Ardersier Port (Scotland) Limited is procuring a separate Phase 2 dredging package estimated at GBP 20 million. The package covers a 140-metre-wide navigation channel beside 300 metres of new quay and 758 metres of existing sheet-pile quay, with dredging planned for the second quarter of 2028.
Phase 2 dredging supplier - appointment not established by the reviewed procurement notice
Contract route
PCS MAR552707 / APP2-HAV-ZZ-DD-PQ-K-000001 / ocds-r6ebe6-0000827520 uses a competitive procedure with negotiation. The PQQ closed at 16:00 BST on 1 May 2026. The notice proposed a shortlist of four, invitations to tender on 15 May, negotiated submissions, preferred-bidder selection, standstill and contract execution; the March notice leaves subsequent stage outcomes unconfirmed.
Execution window
The contract notice gives a four-month duration and anticipates a Q2 2028 dredging window. These are procurement assumptions, not an awarded construction programme or notice to proceed.
Works package
Dredge a 140-metre-wide Phase 2 navigation channel to -12.4mCD along 300 metres of proposed new quay and to -6.5mCD along 758 metres of existing sheet-pile quay being upgraded
Marine interfaces
The dredging contractor must work around the quay civils principal contractor and port operations. The adjoining GBP 23 million quay-civils package includes a 100-metre-wide apron, new quay furniture and upgrades along the existing 758-metre frontage, while stating that dredging is by others.
Commercial evidence boundary
GBP 20 million is the contracting authority's estimate excluding VAT, not an award value. The PQQ sought bidders with at least GBP 30 million annual turnover for the preceding three years, three relevant dredging case studies and NEC/CEMAR experience. Any Phase 2 dredging award should be kept separate from the GBP 23 million quay-civils estimate, the port's earlier financing and completed Phase 1 works.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Ardersier opened prequalification for the Phase 2 dredging package
The notice set a GBP 20 million estimate, exact channel geometry, a four-stage negotiated route, a planned shortlist of four and a Q2 2028 dredging window. It did not publish a shortlist, tender issue, bidder, award or mobilisation.
The separate quay-civils package defined the dredging interface
The GBP 23 million civils notice covers the 300-metre new quay and 758-metre existing frontage and expressly leaves dredging to others. The two packages need coordinated programmes but retain separate scope and value.
Bank reporting confirmed Haventus ownership, a GBP 100 million joint credit facility and construction of the earlier 650-metre quay. That context does not establish progress on the later Phase 2 dredging competition.