Grand Faw's first operating system combines five handed-over container berths, a 23 km navigation channel reported complete to 19.8 m, terminal reclamation and ground improvement, twin breakwaters, an immersed road tunnel, and a 62 km connecting road that received its final GCPI Performance Certificate on 8 July 2026.
Project signal
Construction in Iraq
Current statusCore marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verificationSource confidenceConfirmed
Location
Iraq / Middle East
Segment
Port infrastructure
Status
Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification / Confirmed
Last checked
15 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
General Company for Ports of Iraq / Iraq Ministry of Transport
Delivery parties
Daewoo E&C, Technital
Contract route
Multiple GCPI and Ministry of Transport design, construction, supervision, and operating-readiness packages. No current primary procurement notice has been found for the separately reported remaining-pier bid.
Execution window
Five berths and the navigation channel are reported physically complete, all immersed-tunnel elements are seated, and the connecting road has final certification. Terminal, tunnel, navigation-safety, marine-service, and commercial-operating acceptance remain the decisive sequence; no reliable full-operation date or additional-pier package is established in the primary record.
Works package
Five container berths and terminal platform, navigation-channel and port-basin dredging, reclamation and filling, east and west breakwaters, a container terminal, connecting road, and immersed road tunnel.
Marine interfaces
The quay wall, berth pocket and basin, 23 km navigation channel, breakwater shelter, dredged-material and reclamation programme, tug and pilotage capability, terminal equipment, and landside tunnel-road connection must reach compatible readiness before sustained vessel operations can scale.
Commercial evidence boundary
The existing phase-one works point to near-term demand around commissioning, marine services, navigation safety, surveys, terminal systems, maintenance dredging, and interface management. Treat any additional-pier opportunity as unconfirmed until GCPI, the Ministry of Transport, or an official procurement channel publishes the package.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The 62 km connecting road received GCPI's final Performance Certificate
Daewoo E&C reported final completion approval after 45 months of construction and a one-year defects period. The certificate closes the road package, not the immersed-tunnel, terminal, navigation, marine-service, or commercial-operation interfaces.
The owner was still testing operating and partnership models
GCPI reviewed berthing, cargo handling, operating economics, and international partnerships. This confirms that physical assets had moved into operating preparation while final commercial responsibility and the operating model remained open.
Trial shipping calls began while full commercial operation remained a target
The port authority said the navigation channel and main berths had been prepared and first vessels received on trial lines, while infrastructure and land-sea connections were still being developed. Trial calls are not evidence of sustained commercial throughput.
All immersed-tunnel elements were seated beneath Khor Al-Zubair
GCPI marked completion of element placement and allowed a site walk-through, but its notice said service entry would follow in later project stages. Mechanical, electrical, safety, closure, testing, and operating acceptance therefore remain separate from structural placement.
The owner reported the navigation channel complete and the terminal yard at 96.5%
GCPI reported the 23 km channel at 100%, 19.8 m final depth and 200 m width, the five berths at 100%, and the 2,000 m by 600 m container yard at 96.5%. These are package progress statements; they do not prove hydrographic acceptance, equipment handover, or commercial commissioning.
Terminal-A filling reached 93% with ground improvement still active
The owner reported more than 11 million m3 of fill, PVD installation and surcharge work behind the five berths. The first area behind berths one and two had preliminary acceptance, showing that quay completion still depended on phased terminal formation and soil consolidation.
The Prime Minister's office recorded handover of the five Daewoo-built berths and the first commercial vessel call. At the same event, the berths were described as the backbone of phase one rather than completion of the entire port system.
The western breakwater was recognised as the world's longest breakwater
Daewoo E&C records a 15.952 km rubble-mound breakwater and Guinness recognition on 2 April 2020. The breakwater created the sheltered-water basis for the port but did not by itself establish navigable depth, berth or terminal readiness.