Location
United States / North America
Project record
The City of Los Angeles Harbor Department awarded Specification 2815 to Shimmick Construction Company, Inc. after receiving three bids on 20 November 2025. The approved USD 61,290,400 contract, plus a 10% contingency for a USD 67,419,440 authorization, covers a 34.5 kV industrial station and switchgear, an 18 MVA transformer, 11 kV Alternative Maritime Power equipment and two wharf outlets, concrete wharf repairs, hybrid fender backing panels on steel and timber piles, fenders, bollards, utilities and access improvements. The board attachment names five subcontractors and one steel-pile supplier at bid stage. Executed lower-tier agreements and the physical construction start remain unconfirmed.
United States / North America
Cruise berth rehabilitation, shore power and marine piling
Los Angeles Harbor Commission Resolution 26-10665 approved Shimmick's USD 61,290,400 bid on 6 January 2026, and RAMP records the award on 26 January; the owner's award presentation estimated a March 2026 notice to proceed and January 2029 completion, while the actual NTP, site mobilisation and installed work remain unconfirmed through 8 August 2026 / Confirmed
8 August 2026
Coverage
Cruise berth rehabilitation, shore power and marine piling is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogRAMP converts Opportunity 225023 into award record A-96945 under Contract 2332, confirming the USD 61.290 million award value and named prime contractor.
SourceResolution 26-10665 establishes Shimmick as prime contractor, separates the contract and contingency values, and authorizes a 1,020-calendar-day delivery period.
SourceShimmick identifies the USD 61.3 million preferred-bidder position and describes the electrical, structural and civil work scope before formal board approval.
SourceThe bid opening ranks Shimmick lowest at USD 61.290 million against competing bids of USD 71.922 million and USD 78.799 million.
SourceEvidence gap