Procurement

Ardersier sets a £20 million estimate for its Phase 2 dredge

Published 18 July 2026 Publisher IMWO Region Europe Confidence Confirmed
Quay foundation works, lifting plant and concrete-production equipment at Ardersier Port in May 2024

Scottish National Investment Bank / Ardersier Port, May 2024

Ardersier Port's Phase 2 dredging notice covers a 140-metre-wide navigation channel beside 300 metres of proposed new quay and 758 metres of existing quay. The authority estimated the package at GBP 20 million and targeted a four-month dredging window from Q2 2028.

Published scope and current milestone

The 27 March 2026 Public Contracts Scotland notice controls the dredging geometry, GBP 20 million estimate, four-stage procurement, PQQ deadline and Q2 2028 target. The separate quay-civils notice controls the adjoining waterfront scope and says dredging is by others. Scottish National Investment Bank reporting and its exact-site photographs establish Phase 1 construction context, not progress on the Phase 2 competition. The 2024 Marine Directorate record applies to the earlier licensed capital dredge and material routes.

Contract packaging and mobilisation implications

The dredging package sits between the new quay wall, the longer existing frontage and live port operations. Its programme must therefore match the separate quay-civils contract, while the final material route and Phase 2 licence still need to be shown in the public record.

Evidence conclusion

Award, mobilisation and acceptance evidence

Prequalification closed on 1 May. The notice expected invitations to tender from 15 May, but no shortlist, ITT or award appears in the reviewed public chain. The GBP 20 million figure remains an estimate. It should not be combined with the GBP 23 million quay-civils estimate or the financing used for earlier port construction.

Outstanding evidence

  • Public shortlist and issue of the negotiated tender
  • Final channel geometry and dredging method
  • Material characterization, placement route and Phase 2 marine licence
  • Awarded contractor and executed value against the GBP 20 million estimate
  • Programme interface with the 300-metre quay and 758-metre upgrade
  • Mobilisation in the planned Q2 2028 window
  • Post-dredge survey and accepted channel availability

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Sources used 4

Source collections