Project record

Tema Port Terminal 3 Phase 2 expansion

Aerial view of the active 27-hectare Tema Terminal 3 platform expansion beside container yards and quay cranes

Eiffage; exact Tema Port Terminal 3 Phase 2 platform works at the 20-hectare milestone

Tema Terminal 3's Phase 2 was delivered in distinct layers. Eiffage completed the 400-metre fourth berth in 2021. Meridian Port Services launched the wider second-phase investment in 2023, then Eiffage Genie Civil Marine and De Simone delivered a 27-hectare platform expansion in October 2025 under AECOM's engineering oversight. The completed package covers earthworks, paving, drainage, water and power networks, access roads and storage areas; it should not be described as a new dredging or quay contract.

Project signal

Completed in Ghana

Current status Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021 Source confidence Confirmed

Location

Ghana / Africa

Segment

Deep-water ports and container terminals

Status

Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021 / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Meridian Port Services, owned by Ghana Ports and Harbours Authority (30%), APM Terminals (35%) and Africa Global Logistics (35%)
Delivery parties
Eiffage Genie Civil Marine and De Simone Group consortium - 27-hectare Phase 2 platform expansion completed in October 2025, AECOM - engineer identified by Eiffage for the 2023-25 platform expansion, Eiffage Genie Civil - leading civil contractor for the separate 400-metre fourth berth completed in 2021, Eiffage Genie Civil and RMT - original design-and-build platform and electrical-system delivery chain from the first expansion stage
Contract route
MPS extended the original FIDIC Yellow Book arrangement for fourth-berth land works in 2020 and commissioned the 400-metre berth in 2021. It launched a further second-phase investment in November 2023 after awarding the 27-hectare platform package to Eiffage Genie Civil Marine and De Simone. Eiffage identifies AECOM as MPS's engineer. The 2023 package price and complete downstream subcontract ledger remain undisclosed.
Execution window
The fourth deep-water berth was completed in 2021. The 27-hectare platform expansion began after Eiffage announced the award in October 2023. About 10 hectares were complete by November 2024 and 20 hectares by April 2025. Eiffage's 2025 annual report says all 27 hectares were completed in October 2025 after 2.6 million work hours.
Works package
Complete 27 hectares of new terminal platform including earthworks, pavement, drainage, water and electricity networks, access roads and storage areas. The broader Terminal 3 configuration has a 1.4-kilometre quay with four deep-water berths, 127 hectares after expansion, 12 STS cranes and 41 RTGs as reported when Phase 2 launched. The 2023-25 contract is the platform layer, not a new 1.4-kilometre quay build.
Marine interfaces
The new yard area depends on the previously completed fourth berth, crane power, reefer and utility systems, gate and road access, drainage and terminal-operating controls. Completion of pavement and networks expands stack and landside capacity, but its operating value is demonstrated only when the additional yard blocks, cranes, gates and road connection sustain higher terminal throughput.
Commercial evidence boundary
The programme demonstrates how a deep-water berth can enter service years before its full back-up area. The civil chain is visible at prime-consortium and engineer level, but equipment suppliers, package value, block-by-block handover and operating-performance data remain limited. Future updates should use terminal capacity and service metrics rather than repeat the original 2025 forecast.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Eiffage completed the 27-hectare platform

The contractor's annual report closes the earthworks, pavement, drainage, water, power, road and storage-area package after 2.6 million work hours.

Source

Twenty of 27 hectares were complete

Eiffage identified the client, AECOM engineer and Eiffage-De Simone consortium while showing that seven hectares remained at that date.

Source

MPS launched the broader Phase 2 investment

The launch combined terminal-area expansion and equipment investment around the operating 1.4-kilometre, four-berth marine frontage, linking additional yard capacity to existing berths.

Source

The separate fourth berth entered service

The 400-metre fourth berth extended the Phase 1 frontage to 1.4 kilometres before the later 27-hectare back-up-area package.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Operating release of all new yard blocks
  • Container throughput and berth productivity after the expansion
  • Crane allocation and availability across four berths
  • Drainage, pavement and utility performance on the new platform
  • Motorway-to-port road-link delivery and gate flows
  • Final platform-package value and account
  • Residual works and defects-liability close-out
  • Equipment supplier and controls-package disclosure

Reporting status

Completed, confirmed confidence

Last checked 1 August 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 6