Project record

Tonga Queen Salote International Wharf climate-resilient upgrade

Aerial view of two cargo vessels berthed at the completed Queen Salote International Wharf in Nuku'alofa

McConnell Dowell

Tonga rebuilt and extended Queen Salote International Wharf while keeping its only international port in service. The completed programme covers four wharves, four new berthing or mooring dolphins, a 50-metre Wharf 2 extension, navigation aids, a concrete seawall, strengthened rock revetment, yard pavement, drainage, lighting, power and firefighting systems.

Project signal

Completed in Tonga

Use the 5 November 2025 commissioning record as the controlling completion milestone for the marine and civil works. Keep the USD 43.05 million civil contract, McConnell Dowell's USD 70 million project description and AIFFP's USD 83.5 million total funding line separate, and require post-handover operating evidence before claiming durable performance.

Current status AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025 Source confidence Confirmed

Location

Tonga / Global islands

Segment

Port infrastructure

Status

AIFFP and Ports Authority Tonga confirmed all marine and civil works complete and operational on 5 November 2025 / Confirmed

Evidence reviewed

18 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Government of Tonga, Ministry of Infrastructure and Ports Authority Tonga
Delivery parties
McConnell Dowell Constructors Ltd., Royal HaskoningDHV
Contract route
ADB records an internationally advertised open competitive process with prequalification and merit-point criteria. The Government awarded the main civil contract to McConnell Dowell on 3 August 2022 for USD 43,050,275.49 and the construction-supervision contract to HaskoningDHV for USD 2,002,999.75. AIFFP's completion release records USD 55 million from ADB, USD 20 million from Australia and an estimated USD 8.5 million Tonga contribution, for a USD 83.5 million total project line.
Execution window
The project began in 2022. McConnell Dowell describes Stage 1 from September 2023 to July 2024 and Stage 2 from July 2024 to October 2025, while AIFFP records formal Wharf 1 handover in March 2025. On 5 November 2025, Ports Authority Tonga stated that all marine and civil works were complete and operational.
Works package
Rehabilitate Wharf 1; repair Wharves 2, 3 and 4; extend Wharf 2 by 50 metres; construct four new berthing or mooring dolphins; install navigation markers, moorings and buoys; build a concrete seawall and strengthen existing rock revetment; reorganize and pave the container yard; overlay the access road; and renew drainage, lighting, rainwater, waste-management, electrical and firefighting systems.
Marine interfaces
Construction was split across the eastern and western halves of a live cargo gateway so vessels could continue using the port. Marine piling, wharf demolition and reconstruction, dolphin installation, vessel clearances, temporary works and yard access therefore had to be sequenced with cargo operations rather than delivered behind a closed workfront.
Commercial read
The prime civil package is complete, so the current professional market is post-handover rather than new construction: structural and fender inspection, hydrographic and navigation-aid checks, pavement and drainage maintenance, electrical and firefighting support, storm-damage assessment and asset-management services. Any new package requires a current notice from the Government or Ports Authority Tonga.
Next milestone
Establish the first post-handover evidence set for berth availability, vessel turnaround, storm response, seawall and revetment condition, navigation aids, service-system reliability, maintenance funding and programme close-out.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

All marine and civil works declared complete and operational

The Ports Authority chief executive's commissioning statement closes the construction phase for the named works. Post-handover berth availability, operating costs and long-term climate performance remain unreported.

Read controlling source

First-phase Wharf 1 works commissioned

The first marine stage entered service while repairs, Wharf 2 extension, the western yard and remaining systems continued under Stage 2.

Read controlling source

Main wharf-upgrade civil contract awarded

ADB's contract register names McConnell Dowell and records the USD 43.05 million civil contract, creating the delivery baseline without establishing later physical progress or acceptance.

Read controlling source

Delivery watch

Evidence needed next

Establish the first post-handover evidence set for berth availability, vessel turnaround, storm response, seawall and revetment condition, navigation aids, service-system reliability, maintenance funding and programme close-out.

Decision watchpoints

  • Berth availability and vessel turnaround after commissioning
  • Wharf, dolphin, fender and mooring-system inspection records
  • Concrete seawall and rock-revetment condition after severe weather
  • Yard drainage, lighting, electrical and firefighting system reliability
  • Navigation-marker serviceability and maintenance responsibility
  • Asset-maintenance funding, operating-cost change and formal programme close-out

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 18 July 2026 Sources in this record 6

Source record

AIFFP's dated completion release and the Ports Authority chief executive's statement control the current status: all marine and civil works were complete and operational on 5 November 2025. The same release defines the two-phase scope and USD 83.5 million total funding line. ADB's project page supplies the USD 43.05 million civil award, procurement route, four-dolphin, seawall, revetment, navigation-marker and yard scope, but its 95% and 97% progress figures come from a project data sheet last updated 25 July 2025 and are retained as an earlier snapshot. McConnell Dowell supplies the construction sequence, methods, project photographs and contractor-reported USD 70 million project description. These three values are not interchangeable. The public record stops at commissioning: berth availability, vessel turnaround, maintenance cost, storm performance and operating reliability after handover remain unreported.

Phase: completed. Evidence reviewed: 18 July 2026.

Project sources 6