Tema Terminal 3's Phase 2 was delivered in distinct layers. Eiffage completed the 400-metre fourth berth in 2021. Meridian Port Services launched the wider second-phase investment in 2023, then Eiffage Genie Civil Marine and De Simone delivered a 27-hectare platform expansion in October 2025 under AECOM's engineering oversight. The completed package covers earthworks, paving, drainage, water and power networks, access roads and storage areas; it should not be described as a new dredging or quay contract.
Project signal
Completed in Ghana
Current statusEiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021Source confidenceConfirmed
Location
Ghana / Africa
Segment
Deep-water ports and container terminals
Status
Eiffage reports that the 27-hectare Phase 2 platform expansion was completed in October 2025; this follows the separate 400-metre fourth berth completed and commissioned in 2021 / Confirmed
Last checked
1 August 2026
Coverage
Related sectors
Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Meridian Port Services, owned by Ghana Ports and Harbours Authority (30%), APM Terminals (35%) and Africa Global Logistics (35%)
Delivery parties
Eiffage Genie Civil Marine and De Simone Group consortium - 27-hectare Phase 2 platform expansion completed in October 2025, AECOM - engineer identified by Eiffage for the 2023-25 platform expansion, Eiffage Genie Civil - leading civil contractor for the separate 400-metre fourth berth completed in 2021, Eiffage Genie Civil and RMT - original design-and-build platform and electrical-system delivery chain from the first expansion stage
Contract route
MPS extended the original FIDIC Yellow Book arrangement for fourth-berth land works in 2020 and commissioned the 400-metre berth in 2021. It launched a further second-phase investment in November 2023 after awarding the 27-hectare platform package to Eiffage Genie Civil Marine and De Simone. Eiffage identifies AECOM as MPS's engineer. The 2023 package price and complete downstream subcontract ledger remain undisclosed.
Execution window
The fourth deep-water berth was completed in 2021. The 27-hectare platform expansion began after Eiffage announced the award in October 2023. About 10 hectares were complete by November 2024 and 20 hectares by April 2025. Eiffage's 2025 annual report says all 27 hectares were completed in October 2025 after 2.6 million work hours.
Works package
Complete 27 hectares of new terminal platform including earthworks, pavement, drainage, water and electricity networks, access roads and storage areas. The broader Terminal 3 configuration has a 1.4-kilometre quay with four deep-water berths, 127 hectares after expansion, 12 STS cranes and 41 RTGs as reported when Phase 2 launched. The 2023-25 contract is the platform layer, not a new 1.4-kilometre quay build.
Marine interfaces
The new yard area depends on the previously completed fourth berth, crane power, reefer and utility systems, gate and road access, drainage and terminal-operating controls. Completion of pavement and networks expands stack and landside capacity, but its operating value is demonstrated only when the additional yard blocks, cranes, gates and road connection sustain higher terminal throughput.
Commercial evidence boundary
The programme demonstrates how a deep-water berth can enter service years before its full back-up area. The civil chain is visible at prime-consortium and engineer level, but equipment suppliers, package value, block-by-block handover and operating-performance data remain limited. Future updates should use terminal capacity and service metrics rather than repeat the original 2025 forecast.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The launch combined terminal-area expansion and equipment investment around the operating 1.4-kilometre, four-berth marine frontage, linking additional yard capacity to existing berths.