Tonga rebuilt and extended Queen Salote International Wharf while keeping its only international port in service. The completed programme covers four wharves, four new berthing or mooring dolphins, a 50-metre Wharf 2 extension, navigation aids, a concrete seawall, strengthened rock revetment, yard pavement, drainage, lighting, power and firefighting systems.
Project signal
Completed in Tonga
Use the 5 November 2025 commissioning record as the controlling completion milestone for the marine and civil works. Keep the USD 43.05 million civil contract, McConnell Dowell's USD 70 million project description and AIFFP's USD 83.5 million total funding line separate, and require post-handover operating evidence before claiming durable performance.
Current statusAIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025Source confidenceConfirmed
Location
Tonga / Global islands
Segment
Port infrastructure
Status
AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025 / Confirmed
Evidence reviewed
18 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Government of Tonga, Ministry of Infrastructure and Ports Authority Tonga
Delivery parties
McConnell Dowell Constructors Ltd., Royal HaskoningDHV
Contract route
ADB records an internationally advertised open competitive process with prequalification and merit-point criteria. The Government awarded the main civil contract to McConnell Dowell on 3 August 2022 for USD 43,050,275.49 and the construction-supervision contract to HaskoningDHV for USD 2,002,999.75. AIFFP's completion release records USD 55 million from ADB, USD 20 million from Australia and an estimated USD 8.5 million Tonga contribution, for a USD 83.5 million total project line.
Execution window
The project began in 2022. McConnell Dowell describes Stage 1 from September 2023 to July 2024 and Stage 2 from July 2024 to October 2025, while AIFFP records formal Wharf 1 handover in March 2025. On 5 November 2025, Ports Authority Tonga stated that all marine and civil works were complete and operational.
Works package
Rehabilitate Wharf 1; repair Wharves 2, 3 and 4; extend Wharf 2 by 50 metres; construct four new berthing or mooring dolphins; install navigation markers, moorings and buoys; build a concrete seawall and strengthen existing rock revetment; reorganize and pave the container yard; overlay the access road; and renew drainage, lighting, rainwater, waste-management, electrical and firefighting systems.
Marine interfaces
Construction was split across the eastern and western halves of a live cargo gateway so vessels could continue using the port. Marine piling, wharf demolition and reconstruction, dolphin installation, vessel clearances, temporary works and yard access therefore had to be sequenced with cargo operations rather than delivered behind a closed workfront.
Commercial read
The prime civil package is complete, so the current professional market is post-handover rather than new construction: structural and fender inspection, hydrographic and navigation-aid checks, pavement and drainage maintenance, electrical and firefighting support, storm-damage assessment and asset-management services. Any new package requires a current notice from the Government or Ports Authority Tonga.
Next milestone
Establish the first post-handover evidence set for berth availability, vessel turnaround, storm response, seawall and revetment condition, navigation aids, service-system reliability, maintenance funding and programme close-out.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
All marine and civil works declared complete and operational
The Ports Authority chief executive's commissioning statement closes the construction phase for the named works. Post-handover berth availability, operating costs and long-term climate performance remain unreported.
ADB's contract register names McConnell Dowell and records the USD 43.05 million civil contract, creating the delivery baseline without establishing later physical progress or acceptance.
Establish the first post-handover evidence set for berth availability, vessel turnaround, storm response, seawall and revetment condition, navigation aids, service-system reliability, maintenance funding and programme close-out.
Decision watchpoints
Berth availability and vessel turnaround after commissioning
Wharf, dolphin, fender and mooring-system inspection records
Concrete seawall and rock-revetment condition after severe weather
Yard drainage, lighting, electrical and firefighting system reliability
Navigation-marker serviceability and maintenance responsibility
Asset-maintenance funding, operating-cost change and formal programme close-out
Tonga Ministry of InfrastructureOrganization profile / Government transport-infrastructure ministry and maritime-works implementing agency
Project availability status
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed18 July 2026Sources in this record6
Source record
AIFFP's dated completion release and the Ports Authority chief executive's statement control the current status: all marine and civil works were complete and operational on 5 November 2025. The same release defines the two-phase scope and USD 83.5 million total funding line. ADB's project page supplies the USD 43.05 million civil award, procurement route, four-dolphin, seawall, revetment, navigation-marker and yard scope, but its 95% and 97% progress figures come from a project data sheet last updated 25 July 2025 and are retained as an earlier snapshot. McConnell Dowell supplies the construction sequence, methods, project photographs and contractor-reported USD 70 million project description. These three values are not interchangeable. The public record stops at commissioning: berth availability, vessel turnaround, maintenance cost, storm performance and operating reliability after handover remain unreported.
Phase: completed. Evidence reviewed: 18 July 2026.