Project record
Grand Faw's first operating system combines five handed-over container berths, a 23 km navigation channel reported complete to 19.8 m, terminal reclamation and ground improvement, twin breakwaters, an immersed road tunnel, and a 62 km connecting road that received its final GCPI Performance Certificate on 8 July 2026.
Iraq / Middle East
Port infrastructure
Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Daewoo E&C reported final completion approval after 45 months of construction and a one-year defects period. The certificate closes the road package, not the immersed-tunnel, terminal, navigation, marine-service, or commercial-operation interfaces.
Read controlling sourceGCPI reviewed berthing, cargo handling, operating economics, and international partnerships. This confirms that physical assets had moved into operating preparation while final commercial responsibility and the operating model remained open.
Read controlling sourceThe port authority said the navigation channel and main berths had been prepared and first vessels received on trial lines, while infrastructure and land-sea connections were still being developed. Trial calls are not evidence of sustained commercial throughput.
Read controlling sourceGCPI marked completion of element placement and allowed a site walk-through, but its notice said service entry would follow in later project stages. Mechanical, electrical, safety, closure, testing, and operating acceptance therefore remain separate from structural placement.
Read controlling sourceGCPI reported the 23 km channel at 100%, 19.8 m final depth and 200 m width, the five berths at 100%, and the 2,000 m by 600 m container yard at 96.5%. These are package progress statements; they do not prove hydrographic acceptance, equipment handover, or commercial commissioning.
Read controlling sourceThe owner reported more than 11 million m3 of fill, PVD installation and surcharge work behind the five berths. The first area behind berths one and two had preliminary acceptance, showing that quay completion still depended on phased terminal formation and soil consolidation.
Read controlling sourceThe Prime Minister's office recorded handover of the five Daewoo-built berths and the first commercial vessel call. At the same event, the berths were described as the backbone of phase one rather than completion of the entire port system.
Read controlling sourceDaewoo E&C records a 15.952 km rubble-mound breakwater and Guinness recognition on 2 April 2020. The breakwater created the sheltered-water basis for the port but did not by itself establish navigable depth, berth or terminal readiness.
Read controlling sourceDelivery watch
Confirm terminal-A final handover and equipment readiness, immersed-tunnel commissioning, accepted basin and berth-pocket depths, tug and pilotage commissioning, and named commercial operating responsibility.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe owner and contractor record now separates physical progress from operating readiness. The five berths were handed over on 7 November 2024. By 19 June 2025, terminal-A filling was reported at 93%, with more than 11 million m3 placed and PVD ground improvement continuing. On 4 December 2025, the owner reported the 23 km navigation channel at 100% and 19.8 m final depth, the container yard at 96.5%, and the five berths at 100%. All immersed-tunnel elements were seated by 20 December, but the owner described later work before service entry. January 2026 material confirmed trial shipping calls and continued infrastructure preparation; March material kept operator selection, berthing, cargo handling, and partnership models under review. Daewoo E&C confirmed on 8 July 2026 that the 62 km connecting road had received GCPI's final Performance Certificate after construction and the defects period. That road certificate does not establish tunnel commissioning, terminal handover, accepted basin depths, or full commercial operation.
Phase: construction. Evidence reviewed: 15 July 2026.