Project record
Singapore's Tuas Port Phase 2 combines 387 hectares of reclamation, a 9.1-kilometre seawall formed with 227 caissons, deep-water wharf development, progressive MPA-to-PSA land handover, and terminal construction. MPA's 2025 annual report puts reclamation at 79.5% as of December 2025 and records a March 2026 target for handing the first six completed berths to PSA; the report does not confirm that the handover occurred.
Singapore / Asia Pacific
Port infrastructure
Owner reports Phase 2 reclamation at 79.5% as of December 2025; its March 2026 target for handing six completed berths to PSA remains unverified, while current marine notices confirm active delivery / Confirmed
20 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Port Marine Notice 73 set 24-hour operations in two project-area work zones from 20 June to 19 December 2026 and superseded a 2025 notice. It confirms continuing construction logistics, not completed reclamation, accepted wharf geometry, or commercial terminal operation.
Read controlling sourcePort Marine Notice 43 extended the regulated works period from 26 March to 25 September 2026 and revised the work-area chart and craft list. The notice is activity and navigation-control evidence, not a construction-completion or acceptance certificate.
Read controlling sourceMPA's 2025 annual report advanced the aggregate reclamation measure and said the first six completed berths were targeted for handover to PSA in March 2026. It did not confirm handover, marine-civil acceptance, terminal readiness or operation.
Read controlling sourceMPA reported Phase 2 reclamation about 75% complete. Its accompanying statement that 11 Tuas Port berths were operational describes the wider port and cannot be reassigned to Phase 2; civil acceptance, handover, terminal systems, and Phase 2 commissioning remained separate.
Read controlling sourceMPA advanced the aggregate Phase 2 reclamation measure from the prior 60% record to about 70% and stated that reclamation was expected to finish in 2027. The forecast did not establish final caisson installation, accepted marine works, or terminal readiness.
Read controlling sourceMPA reported reclamation about 60% complete and kept Phase 1 completion and operations separate from Phase 2. This is an aggregate civil-progress baseline, not a berth, dredging, wharf or operating acceptance event.
Read controlling sourceMPA marked the first of 227 planned caissons entering the wharf and seawall sequence for the 387-hectare phase. A first installation demonstrated the method and work-front start but did not prove repeat cadence, full wall continuity, reclamation, or terminal delivery.
Read controlling sourceMPA's current programme timeline records physical reclamation commencement on 7 March 2018. This moves the record from award to execution while leaving caisson installation, dredging output, land formation, handover, and operation as later gates.
Read controlling sourceThe contractor identified the Penta-Ocean-Hyundai-Boskalis joint venture and a package covering reclamation, deep-water wharf, dredging, soil improvement and caisson works. The award fixed scope and counterparties, while mobilisation and accepted output remained ahead.
Read controlling sourceDelivery watch
Confirm whether the first six completed berths were handed to PSA in March 2026, then track final caisson and seawall installation, reclamation completion, marine-civil acceptance, PSA terminal construction and named berth commissioning.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerPenta-Ocean's 1 March 2018 award announcement identifies the joint venture with Hyundai Engineering & Construction and Boskalis and the reclamation, wharf, dredging, soil-improvement, and caisson scope. MPA's current programme timeline dates physical reclamation commencement to 7 March 2018, while its 25 April agreement record identifies a SGD 1.46 billion package, 387 hectares, 9.1 kilometres of caisson wall, and reuse of dredged material. MPA's 4 July 2019 record confirms installation of the first caisson. Owner factsheets then report approximately 60% completion in March 2023, 70% in March 2024, and 75% in January 2025. The 2024 annual report records all 227 caissons constructed, 185 installed, and land for the first five berths to be progressively handed to PSA. The 2025 annual report advances the aggregate reclamation measure to 79.5% as of December 2025 and says the first six completed berths were targeted for handover to PSA in March 2026; it does not state that handover occurred. Port Marine Notices 43 and 73 of 2026 establish continued work-zone and 24-hour bulk-carrier controls into September and December 2026. PSA's terminal sheet identifies Tuas Port as in progress. The 8.6-kilometre wharf figure and 9.1-kilometre seawall figure describe different measures. Final caisson installation, completed dredging, marine-civil acceptance, terminal-system readiness, named Phase 2 berth commissioning and Phase 2 capacity in service have not been reported.
Phase: delivery. Evidence reviewed: 20 July 2026.