA identified Albayrak and Negmar as concessionaires and MTBS as transaction adviser, but did not publish the full package schedule or assign the jetty works.
SourceThe approval fixed the programme scope, blended-finance structure and public targets for the jetty, terminal, ferry, road and digital systems.
SourceEvidence gap