Project record
Aqaba Development Corporation is procuring a concessionaire to rehabilitate, modernize, finance, operate, and transfer the existing Cement Terminal and Mut'ah floating berth, add silica-focused bulk handling and ship-loading facilities, and integrate utilities and transport links under a 20-year DFBOT concession.
Jordan / Middle East
Port infrastructure
DFBOT proposals due 17 August 2026 / Confirmed
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
ADC scheduled mandatory site visits for 8-9 July after the tender-document request window. The reviewed public pages do not identify attendees, confirm that a visit occurred, disclose observations or provide an asset-condition survey.
Read controlling sourceOnly firms that had submitted the 2025 EOI could request the documents by this date. Closing the request window does not establish who requested documents, who remained eligible, or who will bid.
Read controlling sourceThe owner moved from EOI market sounding to a live 20-year DFBOT competition with a possible five-year extension, a JOD 100,000 bid bond, separate technical and financial submissions, and a 17 August close. Publication is not evidence of bids received, award, financing, mobilisation, rehabilitation, or operation.
Read controlling sourceADC extended the EOI submission deadline and said earlier applicants would be automatically shortlisted without resubmitting. The record does not name applicants or establish a final invited-bidder list.
Read controlling sourceADC opened market sounding for a silica terminal using the existing Cement Terminal facilities and Mut'ah floating berth. The EOI initiated procurement but did not award a concession, publish asset condition, or establish an executable rehabilitation package.
Read controlling sourceDelivery watch
Track the 20 July clarification deadline and any addenda, then verify the 17 August proposal close, named bidders or shortlist, preferred bidder, concession award, financial close, notice to proceed, disclosed condition survey, marine rehabilitation package, and accepted start of operations.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerADC's 2025 expression-of-interest record establishes the procurement before Tender 27/A/2026: an initial 25 May deadline, a 2 June site visit, a 15 June question deadline, and an extended 13 July submission deadline. ADC said earlier applicants would be automatically shortlisted without resubmitting, but the page does not name any applicant or confirm a final shortlist. The current tenders register controls the formal 9 June 2026 publication date and 17 August close. Tender 27/A/2026 invites international and local firms to rehabilitate, modernize, finance, operate, and transfer the Cement Terminal facilities and Mut'ah floating berth under a 20-year DFBOT concession, with a possible five-year extension. It identifies silica export as the primary use, future multipurpose flexibility, rehabilitation and integration of existing marine and terminal infrastructure, new support facilities, utility and transport upgrades, modern ship-loading equipment, a JOD 100,000 bid bond, a 20 July clarification deadline, and a 17 August 2026 proposal deadline. ACPOM describes Mut'ah as a 150 m by 35 m floating dock used for general cargo and grain operations and direct truck loading. ACPOM's 2025 insurance RFP confirms an operating port-asset and insurance context; it is not a Tender 27/A/2026 condition survey and does not prove bidder access, site-visit attendance, asset defects, or rehabilitation quantities. The final concessionaire, detailed condition survey, rehabilitation quantities, dredging scope, award value, construction start and operating performance are not disclosed. The photograph is a separate Aqaba bulk-terminal reference, not a condition record for the two Tender 27/A/2026 assets.
Phase: tender. Evidence reviewed: 16 July 2026.