Construction

Paranagua Conveyor Lift Connects Two Construction Programmes

Published 1 November 2026 Publisher IMWO Region Americas Confidence Confirmed
Paranagua Moegao task-duration diagram distinguishes two hours of lifting and four more fixing a 55 m,35-tonne structure during the 11 October operation.

IMWO original engineering diagram; source: Portos do Parana

A 55 m steel structure connects ALTP to the Moegao rail-receiving system. The installed link now needs to become part of a tested material-handling route, with public and terminal work reaching the same handover condition.

A 35-tonne structure crosses the port road

Portos do Parana reports that the first Moegao connection to a private terminal was installed on 11 October. The ALTP connection is 55 m long and weighs about 35 tonnes. A crane rated at up to 600 tonnes was used; the operation required closure of Avenida Portuaria. Lifting took about two hours and fixing another four. The owner expects all 11 eastern-corridor terminals to connect by October 2027 [1].

Check the lift at working radius and the connection at its bearings

Check the crane's load chart at the actual working radius and configuration, with the rigging weight, centre of gravity and pickup and landing positions included in the lifting plan. The reported 600-tonne maximum rating gives the equipment class; the working configuration determines its available lift capacity. The four-hour fixing period also deserves its own allowance because the road and lifting area may remain committed after the load reaches its supports. The receiving team needs the bearings, fixing system and survey controls ready before the structure arrives.

Evidence conclusion

Installed steel precedes a working conveyor route

The owner assigns each terminal its connection investment, with the port approving designs and supervising execution. Its 9 October account specifies 2000 t/hour transfer capacity and enclosed conveyors; it describes no-load tests already under way and loaded tests following energisation of the dedicated substation [2]. The central gallery had reached 54 installed modules by July [3]. The terminal and public systems must demonstrate the agreed transfer duty through their shared valves, controls and conveyors. Tests should follow the operating path across that boundary, with measured performance and fault responses recorded against the connection requirements.

Outstanding evidence

  • Connection survey, fixing and structural release
  • Conveyor, electrical and control interfaces at ALTP
  • Integrated tests before forecasting available handling capacity