Project record

Sihanoukville New Container Terminal 2 Package 1

Participation
Awarded
Participation checked

Toyo reports civil-package award; 36-month duration from a commencement reference still to be confirmed

Participation source

Toyo's JPY 26.2 billion Sihanoukville award links a 400-metre quay with terminal land, buildings and operating software. The engineering handover spans the waterfront, container yard and terminal control system.

Sihanoukville NCT2 diagram distinguishes the approximately JPY 26.2 billion civil package and 36-month duration from the wider JPY 41.388 billion JICA loan programme.

IMWO original engineering diagram; source: Toyo Construction

Location

Cambodia / Asia Pacific

Segment

Port infrastructure

Phase

Award / Confirmed

Last checked

31 October 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Sihanoukville Autonomous Port
Delivery parties
Toyo Construction Co., Ltd.: announced Package 1 civil-works contractor.
Contract route
Owner civil-works award announced by Toyo on 28 October 2026, supported by Japanese ODA financing at programme level.
Execution window
Toyo states 36 months. The announcement does not give an actual commencement date from which to calculate completion.
Works package
400m quay, approximately 200,000m2 terminal area, 12 buildings and a terminal operating system under the approximately JPY 26.2 billion Package 1 award.
Marine interfaces
Quay transfer, container circulation, yard drainage and buried services must align with buildings and terminal software. Handling equipment and channel access also sit within the broader expansion programme.
Commercial evidence boundary
The JPY 26.2 billion contractor award and JICA loan ceiling of JPY 41.388 billion describe different scopes. Equipment interfaces, progressive yard handovers and operating-system trials determine package readiness.

Evidence gap

What remains unverified

Outstanding evidence

  • Contract commencement and the dated 36-month delivery programme
  • Package interfaces with crane supply and channel/basin dredging
  • Progressive yard, building-service and operating-system trials

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
31 October 2026
Cited sources
4